024100-DBB-rev71-Demolition~1.pdf

PDF 95 KB Posted

Attached to
MIL1901E-EC1 MIL-Natick-Solar PV-Design/Build
Solicitation number
BD-19-1019-DCP08-ENR01-29482
Issued by
Middlesex County, Massachusetts

About this file

This document is a detailed demolition specification for a Massachusetts state construction project. It outlines the requirements for the selective demolition and removal of existing building components, site elements, and utilities as part of a larger construction project.

The specification covers the scope of demolition work, including the removal and salvage of existing items, preparation for new construction, and proper disposal of demolished materials. It also includes requirements for utility disconnections, hazardous materials handling, protection of adjacent properties, and blasting procedures (if approved). The document specifies quality assurance standards, submittal requirements, and execution procedures to be followed by the demolition contractor.

View the file

Other files

File Type Posted
MIL1901E Natick Solar PV RFP.pdf PDF
preproposalsignin8.7.18.pdf PDF
MIL1901E Scope of Work Form_Final.xlsx XLSX spreadsheet
MAARNG Natick_C-102_Lyt+Matls Pln_2015_As-Built_Mark-Up.pdf PDF
017419-DBB-rev71-Construction Waste Mgmt and Disposal~1.pdf PDF
MAARNG Natick_E1.00_Elec Site Pln_2015_As-Built_Mark-Up.pdf PDF
MAARNG Natick_E1.01_Elec Site Dets_2015_As-Built_Mark-Up.pdf PDF
018100-DBB-rev71-Commissioning~1.pdf PDF
MIL1901E-EC1_Dec. of Soil Bearing Capacity.pdf PDF
MAARNG Natick_E1.01_Elec Site Detls_2015_As-Built.pdf PDF
017418-DBB-rev71-Demolition Waste Mgmt and Disposal~1.pdf PDF
MIL1901E Eversource Elect Bills Nov 2015-July 2018.pdf PDF
MIL1901E_EC1_ Response_Form.docx DOCX document
Environmental Baseline Study Draft June.4.2010.pdf PDF
MAARNG Natick_C-106_Utility Plan_2015_As-Built.pdf PDF
MIL1901E Cover Letter.docx DOCX document
MAARNG Natick_C-105_Utility Plan_2015_As-Built_Mark-Up.pdf PDF
MIL1901E_Prevailing_Wage.pdf PDF
260001-CMR-rev71-TB Electrical Work~1.pdf PDF
site visit sign in sheet 8.9.18.pdf PDF
MIL1901E EC1 Pricing Savings Form.xlsx XLSX spreadsheet
Natick Readiness Center Report-6.7.17.pdf PDF
MIL1901E Pre-Proposal Conference PresentanKAL.pptx PPTX presentation
MAARNG Natick_C-103_Grading+Drain Pln_2015_As-Built_Mark-Up.pdf PDF
DOC011.pdf PDF
MAARNG Natick_Struct Sects+Detls_As-Built_Mark-Up.pdf PDF
MAARNG Natick_C-101_Lyt Matls Pln_2015_As-Built_Mark-Up.pdf PDF
MAARNG Natick_E1.00_Elec Site Plan_2015_As-Built.pdf PDF
ESA Small Project Template August 2018.pdf PDF
MAARNG Natick_H2.04_HVAC Roof New Wrk Pln_2015_As-Built_Mark-Up.pdf PDF
MAARNG Natick_LS-101_Landscape+Plant Pln_2015_As-Built.pdf PDF
SDO-certified MWBE Sub-contractors~2.xlsx XLSX spreadsheet
MIL1901E_Natick_Real_Property.pdf PDF
MIL1901E Proposals Recieved.pdf PDF
MIL1901E.audit_template_savings.xlsm XLSM spreadsheet
MAARNG Natick_C-104_Grading+Drain Pln_2015_As-Built_Mark-Up.pdf PDF
Geotechnical Engineering Report 03-22-11.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCAMM STANDARD SPECIFICATIONS MASS. STATE PROJECT NUMBER

REV 7.1 - DBB PROJECT NAME, LOCATION

DEMOLITION ISSUE DATE

024100 - 1

SECTION 024100

DEMOLITION

PART 1 - GENERAL

1.1 GENERAL PROVISIONS

A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS, which are hereby made a part of this Section of the Specifications.

