About this file
This is a Schedule of Items (SOI) pricing template for the GAOA Strawberry Kamas Bunkhouse Renovations project on the Uinta/Wasatch/Cache National Forest. The solicitation (1240LT26Q0003) encompasses comprehensive renovation work across five buildings at the Kamas facility, with all line items currently showing zero pricing pending contractor input. The base scope includes mobilization, project management, utility coordination, interior and exterior repairs (painting, door replacements, vents, grills, light fixture and exhaust fan upgrades), electrical work (outlet and switch inspection/replacement across 110 units), safety installations (27 smoke alarms and carbon monoxide detectors), window treatments (57 horizontal lift blinds), furnace and water heater servicing, asbestos inspection, and various building-specific renovations across the West House, East Bunkhouse, North House, and South House.
The optional scope adds supplemental work including drain replacements, furnace and water heater replacement, carpet removal and installation (approximately 4,000 square feet), kitchen countertop replacement (300 linear feet), soffit and fascia replacement (30 linear feet), and building-specific enhancements such as bathroom demolition/rebuild, plumbing relocation with PEX piping installation, cabinetry refinishing, concrete porch replacement, and insulated garage door systems with remotes and keypads. Contractors must submit unit prices for all line items in both base and optional categories. The government notes that unit prices will govern in case of extension errors, and contractors certifying the SOI are responsible for verifying all calculations and pricing accuracy. One award will be made from this solicitation.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KAMAS_SOI
| ATTACHMENT 2 - SCHEDULE OF ITEMS |
| AMENDMENT 02 |
| SOLICITATION NO. 1240LT26Q0003 |
| ITEM 2000 - KAMAS BUNKHOUSE RENNOVATIONS |
| UNITA/WASATCH/CACHE NATIONAL FOREST |
| ITEM/ SPECIFICATION | SUBITEM 2001 - All Kamas Buildings - BASE | METHOD OF MEAS | PAY UNIT | EST QTY | Unit Price | TOTAL |
| 011900 | Mobilization, including bonding, Measurement & Payment, Close Out Procedures | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 013100 | Project Management & Utility Coordination | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 099120-01 | Repair, patch & paint ALL surfaces. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 099120-02 | Repair and paint/stain All interior doors. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 081110-1 | Replace ALL exterior doors, frames & hardware, install electronic coded keypad entry locks. | AQ | EA | 9 | $ - 0 | $ - 0 |
| 233713.23-01 | Replace vents, grills & cold air returns. | AQ | EA | 52 | $ - 0 | $ - 0 |
| 081110-2 | Install door stop/protectors for ALL doors. | AQ | EA | 60 | $ - 0 | $ - 0 |
| 265000 | Replace ALL light fixtures & ceiling fans with LED Lights. Install new or replace old exhaust fans in all restrooms. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 262726 | Inspect, update & replace electrical outlets & switches. | AQ | EA | 110 | $ - 0 | $ - 0 |
| 267500 | Provide and install smoke alarms and carbon monoxide detectors. | AQ | EA | 27 | $ - 0 | $ - 0 |
| 122113 | Provide & Install horizonal lift blinds. | AQ | EA | 57 | $ - 0 | $ - 0 |
| 159500.2 | Full Service ALL furnaces - describe 'full service' meaning in specs | AQ | EA | 4 | $ - 0 | $ - 0 |
| 223400.2 | Full Service ALL water heaters. | AQ | EA | 4 | $ - 0 | $ - 0 |
| 024230 | Asbestos Inspection/Testing (ALL except East Bunkhouse) | LSQ | LS | 1 | $ - 0 | $ - 0 |
| TOTAL ALL BUILDINGS - BASE | $ - 0 |
| ITEM/ SPECIFICATION | SUBITEM 2002 - 19030601: West House - BASE | METHOD OF MEAS | PAY UNIT | EST QTY | Unit Price | Total |
| 85413-601 | Replace ALL windows, finish inside of window frame. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 96519-601 | East entry way to Kitchen, Provide and install LVT, including PVC baseboard. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 96816-601 | Replace carpet flooring, in bedrooms & Living rm. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 093033-601.12 | West bathroom Re-tile floor, provide and install elongated toilet. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 233113-601 | Rear entryway, re-route dryer exhaust through exterior wall. Furnace area move furnace exhaust from N side to S side of unit, construct linin shelving install folding door. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 061000-601 | Remove un-used door frame kitchen, Remove paneling, Remove center bedroom interior window. Finish to match. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| TOTAL WEST HOUSE - BASE | $ - 0 |
| ITEM/ SPECIFICATION | SUBITEM 2003 - 19030405: East Bunkhouse - BASE | METHOD OF MEAS | PAY UNIT | EST QTY | Unit Price | Total |
