This document outlines a federal solicitation for construction services. The U.S. Department of Veterans Affairs is seeking proposals to renovate two mental health clinics at the Edith Nourse Rogers Memorial Veterans Hospital in Bedford, Massachusetts. Project 1 involves corrective work on the second floor outpatient clinic, while Project 2 focuses on renovating an outpatient mental health clinic in Building 6. The total estimated value of the projects ranges between $10-20 million. The solicitation is reserved exclusively for Service-Disabled Veteran-Owned Small Businesses verified in relevant databases. A mandatory pre-bid site visit was held on July 29, 2020, and proposals are due by September 4, 2020.

View the file

Other files

File Type Posted
Amendment 0009 Answers to Vendor Questions.pdf PDF
36C24120R0144 0009.pdf PDF
224000 - PLUMBING FIXTURES - 20200902 Revision 1.pdf PDF
Amendment 0008 Answer to Vendor Questions.pdf PDF
VAMC Bedford Building 6_RFI 09_WME Reponse.pdf PDF
36C24120R0144 0008.pdf PDF
VAMC Bedford Building 6_RFI 07_WME Reponse.pdf PDF
102123_Cubicle Curtain.pdf PDF
2020-08-13 VAMC Bedford 6B Renovation Pre-Bid RFI 01.pdf PDF
2020-08-18_VAMC Bedford_leopardo rfi questions_WME Response.xlsx XLSX spreadsheet
2020.08.20_AE103 and AE602_REV2 Window Fire-Ratings.pdf PDF
Amendment 0007 Answer to Vendor Questions.pdf PDF
B6 Elevation_(11304).PDF PDF
22 40 00 Plumbing Fixtures_REV1.pdf PDF
B6 Elevation_(11305).PDF PDF
36C24120R0144 0007.pdf PDF
leopardo rfi questions_combined 08202020.xlsx XLSX spreadsheet
518-15-103 Upgrade Water - Geotechnical Report and drawings 10-18-2018.pdf PDF
Section 10 25 13 Patient Bed Service Walls from Final Specifications REV1 02182020.pdf PDF
MCE ACM_LBP Bedford VAMC Rpt-(1).pdf PDF
15767 Boring (1979).pdf PDF
2020.08.20_08 80 00 Glazing_REV1.pdf PDF
2020.08.25_VAMC Bedford Building 6_RFI 05_WME Reponse.pdf PDF
062013_GRFC.pdf PDF
leopardo rfi questions and answers.pdf PDF
2020-08-13 VAMC Bedford 6B Renovation Pre-Bid RFI 01-1.pdf PDF
B6 Elevation (11304).PDF PDF
B6 Elevation (11305).PDF PDF
MCE ACM_LBP Bedford VAMC Rpt.pdf PDF
36C24120R0144 0006.pdf PDF
Section 10 25 13 Patient Bed Service Walls from Final Specifications_REV1 02182020.pdf PDF
2020-08-13_VAMC Bedford 6B Renovation_Pre-Bid RFI 01.pdf PDF
2020-08-13_Transmittal 12_Correct Mental Health Deficiencies 6B - VAMC Bedford_Pre-Bid RFI 02.pdf PDF
VAMC Bedford Building 6_RFI 02_WME Reponse.pdf PDF
Answers to Vendor Questions.pdf PDF
36C24120R0144 0005.pdf PDF
2020-08-13_Transmittal 11_Correct Mental Health Deficiencies 6B - VAMC Bedford_Pre-Bid RFI 01.pdf PDF
14 24 00 Hydraulic Elevators_REV01.pdf PDF
2020-08-13_VAMC Bedford 6B Renovation_Pre-Bid RFI 01-1.pdf PDF
room B12 part 3.pdf PDF
room B12 part 1.pdf PDF
Questions and Answers.pdf PDF
room B12 part 2.pdf PDF
36C24120R0144 0004.pdf PDF
S06 36C24120R0144 0003.docx DOCX document
S06 36C24120R0144 0002.docx DOCX document
S06 36C24120R0144 0001.docx DOCX document
S02 518-18-035_Construction Drawings Final R1 02042020 with deduct alternates-part 1 of 4.pdf PDF
S02 518-18-001 Final Specifications_REV1 02182020.pdf PDF
S02 Wage Rates MA20200001 03132020.pdf PDF
Show 40 more

Latest 50 of 60 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHABEDSanfoM Text Box Author: Michael Sanford, Project Manager, Bedford VAMC

* 6 SDVOSB contractors attended the contractor pre-bid site walkthrough: Carrigg Commercial Builders, Monument Construction, Leopardo, Veterans Development, Williams Building Co., Aulson Company. Only the SDVOSB contractors are listed on this attendance list; and only one person from each company is listed.

* Numerous sub-contractors attended the site walkthrough. No attendance records were taken of the subcontractors.

* Contractors and subcontractors were provided access to the basement, first floor, second floor and attic.

* Stated to contractors and subcontractors:

* No specific questions could be answered during the site walkthrough. All questions are to be directed to the Contracting Officer.

* All RFI's are to be directed to the Contracting Officer following the requirements of the Solicitation.

* Highly suggested that contractors make available to their subcontractors electronic copies of all the drawings and specifications, not just ones for their respective discipline.

* Project work is shown in the drawings and specifications; the combination of both is the entirety of the project. Contractors are cautioned that no matter where the work is located in the drawings and specifications, it is covered under the contract and the responsibility of the Contractor.

* One participant stated he did not see quantities for asbestos abatement. The group was informed that the specifications provides for this and they need to relook at the contract documents. If the quantities are not in the contract documents then they can send in an RFI and it will be addressed.

* One participant stated that they did not see demolition drawings for one of the projects. The group was informed that there are demolition drawings and notes for both projects.

* SDVOSB contractors were informed that they need to contact the Contracting Officer if they want a copy of this list.

VHABEDSanfoM Text Box 9:00 a.m.