Projects
| Schedule for FBB Renovatons | |||
| Project A: FBB 2nd Floor Renovation | |||
| EVENTS | Duration: Calendar Days | START DATE | FINISH DATE |
| Preconstruction Meeting | 4 | 9/23/19 | 9/27/19 |
| Remove Furniture from floor | 18 | 9/30/19 | 10/18/19 |
| Demolition | 39 | 10/21/19 | 11/29/19 |
| Framing | 64 | 12/2/19 | 2/4/20 |
| Electrical: rough-in & lighting | 95 | 12/16/19 | 3/20/20 |
| Plumbing: cut/cap; Rough-in; fixture installation | 102 | 12/16/19 | 3/27/20 |
| Sprinkler | 144 | 12/16/19 | 5/8/20 |
| Ductwork/ Diffusers/ Controls/ TABS | 102 | 12/16/19 | 3/27/20 |
| Insulation | 27 | 1/21/20 | 2/17/20 |
| Hang Board | 70 | 2/9/20 | 4/19/20 |
| Communications | 92 | 4/1/20 | 7/2/20 |
| Doors/ Hardware | 25 | 4/22/20 | 5/17/20 |
| Painting | 41 | 5/20/20 | 6/30/20 |
| Ceiling Grid/ Tile | 41 | 5/21/20 | 7/1/20 |
| Carpet/ Ceramic Tile/ Resilient Flooring | 27 | 6/3/20 | 6/30/20 |
| Millwork | 11 | 7/1/20 | 7/12/20 |
| General Contract Closeout and Punchlist | 9 | 7/15/20 | 7/24/20 |
| Treasury Furniture | 18 | 7/27/20 | 8/14/20 |
| Treasury Security Accrediation | 18 | 8/17/20 | 9/4/20 |
| Treasuy Network | 18 | 9/7/20 | 9/25/20 |
| Project Closeout - Customer Move in | 0 | 9/26/20 | |
| Project B: FBB 3rd Floor Renovation | |||
| EVENTS | Duration: Calendar Days | START DATE | FINISH DATE |
| Preconstruction Meeting | 4 | 9/21/20 | 9/25/20 |
| Remove Furniture from floor | 18 | 9/28/20 | 10/16/20 |
| Demolition | 39 | 10/19/20 | 11/27/20 |
| Framing | 66 | 11/30/20 | 2/4/21 |
| Electrical: rough-in & lighting | 95 | 12/21/20 | 3/26/21 |
| Plumbing: cut/cap; Rough-in; fixture installation | 102 | 12/21/20 | 4/2/21 |
| Sprinkler | 144 | 12/21/20 | 5/14/21 |
| Ductwork/ Diffusers/ Controls/ TABS | 102 | 12/21/20 | 4/2/21 |
| Insulation | 27 | 1/25/21 | 2/21/21 |
| Hang Board | 67 | 2/8/21 | 4/16/21 |
| Communications | 92 | 4/5/21 | 7/6/21 |
| Doors/ Hardware | 25 | 4/19/21 | 5/14/21 |
| Painting | 41 | 5/24/19 | 7/4/19 |
| Ceiling Grid/ Tile | 41 | 5/24/21 | 7/4/21 |
| Carpet/ Ceramic Tile/ Resilient Flooring | 27 | 6/7/21 | 7/4/21 |
| Millwork | 11 | 7/5/21 | 7/16/21 |
| General Contract Closeout and Punchlist | 11 | 7/19/21 | 7/30/21 |
| Treasury Furniture | 18 | 8/2/21 | 8/20/21 |
| Treasury Security Accrediation | 11 | 8/23/21 | 9/3/21 |
| Treasuy Network | 18 | 9/6/21 | 9/24/21 |
| Project Closeout | 0 | 9/25/21 |
OFAC / OIA Renovations &D
Projects Pending Funding Project Pending Funding
| FBB Design for Renovation of the 2nd Floor (63 people) | |||||
| EVENTS | TENTATIVE START DATE | TENTATIVE FINISH DATE | ACTUAL START DATE | ACTUAL FINISH DATE | |
| Kickoff Meeting | 10/20/17 | 10/20/17 | COMPLETED | 10/20/17 | 10/20/17 |
| Design Intent Drawings finalized | 1/15/18 | 3/12/18 | COMPLETED | 1/15/18 | 3/12/18 |
| Design Drawings to be Awarded | 9/7/18 | 9/28/18 | COMPLETED | 9/7/18 | 9/28/18 |
| Designs Documents Completed for Construction, LAN & Security | 10/1/18 | 3/31/19 | ON GOING | 10/1/18 | |
| Need funding for Project | 10/1/18 | TBD |
| FBB Design for Renovation of the 3rd Floor (100 people) | |||||
| EVENTS | TENTATIVE START DATE | TENTATIVE FINISH DATE | STATUS | ACTUAL START DATE | ACTUAL FINISH DATE |
| Kickoff Meeting | 10/20/17 | 10/20/17 | COMPLETED | 10/20/17 | 10/20/17 |
| Design Intent Drawings finalized | 1/15/18 | 3/12/18 | COMPLETED | 1/15/18 | 3/12/18 |
| Design Drawings to be Awarded | 9/7/18 | 9/28/18 | COMPLETED | 9/7/18 | 9/28/18 |
| Designs Documents Completed for Construction, LAN & Security | 10/1/18 | 5/31/19 | ON GOING | 10/1/18 | |
| Need funding for Project | 10/1/18 | TBD |
| FBB Design for Renovation of the Sub-Basement Print Shop | |||||
| EVENTS | TENTATIVE START DATE | TENTATIVE FINISH DATE | STATUS | ACTUAL START DATE | ACTUAL FINISH DATE |
| Prepare Procurement Packages, Submit to IRS & Award Contracts (6 weeks) | 5/18/18 | 9/21/18 | IRS pricing came in over 4x's IGE so project to be rebid in FY19. | ||
| Need funding for Project | 10/1/18 | TBD |
| FBB Design for Renovation of the Sub-Basement OFAC office (25 people) | |||||
| EVENTS | TENTATIVE START DATE | TENTATIVE FINISH DATE | STATUS | ACTUAL START DATE | ACTUAL FINISH DATE |
| Prepare Procurement Packages, Submit to IRS & Award Contracts (2 months) | 3/16/2018 5/18/18 | 9/21/18 | IRS pricing came in double IGE so project to be rebid in FY19 | ||
| Need funding for Project | 10/1/18 | TBD | |||
| DID for High Density Files/ Print Shop & IGE submitted to OFAC | 12/6/18 | 1/31/18 |