36C24526B0003 0002.docx
DOCX document 39 KB Posted
- Solicitation number
- 36C24526B0003
About this file
This is Amendment/Modification #0002 to Solicitation 36C24526B0003 for the Halls and Walls construction project at the Louis A. Johnson VA Medical Center in Clarksburg, West Virginia. The amendment provides clarification, additional drawings, and testing reports in response to Requests for Information (RFIs) received from prospective bidders. The bid deadline is Wednesday, September 9, 2026 at 3:00 p.m., with public bid opening at the Contracting Office, 513 Rosebud Plaza, Clarksburg, WV 26301. Electronic submissions are not accepted. The project involves renovation work on the first and second floors of the Clinical Addition, including ceiling work, wall protection, flooring, HVAC modifications, and painting. The contract period of performance is 210 calendar days as established in the SF-1442, with phased work requirements restricting second-floor activities to after normal business hours (Monday-Thursday 4 p.m. to 6 a.m. and Friday 4 p.m. through Monday 6 a.m.) except for specific handrail, corner guard, cove base, and wall protection work that may occur during normal business hours.
The amendment addresses 19 RFI responses covering bid structure clarification (Base Bid with two deduct alternates), scope revisions in the second-floor service elevator bay, asbestos abatement specifications (no known ACM present; contractors responsible for sampling), ICRA containment and infection control requirements, HVAC ductwork cleaning limitations (restricted to disturbed ductwork only), finish specifications updates, and material storage area identification. Key deliverables include updated CAD and PDF floor plans, architectural scaled drawings (36" x 48"), revised specifications (Divisions 01-10 including Sections 02 82 11, 05 50 00, 09 06 00, and 09 51 00), ductwork plans, asbestos survey reports from 1995, and detailed ICRA Class I-IV control measures requiring negative pressurization monitoring at 0.01 inches water gauge, HEPA filtration, differential pressure sensing devices, and dust containment protocols. The Department of Veterans Affairs Veterans Health Administration issued this solicitation through the Louis A. Johnson VAMC Contracting Office (90C and 19ACQ).
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER
IS ISSUED
PURSUANT TO:
Specify authority)
THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT
ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office , appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 08-31-2026 540-26-110 Department of Veterans Affairs Louis A Johnson, VAMC Contracting Office (90C) 1 Med Center DR Clarksburg WV 26301-4199
19ACQ
Department of Veterans Affairs Louis A Johnson, VAMC Contracting Office (19ACQ) 1 Med Center DR Clarksburg WV 26301-4199 To all Offerors/Bidders
36C24526B0003 08-07-2026
X X X The intent of this amendment to the solicitation for the Halls and Walls Project is to provide clarification, additional drawings and testing reports in response to the RFI's that were received.
All bids are due by Wednesday, September 9, at 3:00 p.m. at which time a public bid opening will be conducted at the Contracting Offices at 513 Rosebud Plaza, Clarksburg, WV 26301. Electronic submissions will not be accepted.
All other terms and conditions remain unchanged.
Rebecca Besten Contracting Officer
VA-VHA-RPOE-2022-23571
CONTINUATION PAGE
Solicitation: 36C24526B0003 Project#: 540-26-110 – Halls and Walls
SUMMARY OF CHANGES:
Summary of changes/additions of Addendum #2:
A. 1st and 2nd Floor LAJ VAMC unedited CAD/PDF files in response to RFI #10 B. Architectural Size E 36” x 48” scaled dwg A03 and A09 in response to RFI #10 C. Update to SOW within 2nd floor service elevator bay Dwg A09 and A13 in response to RFI #3 D. Specification Section 05 50 00 Metal Fabrications included in response to RFI #13 E. Specification Section 10 26 00 Wall and Door Protection shifted from Word Specification document 1 of 2 to 2 due to size limitations F. Specification Section 09 22 16 Non-Structural Metal Framing formatting corrections G. Dwg A24 Floor Transitions and Expansion Joint Details added in response to RFI #13 H. Dwg 1-H45 First Floor Addition Ductwork Plan included in response to RFI #17
Responses to Questions Received and Clarifications
1. QUESTION: The asbestos abatement specification 02 28 11 does not provide quantities, Please provide quantities.
VA RESPONSE: No known ACM is present within the work areas. Specification Sections 02 82 11 Traditional Asbestos Abatement and 02 82 13.19 Asbestos Floor Tile and Mastic Abatement are included in-case-of positive ACM sampling and are not expected to be applicable to this contract. A 1995 Survey of Building 1 is included with Addendum #1. No ACM survey has occurred on the 1st or 2nd floor of the Clinical Addition. Contractors are responsible for sampling each unique material to be demolished. The contracted Industrial Hygienist is responsible for determining exact sampling location and quantity. Please note that any incidental abatement necessary as resultant from the ACM survey shall be handled via change order, as dictated by SOW section 2.d.
