2032H319R00008_0002.pdf
PDF 101 KB Posted
- Attached to
- Treasury OFAC Renovation Federal contract opportunity
- Solicitation number
- 2032H319R00008
About this file
amendment 0002
View the file
Other files for this federal contract opportunity
Show all 41
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
2032H319R00008 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Lanham MD 20706 5000 Ellin Road
1-IRS NON-IT (OTPS)
OS:PR:T, Stop C7-430 DCOS/Procurement Internal Revenue Service IRS non-IT (OTPS)
07/09/20190002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/09/2019
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
1. AMENDMENT 002
2. The purpose of this amendment is to address the following:
RFIs (page 2)
4. All other terms and condition of the solicitation remain unchanged.
Invoice Approver/COR: CHOATE, BARBARA Inv
Approver/COR Backup1: PANKEY, HERBERT
Period of Performance: 09/30/2019 to 09/30/2021
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
NANCY P. KEBE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
RFI Questions and Answers
RFI-003 3.1 Factor 1: Technical Approach and Experience states that, "projects must be related to renovation and/or restoration on Government Historical Buildings."
We have renovation and restoration project experience similar in scope, magnitude and complexity to the Treasury OFAC renovation project. Our relevant projects were also performed in historical buildings; however, they were not Government historical buildings. We feel that our project experience is highly relevant and beneficial to the Treasury. Would the government be willing to change the "Government Historical Building" requirement to "Historical Buildings" only?
RESPONSE – The requirement remains must be related to renovation/and or restoration on Government Historical Buildings.
How will renovation and restoration project experience in a historical building (not government historical buildings) be evaluated?
RESPONSE - Proposals must meet the criteria stated in the request for proposal (RFP) to be eligible for award, to include responsiveness, technical acceptability and responsibility.
RFI-004 - Additional ceiling description requested at the Site Visit
RESPONSE - Ceiling Deck: The basic slab structure consists of roughly 1-1/2” concrete on top of a terra cotta structural slab resulting in an overall depth of approximately 10”. Each terra cotta block contains approximately a 6” hollow void that is enclosed within the sides of the block.
Solicitation Change
NA
ATTACHMENTS
NA