2. CDRLs MHMV100050CR Repair Systems B20245.pdf

PDF 199 KB Posted

Attached to
Design Charrette for Repair Consolidated Support Building 20245
Solicitation number
FA9401-21-R-0003
Issued by

About this file

This document outlines the contract data requirements list (CDRL) for a federal contract to provide architectural and engineering services for the repair and modernization of Building 20245 at an Air Force base. Key deliverables include a facility sustainment restoration modernization planning charrette report, design analysis, cost estimates, specifications, and conceptual design drawings at 50%, 95%, and 100% completion rates. The contractor must submit deliverables in Microsoft Word, Excel and PDF formats to the 377th Mission Support Group and base point of contact on a defined schedule, with initial submissions due 45 days after award. Progress and financial reporting, meeting materials, agendas and minutes are also required. The related solicitation provides additional context, seeking a 35% conceptual design for Building 20245 in support of the Air Force's sustainment, restoration and modernization program, with a mandatory site visit.

View the file

Other files

File Type Posted
18. Site Visit Sign In Sheet.pdf PDF
9. B-20245 Component-Section Report updated 15 Feb 21.xlsx XLSX spreadsheet
17. SF330.pdf PDF
Solicitation Amendment 3.pdf PDF
19. Questions and Answers for Solicitation.pdf PDF
Solicitation Amendment FA940121R00030002.pdf PDF
SF330.pdf PDF
Amendment FA940121R00030001 SF 30.pdf PDF
7. Welcome Center Talking Paper.pdf PDF
13b. HVAC Waste Water Discharge Request Form.pdf PDF
6b. Comm Div Specs.pdf PDF
1. Statement of Objectives MHMV 100050CR 28 Oct 20.pdf PDF
8. Section Data Sheet programming.xlsx XLSX spreadsheet
16. DD1391c TEMPLATE.docx DOCX document
11. AFCFS and IFS for KAFB.pdf PDF
10. AF_Sust_Scoresheet_GP_vFeb2017.xls XLS spreadsheet
1a. Appendix 1 FSRM PCR Template.docx DOCX document
15. DD1391 FSRM TEMPLATE 2020-02-05.docx DOCX document
6a. Front End Specs Template.pdf PDF
5a. Floor plan with estimated sqft. bldg. 20245.pdf PDF
3. Schedule of Design Submittals.pdf PDF
Combined Synopsis Solicitation - Design Charette Consolidated Support Bldg..pdf PDF
Solicitation - FA940121R0003.1.pdf PDF
4. Bid Tab Design Charrette MHMV100050CR.pdf PDF
12. AFGSC-Logo-grayscale.jpg JPG image
5c. As builts - Bldg 20245.pdf PDF
14. FY22-26_AFCAMP_Business_Rules_v2_marked up_12Jun2020.pdf PDF
5b. Floor plan with existing organizations bldg. 20245.pdf PDF
9. B-20245 Component-Section Report 6-2-2020.xlsx XLSX spreadsheet
13a. Environmental Check list.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CDRL Table for: MHMV100050CR Report Date: 21 October 2020

CDRL EXHIBIT: A

CDRL : A001 SOW REF : 2.1, 2.4, 2.9, 2.11

Deliverable: SRM Planning and Programming

Title : Scientific and Technical Reports

Deliverable Comments:

Deliverables in MS Word & PDF format

Date of First Submission: With the Preliminary Evaluation Submittal within 45 calendar days from award

Frequency : Single Occurrence

Deliverable Table

Deliverable Submitted to: Final

377 MSG/PKC (CO) 1

Base POC 1

CDRL : A001a SOW REF : 2.0, 2.4, 4.0

Deliverable: 50% Facility Sustainment Restoration Modernization Planning Charrette Report (FSRM PCR)

Date of First Submission: With the Preliminary Submittal within 45 calendar days from Design Charrette Meeting

CDRL : A001a SOW REF : 2.0, 2.4, 4.0

Deliverable: 95% Facility Sustainment Restoration Modernization Planning Charrette Report (FSRM PCR)

CDRL : A001b SOW REF : 2.0, 2.4, 4.0

Deliverable: 100% Facility Sustainment Restoration Modernization Planning Charrette Report (FSRM PCR)

Date of First Submission: With the 100% Submittal within 30 calendar days from the Preliminary Evaluation Review

