This document is an excerpt from VHA Directive 1810 Appendix A, which outlines requirements for two valve isolation on steam systems during maintenance and construction work. The contractor is required to ensure that two isolation valves are supplied and installed in all high pressure steam (HPS), medium pressure steam (MPS), and low pressure steam (LPS) piping that is 2 inches or larger, as well as hot water systems where the temperature is 257 degrees Fahrenheit or greater.

The document is related to Federal Contract Opportunity ID 402ce44f72ad45e5b5d7bb9a7d0742bf, Solicitation Number 36C24424R0001, for the Replace Steam System project at the Altoona VAMC. The contract will be a single, firm fixed-price construction services contract with a period of performance of 720 calendar days. The project will be competed under a tiered evaluation, with service-disabled veteran-owned small businesses (SDVOSBs) and veteran-owned small businesses (VOSBs) receiving priority consideration. The North American Industry Classification System (NAICS) code is 236220 Commercial & Institutional Building & Construction, with a small business size standard of $45 million in annual receipts.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--NRM | 503-19-112 Replace Steam System Project (VA-24-00009779), newest first.
File Type Posted
36C24424R0001 0004_1 10-23-24.pdf PDF
36C24424R0001 0004 10-23-24.pdf PDF
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation 36C24424R0001 10-11-24.pdf PDF
36C24424R0001 0003 10-11-24.pdf PDF
36C24424R0001 0003_1.pdf PDF
EXHIBIT E - Past Performance Questionnaire 36C24424R0001 _ Replace Steam System 10-11-24.pdf PDF
SCHEDULE Line Item replace steam system w alternate 10-11-24.pdf PDF
36C24424R0001 0002 10-8-24.pdf PDF
PN 503-19-112 100PCT Drawings.pdf PDF
Justification-MPT-SAT 01-Apollo Conbraco Ball Valves_Redacted.pdf PDF
Justification MPT-SAT-02-Bettwy Systems_Redacted.pdf PDF
Bid RFIs 12.6.23 - 503-19-112 Replace Steam Project.pdf PDF
P03 Sole Source BNOE 503-19-112 Repalce Steam System.pdf PDF
Cast Iron Operational Alert VHA 121621.pdf PDF
VA Directive 1810.pdf PDF
Justification MPT-SAT 03-Trane Tracer Ensemble_Redacted.pdf PDF
Bid RFIs - 503-19-112 Replace Steam Project - Dec. 2023.pdf PDF
PN 503-19-112 100PCT Specifications.pdf PDF
General Decision Number PA20240002 08-16-2024.pdf PDF
Water Safety Plan Requirements 11.22.2021.pdf PDF
36C24424R0001 0002_1 10-8-2024.pdf PDF
PN 503-19-112 100PCT ACM Specs and Survey.pdf PDF
36C24424R0001 0001 1-18-24.pdf PDF
36C24424R0001_3.pdf PDF
EXHIBIT E - Past Performance Questionnaire 36C24424R0001 _ Replace Steam System.pdf PDF
PM-Part808-405-6 Atch1 Limiting Sources Justification MPT-SAT 03-Trane Tracer Ensemble (s) 10-2-23_Redacted (s).pdf PDF
503-19-112 -CD- Drawings_Part1.pdf PDF
503-19-112 - CD - Specifications.pdf PDF
36C24424R0001 12-8-23.pdf PDF
36C24424R0001_2.docx DOCX document
Bid RFIs - 503-19-112 Replace Steam Project.pdf PDF
EXHIBIT B - Subcontractor Information and Consent Form 36C24424R0001 _ Replace Steam System.pdf PDF
EXHIBIT A - Past Performance Relevancy Questionnaire 36C24424R0001 _ Replace Steam System.pdf PDF
503-19-112 -CD- Drawings_Part3.pdf PDF
PM-Part808-405-6-Atch1-Limiting Sources Justification MPT-SAT 04 Viking Sprinkler Heads (s) 10-2-23_Redacted(s).pdf PDF
PM-Part808-405-6 - Atch1MPT-SAT 01-Apollo Conbraco Ball Valves (s) 10-2-23_Redacted (s).pdf PDF
PM-Part808-405-6 Atch1 Limiting Sources Justification MPT-SAT-02-Bettwy Systems (s) 10-2-23_Redacted(s).pdf PDF
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation 36C24424R0001 _ Replace Steam System.pdf PDF
503-19-112 -CD- Drawings_Part2.pdf PDF
36C24424R0001_1 11-16-23.pdf PDF
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Two Valve Isolation Per VA Directive 1810 Appendix A, 3.F

Please note that the contractor is to ensure two isolation valves are supplied and installed in all HPS, MPS and LPS steam piping per the below description in VHA Directive 1810 Appendix A, 3.F

“Any time maintenance and construction work is performed on steam systems, two valve isolation is required (closed position) in series between the steam and the work being performed. This applies to all HP steam as well as LP steam lines 2 inches or larger and hot water systems where the temperature of the operating fluid is at or greater than 257 degrees Fahrenheit.”