S06 RFI Responses 07262022.pdf

PDF 105 KB Posted

Attached to
Y1NB--650-19-100 Replace Boilers in Bldg 10
Solicitation number
36C24122R0084
Issued by

About this file

This document contains responses to questions from a Request for Information related to solicitation number 36C24122R0084 to replace boilers in Building 10 for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1. Cleaver Brooks will provide the boiler controls equipment, flow meters, and SCADA system, but will not handle installation. Either the electrician or controls subcontractor designated by the prime contractor may install wiring for the boiler controls. There is no sequence of operations or points list for the boiler control system in the bid documents. An existing JCI control panel is mentioned but communication protocols are unclear. The contractor must provide hardware to enable the new boiler control package to communicate with the existing JCI Metasys System via BACnet IP.

View the file

Other files

File Type Posted
36C24122R0084 0008.docx DOCX document
36C24122R0084 0007.docx DOCX document
S06 RFI Response 07212022.pdf PDF
S06 RFI Responses 07202022.pdf PDF
S06 AMENDED Drawing P-502.pdf PDF
S06 AMENDED Spec Section 33 16 15 07202022.pdf PDF
S06 AMENDED Drawing P-601.pdf PDF
36C24122R0084 0006.docx DOCX document
S06 EXHIBIT C Past Performance Questionnaire Revised.pdf PDF
36C24122R0084 0005.docx DOCX document
S06 IMG_3850.pdf PDF
S06 RFI Responses 07192022.pdf PDF
S06 AMENDED Spec Section 33 16 15.pdf PDF
S06 AMENDED Spec Section 03 52 00.pdf PDF
S06 ARCHITECTURAL DRAWINGS BULLETIN 2.pdf PDF
S06 IMG_0098.pdf PDF
S06 IMG_4044.pdf PDF
S06 IMG_4037.pdf PDF
S06 GE- Roofs.pdf PDF
36C24122R0084 0004.docx DOCX document
S06 IMG_4010.pdf PDF
S06 RFI Responses 07142022.pdf PDF
S06 IMG_0094.pdf PDF
S06 ELECTRICAL DRAWINGS BULLETIN 1.pdf PDF
S06 EXHIBIT D Calculation of Self Performed Work Amended.pdf PDF
S06 Bldg 10 Boiler Plant REGULATED BLDG MATERIALS SURVEY REPORT.pdf PDF
S06 RFI Responses.pdf PDF
36C24122R0084 0003.docx DOCX document
S06 MECHANICAL DRAWINGS BULLETIN 1.pdf PDF
S06 JA CCTV System Boilers 650-19-100.pdf PDF
S06 STRUCTURAL DRAWINGS BULLETIN 1.pdf PDF
S06 EXHIBIT A Project Information Sheet for Contractors Amended.pdf PDF
S06 EXHIBIT C Past Performance Questionnaire.pdf PDF
36C24122R0084 0002.docx DOCX document
36C24122R0084 0001.docx DOCX document
Site Visit Sign-In Sheet.pdf PDF
S02 BD03252022 Drawings - 2b_Civil - Part 2.pdf PDF
S02 BD03252022 Drawings - 9_Security Electronics.pdf PDF
S02 BD03252022 Drawings - 7b_Mechanical - Part 2.pdf PDF
S02 BD03252022 Drawings - 6_Plumbing.pdf PDF
S02 BD03252022 Drawings - 1_Hazardous Materials.pdf PDF
S02 BD03252022 - 100pc Const Docs - Specs Vol I.pdf PDF
S02 BD03252022 Drawings - 0_General.pdf PDF
S02 BD03252022 Drawings - 8a_Electrical - Part 1.pdf PDF
S02 BD03252022 Drawings - 3_Structural.pdf PDF
S02 BD03252022 Drawings - 4_Architecture.pdf PDF
S02 BD03252022 Drawings - 8b_Electrical - Part 2.pdf PDF
S02 BD03252022 - 100pc Const Docs - Specs Vol III.pdf PDF
S02 BD03252022 - 100pc Const Docs - Specs Vol II.pdf PDF
S02 BD03252022 Drawings - 5_Fire Protection.pdf PDF
Show 40 more

Latest 50 of 67 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P a g e 1 | 1

Amendment 0008 Responses to RFI.

Question 120: Cleaver Brooks will be providing the Boiler Controls equipment, flow meters and SCADA system but they are not installing it. The plans and specs do not make it clear who owns this wiring so wanted to see if it was the intent for JCI to cover this wiring or does it fall under the DIV 26 Job Electrician.

VA Response: This project is a single prime contractor project, as such either sub‐contractor identified (Electrician, or Control) may install the wiring for the boiler controls equipment as designated by the prime contractor. Wiring installation subcontractor for the boiler controls equipment is at the discretion of the prime contractor.

Question 121: There is no sequence of operations or points list for the boiler control system in the bid documents. Would the construction team be able to put out something for this to get a better handle on the points and equipment that will be needed to meet the sequence of operations.

VA Response: The boiler controls do not have a point list or sequence of operations, similar to a HVAC system, mainly due to the operational requirements needed to meet the specification requirements identified within the project specification 23 09 11, paragraph 2.1.B thru 2.1.C, which are per the approved boiler manufacturer and their control requirements. The basis of design for the boiler controls is Cleaver Brooks.

Question 122: The plans mention an existing JCI panel in the building but not sure if that is correct and if so what communication type is existing. Should it be assumed that providing a new supervisory panel to accommodate the conventional HVAC controls and the BACnet IP integration to the Boiler SCADA system? If so will the VA provide a data drop for this or identify a location to run network cable for BMS tie in.

VA Response: Per the contract specifications Section 23 09 11, paragraph 2.1.A.11 the contractor is to provide required hardware … to enable the new boiler control package to communicate with the existing JCI Metasys System via BACnet IP.

Question 123: Is there an updated bidders list available?

VA Response: Reference Sign‐In Sheet from Site Visit on 6/13/2022 provided in Amendment 0001.