2. QUESTION: Please clarify the following:
a. Bid Item 1 – Base bid includes all ceiling work
b. Bid Item 2 – Bid Deduct Alt. 1 deducts all acoustical ceiling and related work on first floor.
c. Bid Item 2 – Bid Deduct Alt. 2 deducts all work related to the phenolic vaulted ceiling in the ER waiting room
VA RESPONSE:
This is correct, with the exception that the question above should have reflected that item c is bid item #3 as outlined in the solicitation.
Base bid, Item I, includes all work listed in the SOW, including Item II, General Construction – Bid Deduct (Alternate) #1, and Item III, Delegated Design and General Construction – Bid Deduct (Alternate) #2. Bid Item II deducts all acoustical ceiling, related mechanical diffuser/intake/grille, and luminaire work on the first floor other than the acoustical ceiling work within the vaulted ceiling area of the ER waiting room (i.e. work listed in Bid Item III). Bid Item III deducts all work related to phenolic vaulted ceiling in the ER waiting room.
3. QUESTION: At the pre-bid site visit, the COR advised that the scope near the second-floor elevators would be revised, including retaining existing wall tile and revising the handrail and bumper/crash guard work. Please provide a revised scope and drawings identifying the work to be performed in this area.
VA RESPONSE: Impacts A09 and A13 (2nd floor Service Elevator Bay), updates to drawings included in Addendum #1. Specified handrail to be installed as crash rail approximately 8” on-center AFF in-place-of existing resilient crash rail. Install new resilient cove base as specified. Existing wall tile to remain as-is; no wall-covering installed or paint in this area.
4. QUESTION: The Statement of Bid Items in Specification 01 00 00 does not correspond with the price/cost schedule, Statement of Work, Specification Section 09 51 00 or the drawings. Please clarify the intended bid item and deduct alternate structure and revise Section 01 00 00 accordingly.
VA RESPONSE: Bid items and deduct-alternate structure are as listed in the Statement of Work (SOW) and drawings. Division 01 00 00 General Specifications has been updated to reflect the language in SOW and drawing set.
5. QUESTION: The SF1442 establishes a 210 calendar day period of performance, while Specification Section 01 00 00 identifies a 360 calendar day period of performance. Please confirm the contractual period of performance.
VA RESPONSE: Period of Performance is as listed in the SF-1442, 210 calendar days. Division 01 00 00 General Specifications has been updated to reflect the POP in specifications.
6. QUESTION: Section 01 35 26 requires a full-time SSHP for each shift, with no other duties, who is separate from the Superintendent and CQC System Manager. Please confirm that a separate, dedicated SSHO is required to be on site during all construction activities.
VA RESPONSE: A separate Site Safety and Health Officer (SSHO) is not required; the superintendent may be the SSHO.
7. QUESTION: Please identify any required phasing, maximum work-area limitations, corridor-access requirement, or sequencing restriction applicable to the second-floor work.
VA RESPONSE: Handrail, corner guard, cove base, wall protection, and painting demolition/installation depicted on Dwg A10, to plan left of Stair C on A11, and to plan right of service elevators on A13 may occur during normal business hours. All other work shall be accomplished after normal weekday business hours (Monday-Thursday 4pm – 6am) or on the long weekends (Friday 4pm – Monday 6am, may be extended during federal holidays). Do not demolish what cannot be re-installed during the same work period (the long-weekends are 1 singular work period).
8. QUESTION: Please confirm the allowable construction work hours for the project, including which activities may be performed during normal facility operational hours and which are required to be performed during off-hours. Specifically, please confirm that ICRA Class I and II activities may be performed during normal facility operational hours, and that Class III and IV activities are required to be performed during the off-hour periods identified in the solicitation.
VA RESPONSE: For the first-floor ED waiting area: Work may only be performed during normal weekday operational hours if work is performed behind hard ICRA barriers; Erection and Demolition of hard ICRA barriers shall occur after normal weekday business hours or on the long weekends. Otherwise, refer to RFI #7.