1.2 DESCRIPTION OF WORK

A. Work Included:

1. Demolition and removal of selected portions of buildings and structures and as required for new work. Refer to the Drawings for additional requirements.

2. Demolition and removal of selected site elements and as required for new work. Refer to the Drawings for additional requirements.

3. Salvage of existing items to be reused or turned over to the facility.

4. Removal and legal disposal of demolished materials off site. Except those items specifically designated to be relocated, reused, or turned over to the facility, all existing removed materials, items, trash and debris shall become property of the Contractor and shall be completely removed from the site and legally disposed of at her/his expense.

Salvage value belongs to the Contractor. On-site sale of materials is not permitted.

5. Maintenance, watering and care of trees designated to remain by a certified arborist during the construction period.

6. Demolition and removal work shall properly prepare for alteration work and new construction to be provided under the Contract.

7. Blasting requirements.

8. Scheduling and sequencing operations without interrupting utilities serving occupied areas. If interruption is required, obtain written permission from the utility company and the DCAMM Project Manager. Schedule interruption when the least amount of inconvenience will result.

B. Alternates: Not Applicable.

C. Items To Be Installed Only: Not Applicable.

D. Items To Be Furnished Only: Not Applicable.

E. Related Work: The following items are not included in this Section and will be performed under the designated Sections:

1. Section 015000 - TEMPORARY FACILITIES AND CONTROLS:

a. Maintenance of access, cleaning during construction, dust and noise control.

DEMOLITION ISSUE DATE

024100 - 2

2. Section 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL:

a. Waste management and recycling.

3. Section 210001 - FIRE PROTECTION:

a. Disconnecting, capping and otherwise making inactive existing mechanical services in areas where demolition and removal work is required. Mechanical tradesmen will disconnect, cap, inactivate and lower to floor such items where required to be removed under Section 210001 - FIRE PROTECTION. Removal and disposal of such materials shall be then done under this Section 024100 -

DEMOLITION.

b. Disconnect and reinstallation of fire protection equipment temporarily interrupted during construction.

4. Section 220001 - PLUMBING:

a. Disconnecting, capping and otherwise making inactive existing mechanical services in areas where demolition and removal work is required. Mechanical tradesmen will disconnect, cap, inactivate and lower to floor such items where required to be removed under Section 230001 - PLUMBING. Removal and disposal of such materials shall be then done under this Section 024100 -

DEMOLITION.

b. Disconnect and reinstallation of plumbing equipment temporarily interrupted during construction.

5. Section 230001 - HEATING, VENTILATING AND AIR CONDITIONING:

a. Disconnecting, capping and otherwise making inactive existing mechanical services in areas where demolition and removal work is required. Mechanical tradesmen will disconnect, cap, inactivate and lower to floor such items where required to be removed under Section 230001 - HEATING, VENTILATING AND AIR CONDITIONING. Removal and disposal of such materials shall be then done under this Section 024100 - DEMOLITION.

b. Disconnect and reinstallation of HVAC equipment temporarily interrupted during construction.

6. Section 260001 - ELECTRICAL WORK:

a. Disconnecting, capping and otherwise making inactive existing electrical services in areas where demolition and removal work is required. Electrical tradesmen will disconnect, cap, inactivate and lower to floor such items where required to be removed under Section 260001 - ELECTRICAL WORK. Removal and disposal of such materials shall be then done under this Section 024100 - DEMOLITION.

b. Disconnect and reinstallation of electrical equipment temporarily interrupted during construction.

7. Section 311000 – SITE CLEARING:

a. Excavating and removal of existing pavement, sub-surface building and utility structures and lines, appurtenances, and other elements indicated on the Drawings.

1.3 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Detach items from existing construction and deliver them to the User Agency ready for reuse, at a location designated by the User Agency. Protect from weather until accepted by User Agency.

DEMOLITION ISSUE DATE

024100 - 3

C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated. Protect from weather until reinstallation.

D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.4 MATERIALS OWNERSHIP

A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques, antiques, and other items of interest or value to DCAMM that may be encountered during selective demolition remain property of the Commonwealth or user Agency as applicable. Carefully remove each item or object in a manner to prevent damage and deliver promptly to a location acceptable to the DCAMM Project Manger.

