1240LT26Q0003-0001 QA Strawberry Kamas Bunkhouse UWCNF.pdf

PDF 230 KB Posted

Attached to
GAOA – Strawberry – Kamas Bunkhouse Renovations on the Uinta/Wasatch/Cache National Forest
Solicitation number
1240LT26Q0003
Issued by

About this file

This is Amendment 01 to Solicitation 1240LT26Q0003 for the Strawberry-Kamas Bunkhouse Renovations project on the Uinta/Wasatch/Cache National Forest, issued February 23, 2026. The amendment extends the proposal submission deadline from February 27, 2026 at 1:00 p.m. to March 13, 2026 at 1:00 p.m. MST, and extends the deadline for submitting inquiries from February 17, 2026 to March 3, 2026 at 4:30 p.m. MST. The amendment modifies technical specifications for both the Kamas and Strawberry Administrative Sites, including changes to building references (Bldg #1063 to Bldg #1065), deletion of language in the asbestos abatement section, clarification that door hardware work involves replacing doorknobs with lever-type handles only (not full door replacement), and addition of requirements to demo and install lever-type handle faucets in three specified buildings.

The amendment includes a Question and Answers section addressing pricing (no price quote limit; the stated range is informational only), project tax status (not tax exempt; all applicable Federal, State, and local taxes must be included per FAR 52.229-3), site access (exteriors are available for visual inspection; interiors are not available due to current occupancy), flooring product specifications (equivalent products acceptable per specifications sections 096519, 096816, 096813), equipment inspection responsibility (COR responsible prior to mobilization), and project completion deadline (all work must be completed by April 1, 2027). The amendment also addresses worker accommodations (on-site camping in personal RVs requires District Ranger approval after award) and notes that floor plans for the Kamas West House will be provided in Amendment 02, which will be posted within the next week with additional changes and clarifications.

View the file

Other files

File Type Posted
1240LT26Q0003-0004 Attachment 1 SOI Strawberry Renovations Amended.xlsx XLSX spreadsheet
1240LT26Q0003-0004 SF30 Amendment 04.pdf PDF
1240LT26Q0003-0003 SF30 Strawberry Kamas Bunkhouse UWCNF.pdf PDF
1240LT26Q0003-0002 Questions and Answers Amendment 02 .pdf PDF
1240LT26Q0003-0002 Attachment 6A - Kamas Bunkhouses Floorplans.pdf PDF
1240LT26Q0003-0002 Attachment 2 SOI_Kamas Renovations Amended.xlsx XLSX spreadsheet
1240LT26Q0003-0002 SF-30 Amendment 02 Strawberry Kamas Bunkhouse UWCNF.pdf PDF
1240LT26Q0003-0002 Attachment 1 SOI Strawberry Renovations Amended.xlsx XLSX spreadsheet
1240LT26Q0003-0002 Attachment 6B Kamas East Bunkhouse Asbestos Report .pdf PDF
1240LT26Q0003-0001 Attachment 1 SOI Strawberry Renovations Amended.xlsx XLSX spreadsheet
1240LT26Q0003-0001 Questions and Answers Amendment 02 .pdf PDF
1240LT26Q0003-0001 Attachment 2 SOI_Kamas Renovations Amended.xlsx XLSX spreadsheet
1240LT26Q0003-0001 Attachment 6A - Kamas Bunkhouses Floorplans.pdf PDF
1240LT26Q0003-0001 Attachment 6B Kamas East Bunkhouse Asbestos Report .pdf PDF
1240LT26Q0003-0001 SF-30 Amendment 02 Strawberry Kamas Bunkhouse UWCNF.pdf PDF
1240LT26Q0003-0001 SF30 Strawberry Kamas Bunkhouse UWCNF.pdf PDF
Attachment 1 - SOI_Strawberry Renovations.xlsx XLSX spreadsheet
Attachment 12 - 3WeekLookahead_KamasBunkhouses_Template.xlsx XLSX spreadsheet
Attachment 10 Kamas Site Pictures.docx DOCX document
Attachment 5 - Signed Drawing Strawberry Kamas Bunkhouse Renovations.pdf PDF
Attachment 11 - 3WeekLookahead_StrawberryBunkhouses_Template.xlsx XLSX spreadsheet
Attachment 3 - Spec Package_Strawberry Renovations.pdf PDF
Attachment 2 - SOI_Kamas Renovations.xlsx XLSX spreadsheet
Attachment 7 - DBA WD UT202601 Wasatch Co 010226.pdf PDF
Attachment 8 - DBA WD UT202635 Summit Co 010226.pdf PDF
1240LT26Q0003 RFQ GAOA Strawberry Kamas Bunkhouse Renovations FInal.pdf PDF
Attachment 9 Strawberry Site Pictures.docx DOCX document
Attachment 4 - Spec Package_Kamas Renovations FINAL.pdf PDF
Attachment 6 - Existing Conditions Kamas Bunkhouse.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 01 Strawberry-Kamas Bunkhouse Renovations

February 23, 2026

Solicitation 1240LT26Q0003, Strawberry-Kamas Bunkhouse Renovations, Uinta/Wasatch/Cache National Forest, is amended as follows:

The solicitation is amended as follows:

See Attachment 5 – Signed Drawings Strawberry-Kamas Bunkhouse Renovations, Sheet 10 of 10, change all references from Bldg #1063 to Bldg #1065.

See Solicitation, SF-1442, Pg 1, Section 13. Additional Solicitation Requirements, change due date and time from February 27, 2026 at 1:00 p.m. to March 13, 2026 at 1:00 p.m. MST.

See Solicitation, Page 33, Government Point of Contact, change inquiries due date from February 17, 2026 to March 3, 2026 at 4:30 p.m. MST.

Kamas Administrative Site:

See Attachment 4 – Spec Package Kamas Renovations Final, Page 41, Section 024230 – Asbestos Abatement, Part 1 – General, 1.1 Scope, Paragraph A., delete the last sentence in its entirety.

Strawberry Administrative Site:

See Attachment 3 – Spec Package Strawberry Renovations, Page 141, Section 087100 – Door Hardware, Part 1 – General, Section 1.2 - Description of Work, Paragraph A.

Clarification: Not replacing all doors, just doorknobs with lever type handles, and inspecting door hardware as stated in Schedule of Items line item.

See Attachment 3 – Spec Package Strawberry Renovations, Page 246, Section 224216.13 - Commercial Lavatories, add the following: Description: Demo and remove existing bathroom and kitchen faucets. Provide and install level type handle faucet in buildings 1062, 1063, and 1065.

The following questions and answers are being provided for informational or clarification purposes only.

Q: when the questions are due by? is that answer Feb. 17 at 16:30?

A: Due date for questions is extended to 16:30PM MST on 03/03/2026 by this Amendment.

Q: Is the contract limited to $1 million amount?

A: There is no price quote limit/ceiling. The price range is simply for informational purposes based on where the Government estimate falls.

Q: Will the bid date be changing to a different date and time? Also, will the bids be due at 1:00 Mountain Standard Time?

A: Due date for quotes/proposals is extended to 1:00PM MST on 03/132026. by this Amendment.

Q: Are both projects tax exempt?

A: Project is not tax exempt. In accordance with FAR clause 52.229-3 Federal, State, and Local Taxes, the contract price shall include all applicable Federal, State, and local taxes and duties.

Q: Will there be another job walk for the house that wasn’t able to be seen due to sickness of the tenant?

A: No second organized site visit is planned. The exterior of all sites are available for visual access. Interiors will not be available for inspection due to current occupancy.

Q: Will there be another job walk available for subcontractors to come and take a look at both projects?

A: No second organized site visit is planned. The exteriors of all sites are available for visual access. Interiors will not be available for inspection due to current occupancy.

Q: For the project in Kamas, will floor plans be provided so that subcontractors can give us costing or will quantities be issued?

A: A floor plan/drawing of the Kamas West House will be provided in Amendment 02.

Q: Looking at the flooring specs, there are not any products specified. How would you like us to proceed?

A: Product compliance requirements are listed in the specifications part 2: Products. Products shall be equivalent to those listed.

KAMAS LVT: 096519 part 2. PRODUCTS KAMAS SHEET CARPETING: 096816 ‘Part 2. PRODUCTS’ STRAWBERRY TILE CARPETING: 096813 ‘Part 2. PRODUCTS‘ STRAWBERRY LVT: 096519 ‘Part 2. PRODUCTS’

Q: For equipment inspections who will do it?

A: COR will be responsible for inspections prior to equipment mobilization onto Forest Service land.

Q: One year to finish?

A: All work must be completed no later than April 1, 2027.

Q: Can workers stay on-site in their personal RV trailers?

A: Any camping on site must be approved by the District Ranger after award.

A second Amendment will be posted with additional changes and questions/answers within the next week.