2-Sec 01 33 00 - SUBMITTALS.pdf
PDF 144 KB Posted
- Attached to
- 234 McKean Road Demolition (26-00182)
- Solicitation number
- Not on record
- Issued by
- Montgomery County, Pennsylvania
About this file
This is a technical specification document for submittal procedures applicable to the Horsham Township demolition and site restoration project in Pennsylvania. The specification establishes comprehensive requirements for contractor submissions throughout the project lifecycle, including construction progress schedules, product data, shop drawings, samples, design data, test reports, certificates, manufacturer's instructions, field reports, and erection drawings. Contractors must submit a preliminary progress schedule within 10 days of the effective agreement date and a final schedule within 10 days of the preconstruction conference. All submittals must be sequentially numbered, clearly identified with project information, and submitted to the Engineer for review. The specification requires contractors to allow 15 days for Engineer review of each submittal (excluding delivery time) and to identify any variations from contract documents or product limitations. A mandatory pre-bid meeting is scheduled for Thursday, April 2, 2026, at 1100 Limekiln Pike, Ambler, PA 19002, with submission of bids due by September 9, 2025. The project scope includes demolition of a residential home, detached garage, two sheds, and an asphalt driveway, along with capping a domestic water well, abandoning a sanitary service line, restoring a stream crossing damaged by flooding, and grading and stabilizing all disturbed areas.
The submittal specification requires contractors to provide multiple copies of all materials—typically the number required by the contractor plus three copies retained by the Engineer. Product data must identify applicable models, options, and utility characteristics; shop drawings must indicate special utility and electrical requirements; and samples must demonstrate functional and aesthetic characteristics with full project identification. Certificates of conformance and manufacturer's instructions must be submitted when specified in individual specification sections. The specification references Section 01 40 00 (Quality Control) and Section 01 70 00 (Contract Closeout) for manufacturers' field services and closeout submittals including maintenance bonds, warranties, and record drawings. No specific pricing information, set-asides, or funding sources are detailed in this submittal procedures specification; such information would be found in the bid documents and project cost estimates.
View the file
Other files
Show 40 more
Latest 50 of 97 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUBMITTALS
01 33 00-1
SECTION 01 33 00
PART 1 GENERAL
1.01 SECTION DESCRIPTION
A. The Work of This Section Includes:
1. Submittal procedures.
2. Construction progress schedules.
3. Product data.
4. Shop Drawings.
5. Samples.
6. Design data.
7. Test reports.
8. Certificates.
9. Manufacturer’s instructions.
10. Manufacturer’s field reports.
11. Erection drawings.
1.02 RELATED SECTIONS
A. Related Work Specified Elsewhere:
1. Section 01 40 00: Quality Control: Manufacturers' field services.
2. Section 01 70 00: Contract Closeout: Contract closeout submittals including maintenance bond, manufacturers’ warranties, and record drawings.
1.03 REFERENCES
A. AGC (Associated General Contractors of America) publication “The Use of CPM in
Construction - A Manual for General Contractors and the Construction Industry”.
1.04 SUBMITTAL PROCEDURES
A. Transmit each submittal to Engineer.
B. Sequentially number the transmittal forms. Revise submittals with original number and a sequential alphabetic suffix.
C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate.
01 33 00-2
D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of
Products required, field dimensions, adjacent construction Work, and coordination of information, is in accordance with the requirements of the Work and Contract Documents.
E. Schedule submittals to expedite the Project and to coordinate submission of related items.
F. For each submittal for review, allow 15 days excluding delivery time to and from Contractor.
G. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.
H. Provide space for Contractor and Engineer review stamps.
I. When revised for resubmission, identify all changes made since previous submission.
J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements.
K. Submittals not requested will not be recognized or processed.
1.05 CONSTRUCTION PROGRESS SCHEDULES
A. Submit preliminary progress schedule in duplicate within 10 days after Effective Date of Agreement for review by Engineer.