9. QUESTION: Please identify the area(s), if any, that will be made available to the Contractor for material storage and staging.
VA RESPONSE: Area(s) available for material laydown, storage, and/or staging is dependent on amount of material and duration of material staging. Potential areas include, but are not limited to, B243, B204, 2134, 2100A, 2183, 4C469, and 4B48.
10. QUESTION: Are scaled drawings available for bidding? Please also confirm whether the square-foot quantities shown on the drawings represent floor area or wall surface area.
VA RESPONSE: Yes, 1st and 2nd floor scaled CAD and PDF files are provided in this amendment. Architectural Size E 36” x 48” scaled drawings A03 and A13 are also included in Addendum #2.
Square footage relates to the floor area.
11. QUESTION: For work classified as ICRA Class III, please confirm whether temporary plastic barriers are acceptable or hard-wall barriers are required. If hard-wall barriers are required, please confirm whether they must extend to the deck above.
VA RESPONSE: ICRA Class III work is associated with the control measures below:
1. Perform work activity in a manner that does not create dust.
2. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.
3. Any materials and equipment being brought into the facility must be free of contaminants and loose material.
4. Provide active means to control airborne dust from dispersing into occupied areas and/or water mist surface to control dust (e.g., Mobile Dust Containment Cart or some other system).
5. Ensure worker clothing is clean and free of visible dust before leaving the work area.
| 6. | Remove or isolate air diffusers (supply and return) to protect the HVAC system from dust and reduce air turbulence. Rebalance system to address diffuser isolation. | ||
| 7. | When the work involves or impacts potable water systems including | stagnation due to reduced usage, the piping shall be flushed twice a week | or isolated from the main system. |
8. Seal doors to prevent dust migration.
9. Contain all trash and debris in the work area. Perform daily cleaning and disposal of trash (covered) from work area using an identified exit route.
10. Any equipment, tools, or materials removed from the work area must be in sealed containers and/or cleaned of dust and debris prior to removal from the area.
11. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.
12. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.
| 13. | Maintain clean surroundings when area is not contained by damp mopping or HEPA vacuuming surfaces at least daily. |
| 14. | Ensure availability of equipment for cleaning hands. |
15. Construct and complete critical barriers meeting NFPA 241 requirements. Barriers must extend to the ceiling or if ceiling tile is removed, to the deck above.
16. All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to floor and ceiling (or floor/roof deck above) and secure from movement or damage.
17. Seal all penetrations in containment barriers, including floors and ceiling, using approved materials (UL schedule firestop if applicable for barrier type).
18. Maintain .01 inches /water gauge negative pressurization of the entire workspace by use of HEPA exhaust air systems directed outdoors or comply with the alternative method outlined in Appendix A of VHA ICRA 1.4 (April 2026). These control measures must be maintained continuously 24/7 for the duration of the project. HEPA filtered exhaust if discharged directly to the outdoors must be at a distance of 25 feet or greater from entrances, air intakes and operable windows. Exhausting discharged air into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is prohibited.
19. Install a differential pressure sensing device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor and document negative pressurization. The "ball in the wall" or similar apparatus are not acceptable.
12. QUESTION: Sections 02 82 11 and 02 82 13.19 reference asbestos containing materials and estimated quantities, but no project specific asbestos quantities or survey have been provided. Please provide any existing asbestos/hazardous material survey or testing information applicable to the project and confirm whether any known ACM is present within the work areas.
VA RESPONSE: No known ACM is present within the work areas. Specification Sections 02 82 11 Traditional Asbestos Abatement and 02 82 13.19 Asbestos Floor Tile and Mastic Abatement are included in-case-of positive ACM sampling and are not expected to be applicable to this contract. A 1995 Survey of Building 1 is included with Addendum #1. No ACM survey has occurred on the 1st or 2nd floor of the Clinical Addition. Contractors are responsible for sampling each unique material to be demolished. The contracted Industrial Hygienist is responsible for determining exact sampling location and quantity. Please note that any incidental abatement necessary as resultant from the ACM survey shall be handled via change order, as dictated by SOW section 2.d.
