Bid RFIs - 503-19-112 Replace Steam Project.pdf

PDF 140 KB Posted

Attached to
Z1DA--NRM | 503-19-112 Replace Steam System Project (VA-24-00009779) Federal contract opportunity
Solicitation number
36C24424R0001
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4

About this file

This document contains questions and answers regarding a request for information (RFI) for a project to replace an existing steam system at a Department of Veterans Affairs medical center. Key details include: the project involves replacing medium and low pressure steam piping and installing new radiant ceiling panels throughout the facility; contractors must allow for relocating up to 200 linear feet each of electrical/data conduit, hydronic piping, and sanitary/vent piping due to potential interferences; the facility must remain operational 24/7 which may require weekend work; sterilizers have a maximum downtime of 4 hours but the VA will allow longer shutdowns on weekends to facilitate work; and anchors for steam piping will be floor penetrations or as indicated on drawings per the legend.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--NRM | 503-19-112 Replace Steam System Project (VA-24-00009779), newest first.
File Type Posted
36C24424R0001 0004 10-23-24.pdf PDF
36C24424R0001 0004_1 10-23-24.pdf PDF
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation 36C24424R0001 10-11-24.pdf PDF
36C24424R0001 0003 10-11-24.pdf PDF
36C24424R0001 0003_1.pdf PDF
EXHIBIT E - Past Performance Questionnaire 36C24424R0001 _ Replace Steam System 10-11-24.pdf PDF
SCHEDULE Line Item replace steam system w alternate 10-11-24.pdf PDF
36C24424R0001 0002 10-8-24.pdf PDF
Bid RFIs 12.6.23 - 503-19-112 Replace Steam Project.pdf PDF
P03 Sole Source BNOE 503-19-112 Repalce Steam System.pdf PDF
Cast Iron Operational Alert VHA 121621.pdf PDF
VA Directive 1810.pdf PDF
Justification MPT-SAT 03-Trane Tracer Ensemble_Redacted.pdf PDF
Bid RFIs - 503-19-112 Replace Steam Project - Dec. 2023.pdf PDF
PN 503-19-112 100PCT Specifications.pdf PDF
General Decision Number PA20240002 08-16-2024.pdf PDF
Water Safety Plan Requirements 11.22.2021.pdf PDF
36C24424R0001 0002_1 10-8-2024.pdf PDF
PN 503-19-112 100PCT ACM Specs and Survey.pdf PDF
PN 503-19-112 100PCT Drawings.pdf PDF
Justification-MPT-SAT 01-Apollo Conbraco Ball Valves_Redacted.pdf PDF
Justification MPT-SAT-02-Bettwy Systems_Redacted.pdf PDF
Two Valve Isolation Per VA Directive 1810 Appendix A.pdf PDF
36C24424R0001_3.pdf PDF
36C24424R0001 0001 1-18-24.pdf PDF
EXHIBIT B - Subcontractor Information and Consent Form 36C24424R0001 _ Replace Steam System.pdf PDF
EXHIBIT A - Past Performance Relevancy Questionnaire 36C24424R0001 _ Replace Steam System.pdf PDF
503-19-112 -CD- Drawings_Part3.pdf PDF
PM-Part808-405-6-Atch1-Limiting Sources Justification MPT-SAT 04 Viking Sprinkler Heads (s) 10-2-23_Redacted(s).pdf PDF
PM-Part808-405-6 - Atch1MPT-SAT 01-Apollo Conbraco Ball Valves (s) 10-2-23_Redacted (s).pdf PDF
PM-Part808-405-6 Atch1 Limiting Sources Justification MPT-SAT-02-Bettwy Systems (s) 10-2-23_Redacted(s).pdf PDF
EXHIBIT D - Sample Transmittal Letter for Past Performance Evaluation 36C24424R0001 _ Replace Steam System.pdf PDF
503-19-112 -CD- Drawings_Part2.pdf PDF
36C24424R0001_1 11-16-23.pdf PDF
EXHIBIT E - Past Performance Questionnaire 36C24424R0001 _ Replace Steam System.pdf PDF
PM-Part808-405-6 Atch1 Limiting Sources Justification MPT-SAT 03-Trane Tracer Ensemble (s) 10-2-23_Redacted (s).pdf PDF
503-19-112 -CD- Drawings_Part1.pdf PDF
503-19-112 - CD - Specifications.pdf PDF
36C24424R0001 12-8-23.pdf PDF
36C24424R0001_2.docx DOCX document
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

# Question AE Answer VA Final Answer 1 1. The pipe insulation required by

Specification Section 23 07 11 is very likely much thicker than the existing insulation.

a. Have provisions been made to physically fit the new thicker pipe insulation in the same spaces as the existing?

