This document is a Project Closeout specification section (Section 01700) that outlines the procedures and requirements for completing a construction project. The section details the process for declaring substantial completion and final completion of work, which involves the contractor submitting written notices to the Engineer, including lists of items requiring correction or completion. The specification describes a multi-step observation process where the Engineer will review the work, identify any deficiencies, and require the contractor to remedy any issues before final acceptance.
The document specifies that the contractor must submit a final statement of accounting that reflects all contract sum adjustments, including original contract sum, change orders, allowances, unit prices, deductions for uncorrected work, and re-inspection payments. The Engineer will prepare a final Change Order capturing approved adjustments not previously made. The contractor must also submit a final Application for Payment in accordance with contract conditions, package and label spare parts and maintenance materials, and complete all project record documents as specified in Section 01720. If additional observations are required due to the contractor's failure to meet completion standards, the Engineer may deduct compensation from the final payment.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01700-1
SECTION 01700
PROJECT CLOSEOUT
PART 1 GENERAL
1.1 RELATED WORK SPECIFIED ELSEWHERE
A. Project Record Documents - Section 01720.
1.2 SUBSTANTIAL COMPLETION
A. When the work is considered substantially complete, submit a written notice that the work, or a designated portion thereof, is substantially complete. Include a list of all items that require completion or correction.
B. Within a reasonable time after receipt of such notice, an observation will be made to determine the status of completion.
C. If the Work is not considered substantially complete, the Contractor will be notified in writing, giving the reasons therefore.
D. Contractor shall remedy the deficiencies in the Work, and send a second written notice of substantial completion. This notice shall include a statement of action taken on each item noted a requiring correction or completion to achieve "Substantial
Completion" status.
E. The Work will be observed a second time.
F. When the Engineer concurs that the Work is substantially complete, he will:
1. Issue a letter accompanied by Contractor's list of items to be completed or corrected, as verified and amended by the Engineer.
1.3 FINAL OBSERVATION
A. When the Work is considered complete, submit written certification that:
1. Contract Documents have been reviewed.
2. Work has been observed and has been completed in compliance with
Contract Documents.
01700-2
3. Equipment and systems have been tested in the presence of the Engineer and are operational.
4. Work is ready for final observation.
B. Observation will be made to verify the status of completion with reasonable promptness after receipt of such certification.
C. If the Work is not considered complete, the Contractor will be notified in writing, listing the incomplete or defective work.
D. Contractor shall take immediate steps to remedy the stated deficiencies and, after correcting deficiencies, he shall send a second written certificate that the work is complete. This certification shall itemize each deficiency noted and a statement of action taken to remedy or complete the Work.
E. The work will be observed a second time.
F. When the Work is acceptable under the Contract Documents, the Contractor shall be required to make closeout submittals.
1.4 SECOND OBSERVATION FEES
A. Should the Engineer perform a second observation due to failure of the work to comply with the claims of status of completion made by the Contractor:
1. Engineer will deduct the amount of such compensation from the final payment to the Contractor.
1.5 CLOSEOUT SUBMITTALS
A. Project Record documents as specified under Section 01720.
1.6 SPARE PARTS AND MAINTENANCE MATERIALS
A. Furnish spare parts and maintenance materials as specified under various Sections of the Specifications.
B. Package and label parts and materials and store in area of the building where directed by the Engineer.
1.7 FINAL ADJUSTMENT OF ACCOUNTS
01700-3
A. Submit a final statement of accounting.
B. Statement shall reflect all adjustments to the Contract Sum:
1. The original Contract Sum.
2. Additions and deductions resulting from:
a. Previous Change Orders.
b. Allowances.
c. Unit Prices.
d. Deductions for uncorrected Work.
e. Deductions for re-inspection payments.
f. Other adjustments.
3. Total Contract Sum, as adjusted.
4. Previous payments.
5. Sum remaining due.
C. The Engineer will prepare a final Change Order, reflecting approved adjustments to the Contract sum which were not previously made by Change Orders.
1.8 FINAL APPLICATION FOR PAYMENT
A. Submit the final Application for Payment in accordance with procedures and requirements stated in the Conditions of the Contracts.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION