This document outlines the Water Safety Plan requirements for a federal construction contract. The plan must address installer qualifications, temporary service connections, delivery and storage of materials, installation procedures, post-installation procedures, and temperature requirements for the water system. Key requirements include submitting and annually updating the Water Safety Plan, ensuring proper separation and backflow prevention at the water connection, protecting and cleaning piping before installation, avoiding dead legs and carbon filters, flushing and disinfecting new piping, and maintaining specific hot and cold water temperatures throughout the system. The document references relevant master specifications that must be followed.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--NRM | 503-19-112 Replace Steam System Project (VA-24-00009779), newest first.
File Type Posted
36C24424R0001 0004 10-23-24.pdf PDF
36C24424R0001 0004_1 10-23-24.pdf PDF
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation 36C24424R0001 10-11-24.pdf PDF
36C24424R0001 0003 10-11-24.pdf PDF
36C24424R0001 0003_1.pdf PDF
EXHIBIT E - Past Performance Questionnaire 36C24424R0001 _ Replace Steam System 10-11-24.pdf PDF
SCHEDULE Line Item replace steam system w alternate 10-11-24.pdf PDF
36C24424R0001 0002 10-8-24.pdf PDF
Bid RFIs 12.6.23 - 503-19-112 Replace Steam Project.pdf PDF
P03 Sole Source BNOE 503-19-112 Repalce Steam System.pdf PDF
Cast Iron Operational Alert VHA 121621.pdf PDF
VA Directive 1810.pdf PDF
Justification MPT-SAT 03-Trane Tracer Ensemble_Redacted.pdf PDF
Bid RFIs - 503-19-112 Replace Steam Project - Dec. 2023.pdf PDF
PN 503-19-112 100PCT Specifications.pdf PDF
General Decision Number PA20240002 08-16-2024.pdf PDF
36C24424R0001 0002_1 10-8-2024.pdf PDF
PN 503-19-112 100PCT ACM Specs and Survey.pdf PDF
PN 503-19-112 100PCT Drawings.pdf PDF
Justification-MPT-SAT 01-Apollo Conbraco Ball Valves_Redacted.pdf PDF
Justification MPT-SAT-02-Bettwy Systems_Redacted.pdf PDF
Two Valve Isolation Per VA Directive 1810 Appendix A.pdf PDF
36C24424R0001_3.pdf PDF
36C24424R0001 0001 1-18-24.pdf PDF
Bid RFIs - 503-19-112 Replace Steam Project.pdf PDF
EXHIBIT B - Subcontractor Information and Consent Form 36C24424R0001 _ Replace Steam System.pdf PDF
EXHIBIT A - Past Performance Relevancy Questionnaire 36C24424R0001 _ Replace Steam System.pdf PDF
503-19-112 -CD- Drawings_Part3.pdf PDF
PM-Part808-405-6-Atch1-Limiting Sources Justification MPT-SAT 04 Viking Sprinkler Heads (s) 10-2-23_Redacted(s).pdf PDF
PM-Part808-405-6 - Atch1MPT-SAT 01-Apollo Conbraco Ball Valves (s) 10-2-23_Redacted (s).pdf PDF
PM-Part808-405-6 Atch1 Limiting Sources Justification MPT-SAT-02-Bettwy Systems (s) 10-2-23_Redacted(s).pdf PDF
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation 36C24424R0001 _ Replace Steam System.pdf PDF
503-19-112 -CD- Drawings_Part2.pdf PDF
36C24424R0001_1 11-16-23.pdf PDF
EXHIBIT E - Past Performance Questionnaire 36C24424R0001 _ Replace Steam System.pdf PDF
PM-Part808-405-6 Atch1 Limiting Sources Justification MPT-SAT 03-Trane Tracer Ensemble (s) 10-2-23_Redacted (s).pdf PDF
503-19-112 -CD- Drawings_Part1.pdf PDF
503-19-112 - CD - Specifications.pdf PDF
36C24424R0001 12-8-23.pdf PDF
36C24424R0001_2.docx DOCX document
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Water Safety

A) Water Safety Plan: Establish and maintain a site-specific water safety plan. The intent of the Water Safety Plan is to include all water uses

(potable and non-potable). Prior to start of work, prepare a plan detailing site-specific water safety measures and submit to the

Contracting Officer Representative (COR) for review for compliance with contract requirements in accordance with the Master Specifications, Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA AND SAMPLES. Master

Specifications can be found at http://www.cfm.va.gov/TIL/spec.asp.

B) The Water Safety Plan Submission:

1. Shall be submitted, reviewed and approved prior to commencing construction.

2. Shall be resubmitted annually for review and approval in the event a contract extends more than a year.

C) At a minimum, the water safety plan shall address installer experience, license, and certifications, temporary service connections, delivery and storage of domestic water materials, installation procedures, post installation procedures, and a general knowledge in VA temperature requirements to make certain proper auxiliary equipment such as thermometers, anti-scald devices, and mixing valves are installed.