Intent is for new piping to follow pathways of existing piping. However, routing on plans is generally diagrammatic to show design intent. Refer to specification 23 22 13 paragraph 3.1.B.

Concur with AE Response.

2 2. If the existing piping is not pitched per the specification requirements will the new piping have to be?

a. If yes, who will be responsible for utility relocations and potential ceiling height adjustments?

New piping shall be pitched per specifications. Steam may be drip-trapped and re-lifted where necessary to maintain elevation. Coordinate starting heights to stay above ceiling and allow for offsets as required to avoid interferences. Refer also to specification 23 22 13 paragraph 3.1.B. Where interferences are otherwise unavoidable without lifting condensate, relocate conflicting utilities as required. Allow in bid for up to 200 LF of electrical/data conduit relocations and 100 LF of air duct offsets as needed.

Concur with AE Response. In addition, relocations, and adjustments to be made by contractor.

3 3. It appears duct modifications may be required for many existing air terminal units to tie in the new slot diffusers.

a. Are any utilities going to need to be relocated?

b. Is there physical space to fit the new ductwork?

c. Who is responsible for utility relocation?

d. What are the required duct sizes?

i. Detail indicates branch runouts are to match diffuser neck sizes; however, there are multiple branch runouts on single ducts with no size listed.

Refer to specification 23 31 00 paragraph 3.1.B. New branches serving 1 new LSD-1: 6” dia; 2 new LSD-1:

8” dia; 3 new LSD-1: 10” dia. Equivalent rectangular sizes are acceptable for new branches serving multiple diffusers. Individual 6” runouts from existing main are acceptable, as conditions allow, at contractor’s option.

Concur with AE Response. In addition, relocations, and adjustments to be made by contractor.

4 4. It appears the piping is required to be replaced thru the existing ceilings.

a. Who is responsible for any utilities/equipment that must be relocated for this work to take place?

Refer to question 2 Concur with AE Response. Relocations, and adjustments to be made by contractor. In addition to allowances in question 2 response (by AE), allow in bid for 200 LF of hydronic piping relocations and 200 LF of sanitary/vent relocations as needed.

5 5. Previous experience tells us there will be existing steam valves that will not close properly.

a. Who is responsible for replacing non-functional existing valves?

Intent is to replace existing steam system including valves.

Intent is to replace existing steam system including valves. Notify COR to provide direction if any non-functional valves are encountered during shut down of existing system.

6 6. Previous experience tells us hot water radiant ceiling panels provide less heat than the existing steam radiators.

a. Who is responsible if spaces are not able to maintain the appropriate temperature upon project completion?

Radiant panels are supplemental to the VAV heat which was added after the original existing steam radiators.

Concur with AE Response.

7 What capacity is required for each radiant ceiling panel?

Radiant panels shall provide minimum 230 BTU/H per SF at a mean water temperature of 190°F

8 Sheet GC001:

a. Phasing Schedule does not allow much work to be accomplished during each shift with ceilings having to be removed and utilities relocated to start work and then the space having to be returned to previous occupied conditions by the end of the shift.

i. Has this been considered in the Period of Performance?

ii. Are any occupants able to be relocated to allow areas to become construction sites for more than just 8-15 hour, or weekend shifts?

8a.1: VA to confirm

8a.ii: VA to confirm

8b. VA to confirm

8c.i: VA to confirm

8c.ii: There are two large sterilizers “Steris Amsco Century V-148H Prevac Steam Sterilizer” and two washer/disinfectors “Steris Reliance Genfore”. The washer/disinfectors, though not shown on current plans, are located on the plan west wall of room 3E04 and must

8a. JEVZ Medical Center must remain in operation 24 hours a day 7 days a week. The phasing schedule represents the optimal times to achieve work with minimal disruption to VA Staff and Patients. Several of the outpatient, mechanical, office and common areas would be available for weekend work with extended hours. Contractor to request access to these area from VA COR for evaluation of feasibility and coordination.