| 96400-405 | Living room, Repair, sand and, prep re-surface hardwood floors. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 90190-405 | Kitchen, entryway, hallway -deep clean, repair & refinish ALL shelves, drawers, doors. Remove door jam, laundry chute, old fuse box & other closets. Replace with wood drawers, cupboards, doors, add & extend more shelving, cupboards & doors. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 61000-405.10 | Remove Main floor & 2nd floor stair landing cold air return, repair floor, install in wall. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 61000-405.05 | Basement, rebuild lower wood section of stairs, frame & finish both sides of inside walls. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 96519-405 | Kitchen, rear entryway, stairs down & stairs to kitchen, hallway to stairs & ALL landings, stairs to second floor, remove, replace existing flooring with LVT flooring & PVC baseboard. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 96816-405 | All 4 bedrooms, replace/or supply carpet. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 049030-1 | Living rm replace broken bricks, clean all masonary, repoint joints & re-seal masonary, resurface mantel. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 093033-405.10 | 1st floor east bathroom, prepare and install ceramic tile on floor and walls & inside tub/shower area | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 093033-405.20 | 2nd floor bathroom install, tile wall & flooring, sink & vanity, elongated toilet & 3 lg inset medicine cabinets, | LSQ | LS | 1 | $ - 0 | $ - 0 |
| TOTAL EAST BUNKHOUSE - BASE | $ - 0 |
| ITEM/ SPECIFICATION | SUBITEM 2004 - 19030501: North House - BASE | METHOD OF MEAS | PAY UNIT | EST QTY | Unit Price | Total |
| 96530-501 | Reglaze bathtub, replace baseboard & trimboard in bathroom, hallway, kitchen & Utility room. Replace with PVC. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 49030-2 | Living rm replace broken bricks, clean all masonary, re-point joints, seal masonary, replace mantle. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 33000-501 | Replace concrete side walks front & rear of house, replace rear porch. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| TOTAL NORTH HOUSE - BASE | $ - 0 |
| ITEM/ SPECIFICATION | SUBITEM 2005 - 19060701: South House - BASE | METHOD OF MEAS | PAY UNIT | EST QTY | Unit Price | Total |
| 85413-701 | Replace ALL windows, finish inside of window frame. | LSQ | LS | 13 | $ - 0 | $ - 0 |
| 96530-701 | Replace baseboard & trimboard in Bathroom, Kitchen & Utility room. Replace with PVC. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 96816-701 | Replace Front Room carpet | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 099300-701 | Remove carpet 4' wide walk way strip from front door to hallway & including halway, Re-finish hardwood flooring. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 099111-701 | Prepare, repaint backyard shed. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| 33000-701 | Replace concrete under garage door & pad at rear exterior door, Replace front Porch, Replace front portion of sidewalk, remove dirt to slope exisiting ground away from concrete behind the house. | LSQ | LS | 1 | $ - 0 | $ - 0 |
| TOTAL SOUTH HOUSE - BASE | $ - 0 | |||||
| BASE TOTAL (SUBITEMS 2001-2005) | $ - 0 |
| ITEM/ SPECIFICATION | SUBITEM 2006 - All Kamas Buildings - Options | METHOD | |||||
| OF MEAS | PAY UNIT | EST QTY | Unit Price | Total | |||
| 220500 | Replace tub, shower drains as needed | AQ | EA | 3 | $ - 0 | $ - 0 | |
| 235416.13 | Replace Furnace | AQ | EA | 1 | $ - 0 | $ - 0 | |
| 223400 | Replace Water Heater | AQ | EA | 1 | $ - 0 | $ - 0 | |
| 96816-01 | Demo and remove existing carpet, provide and install carpet flooring. Total sqft aprox 4K | AQ | SF | 2000 | $ - 0 | $ - 0 | |
| 123661.16 | Kitchen Remove and replace laminate countertops. | AQ | LF | 300 | $ - 0 | $ - 0 | |
| 074293 | Replace soffit and fascia. | AQ | LF | 30 | $ - 0 | $ - 0 | |
| 093033-601.10 | West House - East bathroom, demolish & rebuild, as per specification. | LSQ | LS | 1 | $ - 0 | $ - 0 | |
| 151400-601.1 | West House - Outside of SW bedroom remove shower, relocate water heater to this area, extend piping to new location & frame in new water heater area, build catch pan to drain, install vent through roof, finish area, install door. Replace ALL water lines to entire house with Pex piping. | LSQ | LS | 1 | $ - 0 | $ - 0 | |
| 090190-601 | West House - Kitchen, west bathroom, rear hallway & utility areas, replace ALL cabinet hinges, door glides, and handles. Deep clean & paint/refinish all cabinetry and replace countertops | LSQ | LS | 1 | $ - 0 | $ - 0 | |
| 033000-601 | West House - Replace rear concrete porch. | LSQ | LS | 1 | $ - 0 | $ - 0 | |
| 083613-501 | North House - New Insulated Garage door system, with remotes and keypad. | LSQ | LS | 1 | $ - 0 | $ - 0 | |
| 090190-501 | North House - ALL Cabinetry & drawers deep clean & refinish to original, replace door glides, handles. | LSQ | LS | 1 | $ - 0 | $ - 0 | |
| 083613-701 | South House - New Insulated Garage door system, with remotes and keypad. | LSQ | LS | 1 | $ - 0 | $ - 0 | |
| 91110-405.05 | East Bunkhouse - Build and finish storage room basement. | AQ | EA | 2 | $ - 0 | $ - 0 | |
| TOTAL ALL BUILDINGS - OPTIONS | $ - 0 | ||||||
| TOTAL ALL BASE & OPTIONAL SUBMITEMS (SUBITEMS 2001-2006) | $ - 0 | ||||||
| SOI NOTES: | |||||||
| NOTE 1: Contractor input Unit Prices | |||||||
| NOTE 2: Auto Calculated Values | |||||||
| NOTE 3: One award will be made from this solicitation. Contractors shall submit a quote for all Base Items and all Optional Items in the Schedule of Items. In the event of an error in extending the proposed prices, unit prices will govern, unless otherwise determined by the Contracting Officer, in accordance with applicable regulations. | |||||||
| NOTE 4: Submission of a signed SOI represents the Contractors commitment to the data herein. It is the responsibility of the Contractor to verify that all values presented in the signature certified SOI, including auto-calculated cells, accurately represent the Contractor's intended price elements. The Government shall not be held liable for any errors in calculation or pricing data. |
QUOTER NAME: BUSINESS EMAIL:
SAM UEI #: BUSINESS PHONE:
AUTHORIZED TO SIGN: (NAME & TITLE)
SIGNATURE: DATE:
File details come from the government source that posted it. Updated .