D) Installer Qualifications

1. Tradesman skilled in the appropriate trade shall be provided.

2. Provide installers appropriate license.

3. Provide evidence of the successful completion of at least five projects of equal or greater size and complexity.

4. Provide additional qualifications or continuing education.

E) Temporary service connections, Pre-Construction, Delivery, and Storage

1. Although the VA allows for use of domestic water during construction, it must be ensured that proper separation is in place at the point of connection via a backflow device.

2. Water lines and equipment shall be capped/covered when delivered to the site and kept capped until installation. They shall be protected and cleaned (inside and outside) before placing in operation.

3. Existing equipment and piping being worked on by the contractor shall be under the custody and responsibility of the contractor and shall be protected as required for new work.

4. Reference Master Specifications 22 05 11 Delivery, Storage, and

Handling.

F) Risk Assessment

1. Ensure the infection control risk assessment is conducted with Facility stakeholders to address the potential impact of construction and maintenance of water systems on growth or transmission of waterborne pathogens and commissioning requirements.

G) Installation

1. Reference Master Specifications 22 05 11 Cleanliness of Piping and

Equipment Systems.

2. Ream all pipe ends to remove burrs. Burrs can trap sediment and cause corrosion.

3. Aerators shall not be installed on faucets. Reference Master

Specifications 22 40 00.

4. Dead legs are considered a length of pipe two pipe diameters from the branch, riser or main with one end open to the system and the other end terminating at a cap, blind flange or closed valve. Dead legs shall not be installed on the system without COR approval.

5. Carbon filters shall not be installed on the system.

6. Avoid running fire sprinkler piping above ductwork.

7. Water lines shall be run at a slight fall to make drainage of the system easier and reduce air locks. Drain valves shall be provided at all low points in the system and traps in the hot water circulating lines shall be avoided.

8. Connect branch lines at the bottom of mains serving fixtures and pitch the lines down so that the main may be drained through the fixture. Connect branch lines to top of main serving only fixtures located on the floor above.

9. All water lines shall be insulated per the specifications.

10. Avoid running ice machine supply lines near source of heat such as the compressor.

11. All water line shutdowns shall be scheduled with the COR.

12. Remove unused piping (e.g. dead legs left as a result of removing equipment such as water heaters, sinks, or showers). To minimize stagnant water, the lines should be cut and capped where they tee into the main, if feasible, or at the last accessible point of flow.

13. Properly balance water circulation system.

H) Post installation

1. Hydrostatically pressure test per Master Specifications 22 11 00.

Once testing is complete the lines shall either be drained or have proper separation from the main domestic water connection.

2. Remove piping installed for leak testing.

3. Flush lines with clean potable water until dirty water does not appear at the points of outlet. This shall also include any parts of existing systems that have been altered, extended, or repaired.

4. Disinfect water lines per procedures outlined in specifications, International Plumbing Code (IPC) and American Water Association

(AWA) C651. Newly installed water piping, equipment, and distribution system components that had been disinfected but not put into use within a week of the action must be disinfected again prior to building occupancy due to stagnation of water in the system.

5. Conduct Bacterial testing and water quality testing as required by the COR/Engineer.

6. Once sterilization has occurred daily flushing of the system and every fixture must be conducted and documented until turnover of the project. COR/Engineer will keep documentation of flushing and disinfection for at least 3 years.

7. Equipment must be commissioned to ensure operation meets the design intent and documentation retained for at least 3 years.

I) Temperature Requirements

1. Tank type hot water heaters shall heat the water to a minimum of 140 degrees Fahrenheit.

2. Instantaneous or semi-instantaneous hot water heaters must heat the water to a minimum of 130 degrees Fahrenheit.

3. Circulation loops in the hot water system must be maintained throughout the system at 124 degrees Fahrenheit.

4. Cold water should be at or below 67 degrees Fahrenheit to the greatest extent possible.

5. Master thermostatic mixing valves shall be installed to temper water distribution from the hot water source and shall comply with the IPC and ASSE 1017.

6. General use showers and sinks, as well as immersion tubs, must not exceed a water discharge above 110 degrees Fahrenheit and have combination balanced-pressure/thermostatic valves meeting the IPC and ASSE 1016 (Tubs and showers) and ASSE 1070 (sinks and lavatories).

7. Emergency showers and eye wash stations must maintain temperatures between 60 degrees Fahrenheit and 100 degrees Fahrenheit and have anti scald protection meeting the IPC and ASSE 1071.

8. Verify temperatures with a calibrated thermometer.