SECTION F: DELIVERIES OR PERFORMANCE
DELIVERABLES
Annex/ Spec Item
Form Attachment
Number Deliverable
Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.2.1.2
N/A Request to Work Outside Government’s Regular Working Hours
At least seven calendar days prior to requested day.
KO 1 As required
0200000/ 2.3.1
N/A Sign-In Sheets and Minutes
Within two working days.
KO, COR
and all attendees
1 Monthly
0200000/ 2.3.1
N/A Final Revision of Minutes
Within two working days.
KO, COR
and all attendees
1 Monthly
0200000/ 2.3.4
N/A Permits, Licenses and Certifications
Before work commences and as requested by the
KO.
KO and
COR
1 As specified
0200000/ 2.3.5
N/A Certificate of Insurance
At least 30 calendar days prior to start of contract performance and annually thereafter.
KO and
COR
1 As specified
0200000/ 2.6.1 N/A Work Reception Phone Numbers
Furnished 10 days prior to the start of the contract
KO and
COR
1 As specified
0200000/ 2.6.2
N/A Work Status Report
As Specified KO and
COR
1 Within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.
0200000/ 2.6.7.1
N/A Quality Management Plan
At least 30 calendar days prior to start of contract performance and within 15 calendar days prior to any changes.
KO and
COR
1 As specified
0200000/ 2.6.7.2
N/A QC Inspection File
Within five calendar days of completion/ termination of the contract.
KO and
COR
1 As specified
Item
Form Attachment
Number Deliverable
Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.6.7.3
J-0200000- 5B
Contractor Quality Inspection and Surveillance Report
First work day of each month.
KO and
COR
1 Monthly
0200000/ 2.7.1
N/A List of Key Personnel and Qualifications
At least 30 calendar days prior to start of contract performance.
KO and
COR
1 As specified
0200000/ 2.7.1
N/A Organizational Chart
Within 15 calendar days after award.
KO and
COR
1 As specified
0200000/ 2.7.1.4
N/A Environmental Management System Goals and Policy Measurement Information
As Specified KO and
COR
1 When Requested
0200000/ 2.7.2.6
N/A Proof of Legal Residency
Prior to be admitted to site of work.
KO and
COR
1 As specified
0200000/ 2.7.3
N/A Contractor Labor Hours (eCMRA) Report
No later than 31 October
KO and
COR
1 Annually for labor executed during the period of performance during each Government fiscal year (FY) 0200000/
2.8.1 N/A Employee
Listing Upon request. KO and
COR
1 As required
0200000/ 2.8.3
N/A Passes and Badges
As Specified KO/ Security
1 Within 10 calendar days wihen an employee leaves the Contractor’s service 0200000/
2.8.8 N/A Personnel
Security Investigation
(PSI),
Fingerprint Card (FD87), and OF-306 Declaration for Federal Employment
Prior to employee access to sensitive unclassified information.
KO/PAR/
Security Manager
1 As required
Item
Form Attachment
Number Deliverable
Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.9.1
N/A Accident Prevention Plan
At least 30 calendar days prior to start of contract performance and 15 calendar days prior to any changes.
KO and
COR
1 As specified
0200000/ 2.9.2
N/A Activity Hazard Analysis
Together with the Accident Prevention
Plan and for changes.
KO and
COR
1 As specified
0200000/ 2.9.3
N/A Compliance Plans, Programs, and Procedures
Together with the Accident Prevention
Plan and for changes.
KO and
COR
1 As specified
0200000/ 2.9.5
J-0200000- 5C
NAVFAC
Contractor Incident Reporting System (CIRS)
Within five calendar days of accident.
KO and
COR
1 As required
0200000/ 2.9.7
J-0200000- 5A
Monthly On- Site Labor Report
First work day of each month.
KO and
COR
1 Monthly
0200000/ 2.9.8
N/A OSHA Citations and Violations Corrective Action Report
Within 48 hours after receiving a citation.
KO and
COR
1 As required
0200000/ 2.9.10
N/A Safety Certifications
At least 15 calendar days prior to start of contract performance and prior to expiration of certifications.