1.5 SUBMITTALS

A. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with early and late starting and finishing dates for each activity. Ensure User Agency's on-site operations are uninterrupted if applicable.

2. Interruption of utility services. Indicate how long utility services will be interrupted.

3. Coordination for shutoff, capping, and continuation of utility services.

4. Use of elevator and stairs.

5. Locations of proposed dust- and noise-control temporary partitions and means of egress, including for other occupants affected by selective demolition operations.

6. Coordination of User Agency's continuing occupancy of portions of existing building and of User Agency's partial occupancy of completed Work.

7. Means of protection for items to remain and items in path of waste removal from building.

B. Inventory: After selective demolition is complete, submit a list of items that have been removed and salvaged, and turned over to the User Agency.

C. Predemolition Videotapes: Show existing conditions of adjoining construction and site improvements, including finish surfaces, that might be misconstrued as damage caused by selective demolition operations. Comply with Division 01. Submit before Work begins.

D. Landfill Records: Provide trip tickets (receipts) indicating receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.

1. Comply with submittal requirements in Section 017419 - CONSTRUCTION WASTE

MANAGEMENT AND DISPOSAL.

1.6 QUALITY ASSURANCE

A. Examination of Existing Conditions: The Contractor shall examine the Contract Drawings for demolition and removal requirements and provisions for new work. Verify all existing

DEMOLITION ISSUE DATE

024100 - 4 conditions and dimensions before commencing work. The Contractor shall visit the site and examine the existing conditions as he finds them and shall inform herself/himself of the character, extent and type of demolition and removal work to be performed. Submit any questions regarding the extent and character of the demolition and removal work in the manner and within the time period established for receipt of such questions during the bidding period.

B. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.

C. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.

D. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

E. Standards: Comply with ANSI A10.6 and NFPA 241.

F. Predemolition Conference: Conduct conference at Project site to comply with requirements in Section 013100 - PROJECT MANAGEMENT, COORDINATION AND COMMISSIONING.

Review methods and procedures related to selective demolition including, but not limited to, the following:

1. Inspect and discuss condition of construction to be selectively demolished.

2. Review structural load limitations of existing structure.

3. Review and finalize selective demolition schedule and verify availability of materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

5. Review areas where existing construction is to remain and requires protection.

1.7 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.

1.8 BLASTING

A. Blasting, when allowed in the contract, or subsequently approved in writing by the DCAMM Project Manager, shall be performed in accordance with the Board of Fire Prevention Regulations 527 CMR 13.00 – EXPLOSIVES, Section 13.09 (latest edition). Section 13.09 shall become an integral part of these specifications. The Blaster through the Construction Manager shall submit a Blasting Plan (a.k.a. Blast Design Plan), prepared and sealed by a registered professional engineer that includes calculations of over-pressure and debris hazards.

The DCAMM Project Manager or her/his designee and the Construction Manager are responsible for reviewing the Blast Design Plan before a charge is detonated. The Construction Manager shall be responsible for all damage caused by the blasting operations.

DEMOLITION ISSUE DATE

024100 - 5

1. The Construction Manager through the Site Subcontractor shall supply the DCAMM Project Manager with XUC (Explosives User Certificate) and proof of current liability insurance and bonds required by MGL 148, Paragraphs 19, 20 and 20A prior to the use of explosives.

2. When blasting is done within 250 feet from the center of the blast site, or a building, structure, railway, or highway or any other installation that could be affected, the Blaster shall provide DCAMM with a Liability Insurance Policy in the amount of $ 5,000,000., naming DCAMM as additional insured.

3. The Construction Manager shall engage the services of a third party to perform a pre-blast and post-blast video survey of all structures above and below ground, within the 250 feet radius. The video records shall become the property of DCAMM.

4. The Blasting Company and the Blaster shall be licensed for blasting operations in the Commonwealth of Massachusetts. The Blasting Company is responsible for obtaining all permits necessary for blasting operations.

5. The Blaster shall limit the size of explosive charges to the smallest amount possible and the smallest quantity in a detonation sequence. The Blaster shall place a minimum of four (4) feet of 3/8” crushed stone over the blast zone and then place blasting mats on top of the crushed stone.

6. As part of the review of the Blast Design Plan, the DCAMM Project Manager or her/his designee shall designate an exploratory area of rock excavation to which the Blaster will confine his initial drilling and blasting. No additional drilling or blasting will be performed until the effects of the blasting has been completed and the original Blast Design Plan has been reaffirmed and/or revised in writing.