B. Revise and resubmit as required.
C. Submit final progress schedule within 10 days of preconstruction conference or within 10 days upon request of Engineer if no preconstruction conference is to be held.
D. Submit revised progress schedule in duplicate with each Application for Payment, identifying changes since previous version.
E. Submit a horizontal bar chart with separate line for each section of Work, identifying first work day of each week.
F. Show complete sequence of construction by activity, identifying Work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.
G. Indicate estimated percentage of completion for each item of Work at each submission.
H. Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates, including those furnished by Owner.
1.06 PRODUCT DATA
A. Product Data for Review:
1. Submitted to Engineer for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents.
2. After review, provide copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
01 33 00-3
B. Product Data for Information:
1. Submitted for the Engineer’s knowledge as contract administrator or for Owner.
C. Product Data for Project Closeout:
1. Submitted for Owner’s benefit during and after project completion.
D. Submit the number of copies which Contractor requires, plus three copies which will be retained by Engineer.
E. Mark each copy to identify applicable Products, models, options, and other data. Supplement manufacturers’ standard data to provide information specific to this Project.
F. Indicate Product utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
1.07 SHOP DRAWINGS
A. Shop Drawings for Review:
with information given and the design concept expressed in the Contract Documents.
2. After review, produce copies and distribute in accordance with Submittal Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
B. Shop Drawings for Information:
1. Submitted for Engineer’s knowledge as contract administrator or for Owner.
C. Shop Drawings for Project Closeout:
1. Submitted for Owner’s benefit during and after project completion.
D. Indicate special utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances.
E. Submit the number of opaque reproductions which Contractor requires, plus three copies which will be retained by Engineer.
1.08 SAMPLES
A. Samples for Review:
with information given and the design concept expressed in the Contract Documents.
2. After review, produce duplicates and distribute in accordance with Submittal
Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
B. Samples for Information:
1. Submitted for Engineer’s knowledge as contract administrator or for Owner.
01 33 00-4
C. Samples for Selection:
1. Submitted to Engineer for aesthetic, color, or finish selection.
2. Submit samples of finishes [from the full range of manufacturers’ standard colors,] [in custom colors selected,] textures, and patterns for Engineer’s selection.
3. After review, produce duplicates and distribute in accordance with Submittal
Procedures article above and for record documents purposes described in Section 01 70 00 - Contract Closeout.
D. Submit samples to illustrate functional and aesthetic characteristics of the Product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.
E. Include identification on each sample, with full Project information.
F. Submit the number of samples specified in individual specification sections; one of which will be retained by Engineer.
G. Reviewed samples which may be used in the Work are indicated in individual specification sections.
H. Samples will not be used for testing purposes unless specifically stated in the specification section.
1.09 DESIGN DATA
A. Submit for Engineer’s knowledge as contract administrator or for Owner.
B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
1.10 TEST REPORTS
A. Submit for Engineer’s knowledge as contract administrator or for Owner.
B. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
1.11 CERTIFICATES
A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, or Contractor to Engineer, in quantities specified for Product Data.
B. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate.
C. Certificates may be recent or previous test results on material or Product, but must be acceptable to Engineer.
1.12 MANUFACTURER’S INSTRUCTIONS
A. When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, to Engineer for delivery to Owner in quantities specified for Product Data.
01 33 00-5
B. Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation.
C. Refer to Section 01 40 00 - Quality Control, Manufacturers’ Field Services article.
1.13 MANUFACTURER’S FIELD REPORTS
A. Submit reports for Engineer’s benefit as contract administrator or for Owner.
B. Submit report in duplicate within 30 days of observation to Engineer for information.
C. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
1.14 ERECTION DRAWINGS
A. Submit drawings for Engineer’s benefit as contract administrator or for Owner.
B. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
C. Data indicating inappropriate or unacceptable Work may be subject to action by Engineer or
Owner.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
File details come from the government source that posted it. Updated .