8ai. Yes

8aii. No

b. Phasing General Note I - Which two weeks of the year will the JCAHO inspection be?

c. Sterilizer maximum allowable downtime is only 4 hours.

i. Is there a limit on the number of times the sterilizers can be down for 4 hours?

ii. Can sterilizer equipment data be provided to determine cost for rental clean steam generator?

be reconnected to the new steam and condensate mains shown to the large sterilizers.

8b. Recent JHACO inspections have typically been during summer months. However, inspections schedule dates and times are at the discretion of the inspecting authority and subject to change or reschedule at any time.

8ci. VA would allow weekend work in SPS areas to facilitate longer shutdown durations of the sterilizers.

8cii. Concur with AE Response.

9 Sheet GC101:

a. MEDIUM PRESSURE STEAM BASEMENT MAIN PIPING PHASING PLAN – Requires a new parallel 6” MPS main be installed adjacent to the existing.

i. Is there physical space to install this main?

1. Sheet MP103 – Shows new 6” MPS, 4” LPS & 4” PC in the same location as many 3”, 4”, 5” & 6” existing to remain pipes.

a. Is there physical space for the new piping?

ii. Who is responsible for any equipment or utilities that may have to be relocated?

New pipes were intended to follow pathways of demo’d pipes (3, 4, 5, 6” pipes noted are not existing to remain).

Refer to previous RFI responses regarding field adjustments and offsets as required to achieve general layout intent.

Concur with AE Response.

10 Sheet MD601:

a. Keynote 2 indicates steam radiator digital valve controls are to be migrated to the new hydronic radiant ceiling panels.

i. Do the existing valves have the proper Cv to appropriately control the new radiant ceiling panels?

The control I/O point is to be migrated, the physical controls (valve, wiring, conduit) are to be new per plan notes. Below keynote is typical for new radiant ceiling panels.

3.MITIGATE EXISTING BAS I/O POINT FOR ABANDONED-

IN-PLACE WALL RADIATORS TO NEW RADIANT CEILING

PANEL CONTROL VALVES. PROVIDE NEW CONTROLS

CONDUIT AND CONDUCTORS IN ACCORDANCE WITH

SPECIFICATIONS 23 09 23. REFER ALSO TO I/O POINT

LISTS ON M-700 SHEET SERIES.

11 Sheet MP303:

a. There is an “X” on the 4” dia MPS (tagged “MSV”) line to the domestic water heaters.

i. Does this “X” symbol represent a pipe anchor?

ii. Is an anchor required for the 6” MSV line?

Floor penetration serves as an anchor in this plane.

iii. If this is an anchor, locations shown on plan will not work with the distances on the expansion loop detail.

1 . Where are the guides to be installed?

iv. There are other “X”s throughout the plans.

1. Are anchors required at each location?

v. Can a plan be provided with anchor locations identified?

b. Is MLPS low pressure steam?

a.i: Yes a.ii: Floor penetration serves as an anchor in this plane.

a.iii.1: Refer to detail 11 on M-502 and general note 3 therin.

a.iv.1: Refer to symbols legend a.v: Anchor locations are indicated per the symbols legend a.v.b: Refer to HVAC piping symbols on M-002

Concur with AE Responses.

12 Sheet MP112:

a. The new pipes up thru the bldg are larger than existing.

i. Will the equipment function properly if deduct alternate 1 is accepted?

a.1: Equipment will function as existing b.1: 4 is typical

Concur with AE Responses.

b. Keynote 4 indicates “TYP 5”

ii. There appears to only be 4 pipes. Are we missing one?

13 On GC101 Main piping phasing plan, to maintain steam while installing new line the branch connections are they the 6” mains only?

Question is not clear Intent of question is not clear. Drawing GC101 and MP103 show two new 6” MPS lines.

14 The piping tagged MSV would that piping fall under medium pressure steam or vent piping. On drawing MP303 the 4” MSV is suppling medium pressure steam to the existing domestic water heaters and is not vent piping. The 5” MSV piping is from the SV. Do you want this piping galvanized as stated in specifications.

MSV is steam vent piping. The 4” MSV on MP303 is venting the condensate pump receiver in BB12 from the south and pump receiver in BE01F from the north and then rising between the water heaters through the chase to the roof. Follow steam vent specifications.