7. Approval of the Blast Design Plan will not relieve the Blaster and/or the Construction Manager of their responsibilities in connection with the work, safety and direct or indirect damages to existing or new structures.

B. The Department of Environmental Protection has identified “perchlorate” as a contaminant of concern. Perchlorate is very soluble in water and is easily leached from the ground surface into the groundwater. Explosives with perchlorate, or ingredients that may produce perchlorate residue, are prohibited.

1. The Contractor shall provide ground water monitoring test wells at intervals of 25 feet along perimeters of blast areas or as otherwise directed by the DCAMM Project Manager.

The DCAMM Testing Agency shall take ground water samples, prior to blasting and after blasting operations are completed, utilizing the monitoring test wells.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped.

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

DEMOLITION ISSUE DATE

024100 - 6

C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.

D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict.

Promptly submit a written report to Designer.

E. Engage a professional engineer registered in the Commonwealth of Massachusetts to survey condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations.

F. Survey of Existing Conditions: Record existing conditions by use of preconstruction videotapes.

1. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.

G. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Service/System Requirements: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Arrange to shut off indicated utilities with utility companies and User Agency.

2. If services/systems are required to be removed, relocated, or abandoned, before proceeding with selective demolition provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

3. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing. Where entire wall is to be removed, existing services/systems may be removed with removal of the wall.

4. Prior to commencing cutting work in existing surfaces, take all precautionary measures to assure that mechanical and electrical services to the particular area have been made inactive. Coordinate with Fire Protection, Plumbing, HVAC, and Electrical subcontractors. Only licensed tradesmen of that particular trade shall disconnect and cap existing mechanical and electrical items that are to be removed, abandoned and/or relocated.

5. If, during the process of cutting work, existing utility lines are encountered which are not indicated on the Drawings, regardless of their condition, immediately report such items to the Designer. Do not proceed with work in such areas until instructions are issued by the Designer. Continue work in other areas.

DEMOLITION ISSUE DATE

024100 - 7

3.3 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Comply with requirements for access and protection specified in Section 015000 -

TEMPORARY FACILITIES AND CONTROLS.

2. Maintain adequate passage to and from all exits at all times. Before any work is done which significantly alters access or egress patterns, consult with the Designer and obtain approval of code required egress. Under no condition block or interfere with the free flow of people at legally required exits, or in any way alter the required condition of such exits.

B. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

1. Strengthen or add new supports when required during progress of selective demolition.

2. Remove temporary shoring, bracing and structural supports when no longer required.

3. Post warning signs and place barricades as applicable during placement and removal of temporary shoring.

C. Conduct demolition operations to prevent injury to people and damage to adjacent buildings and facilities to remain. Ensure safe passage of people around demolition area(s).

1. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction. Provide temporary barricades as required to limit access to demolition areas.

2. Protect existing site improvements, appurtenances, and landscaping to remain.

D. Drain, purge, or otherwise remove, collect, and dispose of chemicals, gases, explosives, acids, flammables, or other dangerous materials before proceeding with demolition operations.

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.

DEMOLITION ISSUE DATE

024100 - 8

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire-suppression devices during and after flame-cutting operations.

5. Maintain adequate ventilation when using cutting torches.

6. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.

7. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

8. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

9. Dispose of demolished items and materials promptly. Comply with requirements in

Section 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL.

B. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to User Agency.

4. Transport items to storage area designated by the DCAMM Project Manager.

5. Protect items from damage during transport and storage.

C. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Designer, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

E. Items for Re-use and Preservation of Existing Surfaces to Remain:

1. The Contractor shall inspect closely each item specifically designated to be relocated, re-used, or turned over to the Owner prior to its removal, and immediately report damages and defects to the Designer and DCAMM Project Manager. The Contractor shall be responsible for any subsequent damage to the same other than latent defects not readily apparent from close inspection, and shall bear responsibility for its repair or same replacement as directed by the Designer, to the satisfaction of the DCAMM Project Manager.

2. Unless special surface preparation is specified under other Specification Sections, leave existing surfaces that are to remain in a condition suitable to receive new materials and/or finishes.