13. QUESTION: The specifications appear to contain missing pages and/or specification sections. Please provide the following specification sections/pages:
a. Complete Section 02 83 33.13
b. Section 05 50 00
c. Section 06 20 00
VA RESPONSE: Specification Section 02 83 33.13 Lead Paint Removal is not missing pages or specification subsections. Specification Section 05 50 00 Metal Fabrications is included in Addendum #1. Specification Section 06 20 00 Finish Carpentry is not applicable to this project and references to this specification section have been removed in the addended specifications.
14. QUESTION: Specification Section 09 06 00, Schedule of Finishes, contains numerous blank finish, color, manufacturer, and project fields. Please provide project-specific finish selections required for bidding.
VA RESPONSE: Specification Section 09 06 00 Schedule for Finishes has been updated to include various Basis of Design. Refer to individual specification sections for more detailed product requirements.
15. QUESTION: Specification Section 09 51 00 identifies the acoustical wood ceiling work as “Delegated Design”. Please clarify the extent of delegated design required, including whether signed and sealed drawings and/or calculations by registered design professional are required.
VA RESPONSE: Signed and sealed drawings by a registered design professional are not required. The reference to “Delegated Design” as it relates to the acoustical wood ceiling work refers to the contractor’s discretion in selection and submission of architecturally integrated wood ceiling and lighting assembly other than the basis of design; selection and submission of an integrated system that adequately fits the space is responsibility of the contractor through careful coordination and communication of vaulted space dimensions with the selected suspension assembly manufacturer(s). Contractor shall submit selected product(s) with detailed layout of installation spacing location intention.
16. QUESTION: Drawing A01, General Project Note 12, requires all finished drywall to receive a Level 5 finish. Please confirm that this requirement applies to all existing drywall surfaces within the project limits that are to be refinished and painted.
VA RESPONSE: Note 12 on A01 General Project Notes requires all drywall to receive a Level V finish unless otherwise accepted by the Contracting Officer’s representative (COR). This note relates only to all walls receiving new joint compound within the scope of this project. New joint compound and sanding is not required on all walls within the scope of this project; only where necessary, e.g. if the existing wall finish is cracked, chipped, or otherwise damaged as determined by the COR. Please note that the vaulted skylight over the 1st Floor Lobby/ED waiting area, depicted in photograph 14 of A19, is not within the scope of this project.
17. QUESTION: The Statement of Work requires the Contractor to professionally clean all ductwork, diffusers, intakes, filters, and grilles disturbed throughout the course of project work. Please provide HVAC drawings identifying the existing systems serving the project areas and clarify the limits of required duct cleaning, including whether cleaning is limited to ductwork directly disturbed by the work or extends to the full associated supply and return duct systems.
VA RESPONSE: Original First Floor Clinical Addition Ductwork Plan dwg 1-H45 is included in addendum #1. Ductwork cleaning is limited to ductwork directly disturbed by the work within the scope of this project. Contractors may install manual dampers within ductwork just upstream from ductwork within scope to restrict airflow to complete mechanical work. Should a contractor install a manual damper, or close an existing damper, at the onset of mechanical work, ductwork cleaning would be restricted to all mechanical work/equipment downstream of said damper.
18. QUESTION: Please confirm whether HVAC cleaning is limited to ductwork, diffusers, intakes intakes, filters, and grilles disturbed by the project, or whether cleaning of associated HVAC equipment and components, including VAV boxes, reheat coils, air-handling equipment, or other components, is also required.
VA RESPONSE: Please refer to response provided in RFI 17.
19. QUESTION: May the required HVAC duct cleaning be performed after completion of the associated construction work rather than on a phase-by-phase basis, to minimize repeated HVAC shutdowns and potential recontamination of previously cleaned ductwork?
VA RESPONSE: Please refer to response provided in RFI 17.
36C24526B0003 Construction – Halls and Walls Project
ATTACHMENTS:
See attached document: 053 1 H45 First Floor Addition Ductwork Plan.
See attached document: A03 ARCH E 36 x 48.
See attached document: A13 ARCH E 36 x 48.
See attached document: VAMC 540-26-110 Specifications- revised.
See attached document: AD1 A09.
See attached document: AD1 A13.
See attached document: AD1 A24.
See attached document: First Floor_8-13-26.
See attached document: Second Floor_10-25-22.
See attached document: VAMC 540-26-110 Specifications Div 0-9.
See attached document: VAMC 540-26-110 Specifications Div 10 23-26.
See attached document: 1995 Survey - Overview.
See attached document: 1995 Survey - Building 1.
See attached document: 1995 Survey - Lab Results.