KO and
COR
1 As specified
0200000/ 2.10.1.1
N/A Water Conservation Plan
At least 30 calendar days prior to start of contract performance and 15 calendar days prior to any changes.
KO and
COR
1 As specified
0200000/ 2.10.2.7
N/A Spill Report Within 48 hours of spill occurrence
KO and
COR
1 As required
0200000/ 2.10.2.8
N/A Emergency Planning and Community Right-To-Know Act (EPCRA) Report
At least 15 calendar days prior to start of contract performance and not less than 10 working days prior to planned use of hazardous material.
KO and
2 As specified
Item
Form Attachment
Number Deliverable
Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.10.2.8
J-0200000- 5D
Contractor Hazardous Material Inventory Log
Within 15 calendar days after the end of each calendar year and at termination of the contract.
KO and
PAR
2 Annually
0200000/ 2.10.2.12
N/A Asbestos Containing Material (ACM) Notification
As Specified KO and
COR
1 Notify the KO within one hour and follow up with written
ACM
Notification with
24 hours 0200000/
2.10.3 N/A Sustainable
Procurement and Practices Plan
At least 15 calendar days prior to start of contract performance and within 15 calendar days after exercised option periods..
KO and
COR
1 Annually
0200000/ 2.10.3
N/A Sustainable Delivery of Services Report
Within five calendar days after each contract period.
KO and
COR
1 Annually
0200000/ 2.10.3.2
N/A Recovered Material Certification
.As specified
KO and
1 When a product containing recovered materials is equal to or better than the original and could be used.
0200000/ 2.14.1
N/A Detailed Scope of Work and Detailed Estimate
Within two work days
KO and
COR
2 As required
0200000/ 2.15.2.1
N/A Non Recurring Work Proposals
Within two working days following receipt of request
KO and
COR
1 As required
1800000/2.2.1 N/A Training Plan 15 days after award/ Annually
KO and
COR
1 Annually
1800000/2.2.1 N/A Training Documentation
15 days after award/ Annually
KO and
1 Once
Item
Form Attachment
Number Deliverable
Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
1800000/2.2.2 N/A RAD CON
Training Certification
As Specified KO and
COR
1 Prior to accessing Lower
Base 1800000/2.3.1 N/A Laboratory
Accreditation and Certification
As specified KO/ Installation Env. Office
2 Prior to the start of work
1800000/2.3.2 N/A Contractor Water Testing Sampling and Analysis Plan
Within 15 calendar days after award and within seven calendar days of changes.
KO/
Installation Env. Office
1 As specified
1800000/3.1.1 N/A Sample Collection Logs
7 days after sampling
KO/
Installation Env. Office
2 As Required
1800000/3.1.1 N/A Sampling Reports
As Specified KO/ Installation Env. Office
2 IAW Contractor WSSAP and
SUBASE
Drinking Water Sampling Plans
1800000/3.1.2 N/A Field Testing Reports
7 days after testing KO/ Installation Env. Office
2 As Required
1800000/3.1.3 N/A Laboratory Analysis Reports
14 days after receipt of sample
KO/
Installation Env. Office
2 As Required
1800000/3.1.4 N/A Deviation Reports
Submitted with Sampling Reports
KO/
Installation Env. Office
2 IAW Contractor WSSAP and
SUBASE
Drinking Water Sampling Plans
1800000/3.1.5 N/A Monthly Sampling Schedule
Submitted one week prior to the month scheduled
KO/
Installation Env. Office
2 IAW Contractor WSSAP and
SUBASE
Drinking Water Sampling Plans
1800000/3.2 N/A Storm Water Monitoring Report
30 days after sample date
KO/
Installation Env. Office
2 Quarterly
1800000/3.3 N/A Wastewater Monitoring Report
As Specified KO/ Installation Env. Office
2 Monthly
1800000/3.4 N/A Drinking Water Monitoring Report
As Specified KO/ Installation Env. Office
2 Monthly