DEMOLITION ISSUE DATE

024100 - 9

3.5 PROTECTION OF PUBLIC AND PROPERTY

A. Provide all measures required by federal, state and municipal laws, regulations, and ordinances for the protection of surrounding property, the public, workmen, and Commonwealth’s employees during all demolition and removal operations. Measures are to be taken, but not limited to installation of sidewalks, sheds, barricades, fences, warning lights and signs, trash chutes and temporary lighting.

B. Protect all walks, roads, streets, curbs, pavements, trees and plantings, on and off premises, and bear all costs for correcting such damage as directed by the Designer, and to the satisfaction of the DCAMM Project Manager.

C. Demolition shall be performed in such a manner that will insure the safety of adjacent property.

Protect adjacent property from damage and protect persons occupying adjacent property from injuries which might occur from falling debris or other cause and so as not to cause interference with the use of other portions of the building, of adjacent buildings or the free access and safe passage to and from the same.

D. Every precaution shall be taken to protect against movement or settlement of the building, of adjacent buildings, structures, sidewalks, roads, streets, curbs and pavements. Provide and place at the Contractor’s own expense, all necessary bracing and shoring in connection with demolition and removal work.

E. Remove portions of structures with care by using tools and methods that will not transfer heavy shocks to existing and adjacent building structures, both internal and external of the particular work area.

F. Provide and maintain in proper condition, suitable fire resistive dust barriers around areas where interior demolition and removal work is in progress. Dust barriers shall prevent the dust migration to adjacent areas. Remove dust barriers upon completion of major demolition and removal in the particular work area.

G. Protect unaltered portions of existing construction, including finishes, furnishings and equipment

H. Provide secure weather protection where demolition has removed a portion of the exterior envelope.

3.6 DISCOVERY OF HAZARDOUS MATERIALS

A. If hazardous materials, such as chemicals, asbestos-containing materials, or other hazardous materials are discovered during the course of the work, cease work in affected area only and immediately notify the Designer and the DCAMM Project Manager of such discovery. Do not proceed with work in such areas until instructions are issued by the Designer. Continue work in other areas.

B. If unmarked containers are discovered during the course of the work, cease work in the affected area only and immediately notify the Designer and the DCAMM Project Manager of such discovery. Do not proceed with work in such areas until instructions are issued by the Designer.

DEMOLITION ISSUE DATE

024100 - 10

Take immediate precautions to prohibit endangering the containers integrity. Continue work in other areas.

3.7 CUTTING

A. Perform all cutting of existing surfaces in a manner which will ensure a minimal difference between the cut area and new materials when patched. Use extreme care when cutting existing surfaces containing concealed utility lines which are indicated to remain and bear full responsibility for repairing or replacement of all such utilities that are accidentally damaged.

B. Provide a flush saw cut edge where pavement, curb and concrete removals abut new construction work or existing surfaces to remain undisturbed.

3.8 BLASTING

A. When blasting is allowed by DCAMM, obtain written permission and approval of method for blasting from the Designer with concurrence of the DCAMM Project Manager, Fire Chief, and local authorities before proceeding with explosive operations.

B. Notify the DCAMM Project Manager at least 48 hours before any intended blasting and do no blasting without specific written approval of each blasting operation. Conduct blasting operations using explosives of such quantity and power, and fired in such sequence and locations, as not to injure personnel or damage property, or damage adjacent work.

C. Assume full responsibility for damages resulting from or attributable to blasting operations.

D. All rock blasting shall be well covered with heavy mats or timbers chained together and the Contractor shall take great care to do no damage to existing buildings, foundations, existing roadways, glazed areas and trees to remain. Any damage caused by the work of this Contractor shall be repaired to the full satisfaction of the DCAMM Project Manager at no additional cost to

DCAMM.

3.9 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Comply with requirements of Section 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL and the following.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

B. Burning: Do not burn demolished materials.

DEMOLITION ISSUE DATE

024100 - 11

3.10 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Premises shall be left in a clean condition and ready to accept alteration work and new construction.

END OF SECTION

DEMOLITION ISSUE DATE

024100 - 12

STANDARD SPECIFICATIONS

DCAMM Standard Specifications are intended for use only on projects of the Division of Capital Asset Management and Maintenance in the Commonwealth of Massachusetts. The specifications are intended to assist the Designer with incorporating DCAMM and MGL Chapter 149 filed sub-bid requirements in documents used for bidding and construction. Each section will require editing by a registered architect or engineer before issue.