Base POC 2

CDRL : A001d SOW REF : 4.0

Deliverable: 50% Design Analysis

Deliverables in PDF format

CDRL : A001d SOW REF : 4.0

Deliverable: 95% Design Analysis

CDRL : A001e SOW REF : 4.0

Deliverable: 100% Design Analysis

Deliverable electronically and Hard Copy

Date of First Submission: With the 100% Submittal within 30 calendar days from the Preliminary

Base POC 2

CDRL : A003 SOW REF : 3.9

Deliverable: Critical Issues Notification

Title : Report, Production or Delivery Problems (Human Health or Contract Issues)

Deliverable to 377 MSG/PKC (CO) and Base POC by email

Date of First Submission: Within 3 working days of verbal notification

Frequency : As required

CDRL : A004 SOW REF : 3.10

Deliverable: Occupational Safety and Health Administration Requirements

Title : Scientific and Technical Report

Deliverable to 377 MSG/PKC (CO) and Base POC by email

Date of First Submission: In Accordance with Contract Frequency : One report plus revisions

CDRL : A010a SOW REF: 2.1, 2.3, 2.9, 2.13, 4.0

Deliverable: Preliminary Evaluation Cost Analysis

Title : Scientific and Technical Reports: Cost Analysis

Deliverables is MS Excel and PDF formats.

CDRL : A010b SOW REF: 2.1, 2.3, 2.9, 2.13, 4.0

Deliverable: Preliminary Cost Estimate

Title : Scientific and Technical Reports: Cost Estimate

Deliverables is MS Excel and PDF formats.

Date of First Submission: With the 50% Design Submittal within 30 calendar days from the Preliminary Submittal Review

CDRL : A011a SOW REF: 2.1, 4.0

Deliverable: 50% Design Specifications

Title : Scientific and Technical Reports: Design Specification s

Date of First Submission: With the 50% Design Submittal within

CDRL : A011b SOW REF: 2.1, 4.0

Deliverable: 95% Design Specifications

Title : Scientific and Technical Reports: Design Specifications

Date of First Submission: With the 95% Design Submittal within 30 calendar days from the 50%

CDRL : A011b SOW REF: 2.1, 4.0

Deliverable: 100% Design Specifications

Title : Scientific and Technical Reports: Design Specifications

Date of First Submission: With the 100% Design Submittal within 30 calendar days from the 90%

CDRL : A012a SOW REF: 2.1, 2.4, 2.9, 2.13, 4.0

Deliverable: 50% Conceptual Design Drawings

Title : Engineering Drawings: Design Drawings

Deliverables in DWG and PDF format.

CDRL : A012a SOW REF: 2.1, 2.4, 2.9, 2.13, 4.0

Deliverable: 95% Conceptual Design Drawings

CDRL : A012b SOW REF: 2.1, 2.4, 2.9, 2.13, 4.0

Deliverable: 100% Conceptual Design Drawings within 30 calendar days from the Preliminary Evaluation Review

CDRL : A012b SOW REF: 2.6, 2.8.2, 4.0

Deliverable: 50% Re-Programing Plan

Date of First Submission: With the 50% Design Submittal within

Frequency :

Single Occurrence

Deliverable: 95% Re-Programing Plan

Date of First Submission: With the 95% Design Submittal within

Deliverable: 100% Re-Programing Plan within 30 calendar days from the Preliminary Evaluation Review

CDRL EXHIBIT: B

CDRL : B001 SOW REF : 3.3

Deliverable: AF Form 3065

Title : Contract Work Breakdown Structure

Deliverable Comments: Deliverables shall be submitted to Base POC by email.

Date of First Submission: 7 work days after award Frequency : Monthly with revisions

CDRL : B002 SOW REF : 2.12

Deliverable: Photo Documentation

Title : Contract Progress Schedule

Deliverables shall be submitted to Base POC by email.

Date of First Submission: 45 work days after award Frequency : Monthly with revisions

CDRL : B007 SOW REF : 2.2, 2.13

Deliverable: Meeting Presentation Materials

Title : Presentation Materials

Deliverables shall be submitted to Base POC by email

Date of First Submission: 3 working day prior to meetings Frequency : Once per meeting

CDRL : B008 SOW REF : 2.1.1

Deliverable: Meeting Agenda

Title : Conference Agenda

Date of First Submission: 1 working day prior to meeting

CDRL : B009 SOW REF : 2.1.1

Deliverable: Meeting Minutes

Title : Conference Minutes

Date of First Submission: 3 working days following meeting