NOTES TO THE DESIGNER

Selective Demolition: The Drawings must indicate major and minor items for selective demolition to enable the contractor to submit a proper bid. If necessary, include a detailed narrative in this specification section. If selective demolition must be done in phases, include detailed requirements.

Blasting: Because the Commonwealth is “self-insured”, blasting on State property that has existing buildings and/or structures is discouraged. If blasting is allowed, the onus for insuring such existing buildings adjacent to or in near proximity of proposed new construction must be borne by the Contractor.

RESOURCES

None for this Section

END

PART 1 - GENERAL
1.1 GENERAL PROVISIONS
A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL REQUIREMENTS, which are hereby made a part of this Section of the Specifications.
1.2 DESCRIPTION OF WORK
A. Work Included:
B. Alternates: Not Applicable.
C. Items To Be Installed Only: Not Applicable.
D. Items To Be Furnished Only: Not Applicable.
E. Related Work: The following items are not included in this Section and will be performed under the designated Sections:
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Detach items from existing construction and deliver them to the User Agency ready for reuse, at a location designated by the User Agency. Protect from weather until accepted by User Agency.
C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated. Protect from weather until reinstallation.
D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.4 MATERIALS OWNERSHIP
A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques, antiques, and other items of interest or value to DCAMM that may be encountered during selective demolition remain property of the Commonwealth or user Agency as applicable. Carefully remove each item or object in a manner to prevent damage and deliver promptly to a location acceptable to the DCAMM Project Manger.
1.5 SUBMITTALS
A. Schedule of Selective Demolition Activities: Indicate the following:
B. Inventory: After selective demolition is complete, submit a list of items that have been removed and salvaged, and turned over to the User Agency.
C. Predemolition Videotapes: Show existing conditions of adjoining construction and site improvements, including finish surfaces, that might be misconstrued as damage caused by selective demolition operations. Comply with Division 01. Submit before Work begins.
D. Landfill Records: Provide trip tickets (receipts) indicating receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.
1.6 QUALITY ASSURANCE
A. Examination of Existing Conditions: The Contractor shall examine the Contract Drawings for demolition and removal requirements and provisions for new work. Verify all existing conditions and dimensions before commencing work. The Contractor shall visit the site and examine the existing conditions as he finds them and shall inform herself/himself of the character, extent and type of demolition and removal work to be performed. Submit any questions regarding the extent and character of the demolition and removal work in the manner and within the time period established for receipt of such questions during the bidding period.
B. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.
C. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.
D. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
E. Standards: Comply with ANSI A10.6 and NFPA 241.
F. Predemolition Conference: Conduct conference at Project site to comply with requirements in Section 013100 - PROJECT MANAGEMENT, COORDINATION AND COMMISSIONING. Review methods and procedures related to selective demolition including, but not limited to, the following:
1.7 WARRANTY
A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.
1.8 BLASTING
A. Blasting, when allowed in the contract, or subsequently approved in writing by the DCAMM Project Manager, shall be performed in accordance with the Board of Fire Prevention Regulations 527 CMR 13.00 – EXPLOSIVES, Section 13.09 (latest edition). Section 13.09 shall become an integral part of these specifications. The Blaster through the Construction Manager shall submit a Blasting Plan (a.k.a. Blast Design Plan), prepared and sealed by a registered professional engineer that includes calculations of over-pressure and debris hazards. The DCAMM Project Manager or her/his designee and the Construction Manager are responsible for reviewing the Blast Design Plan before a charge is detonated. The Construction Manager shall be responsible for all damage caused by the blasting operations.
B. The Department of Environmental Protection has identified “perchlorate” as a contaminant of concern. Perchlorate is very soluble in water and is easily leached from the ground surface into the groundwater. Explosives with perchlorate, or ingredients that may produce perchlorate residue, are prohibited.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped.
B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.
D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Designer.
E. Engage a professional engineer registered in the Commonwealth of Massachusetts to survey condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations.
F. Survey of Existing Conditions: Record existing conditions by use of preconstruction videotapes.
G. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.
3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Service/System Requirements: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.
3.3 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
B. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.
C. Conduct demolition operations to prevent injury to people and damage to adjacent buildings and facilities to remain. Ensure safe passage of people around demolition area(s).
D. Drain, purge, or otherwise remove, collect, and dispose of chemicals, gases, explosives, acids, flammables, or other dangerous materials before proceeding with demolition operations.
3.4 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
B. Removed and Salvaged Items:
C. Removed and Reinstalled Items:
D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Designer, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
E. Items for Re-use and Preservation of Existing Surfaces to Remain:
3.5 PROTECTION OF PUBLIC AND PROPERTY
A. Provide all measures required by federal, state and municipal laws, regulations, and ordinances for the protection of surrounding property, the public, workmen, and Commonwealth’s employees during all demolition and removal operations. Measures are to be taken, but not limited to installation of sidewalks, sheds, barricades, fences, warning lights and signs, trash chutes and temporary lighting.
B. Protect all walks, roads, streets, curbs, pavements, trees and plantings, on and off premises, and bear all costs for correcting such damage as directed by the Designer, and to the satisfaction of the DCAMM Project Manager.
C. Demolition shall be performed in such a manner that will insure the safety of adjacent property. Protect adjacent property from damage and protect persons occupying adjacent property from injuries which might occur from falling debris or other cause and so as not to cause interference with the use of other portions of the building, of adjacent buildings or the free access and safe passage to and from the same.
D. Every precaution shall be taken to protect against movement or settlement of the building, of adjacent buildings, structures, sidewalks, roads, streets, curbs and pavements. Provide and place at the Contractor’s own expense, all necessary bracing and shoring in connection with demolition and removal work.
E. Remove portions of structures with care by using tools and methods that will not transfer heavy shocks to existing and adjacent building structures, both internal and external of the particular work area.
F. Provide and maintain in proper condition, suitable fire resistive dust barriers around areas where interior demolition and removal work is in progress. Dust barriers shall prevent the dust migration to adjacent areas. Remove dust barriers upon completion of major demolition and removal in the particular work area.
G. Protect unaltered portions of existing construction, including finishes, furnishings and equipment
H. Provide secure weather protection where demolition has removed a portion of the exterior envelope.
3.6 DISCOVERY OF HAZARDOUS MATERIALS
A. If hazardous materials, such as chemicals, asbestos-containing materials, or other hazardous materials are discovered during the course of the work, cease work in affected area only and immediately notify the Designer and the DCAMM Project Manager of such discovery. Do not proceed with work in such areas until instructions are issued by the Designer. Continue work in other areas.
B. If unmarked containers are discovered during the course of the work, cease work in the affected area only and immediately notify the Designer and the DCAMM Project Manager of such discovery. Do not proceed with work in such areas until instructions are issued by the Designer. Take immediate precautions to prohibit endangering the containers integrity. Continue work in other areas.
3.7 CUTTING
A. Perform all cutting of existing surfaces in a manner which will ensure a minimal difference between the cut area and new materials when patched. Use extreme care when cutting existing surfaces containing concealed utility lines which are indicated to remain and bear full responsibility for repairing or replacement of all such utilities that are accidentally damaged.
B. Provide a flush saw cut edge where pavement, curb and concrete removals abut new construction work or existing surfaces to remain undisturbed.
3.8 BLASTING
A. When blasting is allowed by DCAMM, obtain written permission and approval of method for blasting from the Designer with concurrence of the DCAMM Project Manager, Fire Chief, and local authorities before proceeding with explosive operations.
B. Notify the DCAMM Project Manager at least 48 hours before any intended blasting and do no blasting without specific written approval of each blasting operation. Conduct blasting operations using explosives of such quantity and power, and fired in such sequence and locations, as not to injure personnel or damage property, or damage adjacent work.
C. Assume full responsibility for damages resulting from or attributable to blasting operations.
D. All rock blasting shall be well covered with heavy mats or timbers chained together and the Contractor shall take great care to do no damage to existing buildings, foundations, existing roadways, glazed areas and trees to remain. Any damage caused by the work of this Contractor shall be repaired to the full satisfaction of the DCAMM Project Manager at no additional cost to DCAMM.
3.9 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Comply with requirements of Section 017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL and the following.
B. Burning: Do not burn demolished materials.
3.10 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Premises shall be left in a clean condition and ready to accept alteration work and new construction.