02_BRACE_ARCHITECT_SPECIFICATIONS.pdf
PDF 6 MB Posted
- Attached to
- Buckwalter Recreation Athletic Complex Expansion
- Solicitation number
- 120925
- Issued by
- Beaufort County, South Carolina
About this file
The document 02_BRACE_ARCHITECT_SPECIFICATIONS.pdf appears to be architectural specifications for the Buckwalter Recreation Athletic Complex Expansion project in Beaufort County, South Carolina. The project involves constructing a comprehensive sports and recreational facility spanning 142.91 acres, which includes four artificial turf soccer fields, a new restroom building, existing restroom renovations, parking areas, driveways, sidewalks, storm water management facilities, site and sports lighting, site furnishings, and planting and irrigation systems. The bid submission deadline is December 9, 2025, at 3:00 pm EST, with a non-mandatory virtual pre-bid conference scheduled for October 29, 2025, at 2:00 pm. The contract duration is 540 days from the Notice to Proceed, with contractors required to commence work within 15 calendar days of receiving the notice.
The project will be funded through state, federal, and/or Beaufort County appropriations, with payment structured as monthly progress payments at 90% of completed work and a 10% retainage released upon final completion. Liquidated damages are set at $600 per calendar day for project delays. The procurement includes specific requirements for small and minority business participation, requiring bidders to submit a Good Faith Efforts Checklist and a Proposed Utilization Plan. Contractors must comply with Title VI of the Civil Rights Act and provide comprehensive insurance coverage. Technical specifications follow the South Carolina Department of Transportation Standard Specifications for Highway Construction, Edition of 2025, with specific requirements for irrigation systems, including a minimum water pressure of 115 psi and comprehensive installation standards.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WP BUCKWALTER RECREATION ATHLETIC COMPLEX EXPANSION 01-21050
COURT ATKINS CONSTRUCTION DOCUMENTS 08/12/2024
TABLE OF CONTENTS 00110 - 1
SECTION 00110 - TABLE OF CONTENTS
ARCHITECTURAL, STRUCTURAL and MEP SPECIFICATIONS
(Civil Specifications contained on Civil Documents)
TABLE OF CONTENTS
PROJECT SPECIFICATIONS
Division 0 – General Requirements (Not this Project)
Division 01 – General Requirements (Not this Project)
Division 02 -- Existing Conditions
024119 - Selective Demolition
Division 03 -- Concrete
033000 - Cast-in-Place Concrete
Division 04 -- Masonry
042200 - Concrete Unit Masonry
Division 05 – Metals
050520 - Post Installed Structural Anchors
054000 - Cold Formed Metal Framing
Division 06 -- Wood, Plastics, and Composites
061000 - Rough Carpentry
061100 - Structural Wood Framing
061600 - Sheathing
061620 - Structural Wood Sheathing
Division 07 -- Thermal and Moisture Protection
072100 - Thermal Insulation
072119 - Foamed-In-Place Insulation
072726 - Fluid Applied Membrane Air Barriers
074113.16 - Standing Seam Metal Roof Panels
079200 - Joint Sealants
Division 08 - Openings
081113 - Hollow Metal Doors and Frames
083113 - Access Doors and Frames
083313 - Coiling Counter Doors
085323.13 - Hot-Rolled Steel Windows
TABLE OF CONTENTS 00110 - 2
087100 - Door Hardware
088000 - Glazing
Division 09 – Finishes
092216 - Non-Structural Metal Framing
092400 - Cement Plastering
092900 - Gypsum Board
096723 - Resinous Flooring
099113 - Exterior Painting
099123 - Interior Painting
Division 10 – Specialties
102113.19 - Phenolic Core Toilet Compartments
102800 - Toilet, Bath, And Laundry Accessories
Division 11 – Equipment (Not this Project)
Division 12 – Furnishings
123616 - Metal Countertops (Reference Architectural Drawings).
Division 13 - Special Construction (Not this Project)
Division 14 - Conveying Equipment (Not this Project)
MECHANICAL ELECTRICAL & PLUMBING
Division 22 – Plumbing
220500 - Plumbing General Provisions
220523 - Valves and Plumbing Accessories
220529 - Pipe Hangers and Supports
220576 - Cleanouts and Drains
220719 - Insulation
221116 - Domestic Water Piping
221316 - Drainage Piping
223300 - Electric, Domestic – Water Heaters
224200 - Plumbing Fixtures
224713 - Drinking Fountains
TABLE OF CONTENTS 00110 - 3
Division 23 -- Heating, Ventilating and Air Conditioning (HVAC)
230500 - Mechanical General Provisions
230593 – Testing, Adjusting & Balancing
230713 - Duct Insulation
232300 - Refrigerant Piping
233113 - Ductwork
233423 - HVAC Power Ventilators
238126 - Split System Air Conditioners
238239 – Wall and Ceiling Unit Heaters
Division 26 – Electrical
260100 - General Provisions - Electrical
260120 - Electrical Submittals
261010 - Raceway Systems and Supports
262010 - Wires and Cables, 600v and Below
262020 - Wiring Devices
262021 - Safety and Disconnect Switches
262030 - Lighting Fixtures
262042 - Panelboards
262044 - Separately Enclosed Circuit Breakers
262047 - Dry Type Transformers, 600v and Below
262049 - Surge Protection Devices
262080 - Electrical Grounding, 600v and Below
265668 - Led Sport Field Lighting System
END OF TABLE OF CONTENTS
TABLE OF CONTENTS 00110 - 4
SELECTIVE DEMOLITION 024119 - 1
SECTION 024119 – SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and any Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Demolition and removal of selected portions of building.
2. Salvage of existing items.
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.
B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and deliver to Owner.
C. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.
D. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.
E. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.
1.4 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
1.5 PREINSTALLATION MEETINGS
A. Predemolition Conference: Conduct conference at Project site.
1. Inspect and discuss condition of construction to be selectively demolished.
SELECTIVE DEMOLITION 024119 - 2
2. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.
1.6 CLOSEOUT SUBMITTALS
A. Inventory: Submit a list of items that have been removed and salvaged.
1.7 FIELD CONDITIONS
A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.
B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
1. Before selective demolition, Owner will remove the following items:
1.8 COORDINATION
A. Arrange selective demolition schedule so as not to interfere with Owner's operations.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Comply with hauling and disposal regulations of authorities having jurisdiction.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting selective demolition operations.
B. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs or video.
3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.
1. Owner will arrange to shut off indicated services/systems when requested by Contractor.
SELECTIVE DEMOLITION 024119 - 3
3.3 PROTECTION
A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.
3.4 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated.
1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping.
Temporarily cover openings to remain.
2. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.
B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
C. Existing Items to Remain: Protect construction indicated to remain against damage.
3.5 DISPOSAL OF DEMOLISHED MATERIALS
A. Remove demolition waste materials from Project site.
1. Do not allow demolished materials to accumulate on-site.
3.6 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
END OF SECTION 024119
SELECTIVE DEMOLITION 024119 - 4
WP BUCKWALTER RECREATION ATHLETIC COMPLEX EXPANSION 01-033000
CAST-IN-PLACE CONCRETE 033000 - 1
SECTION 033000 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and any Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes, for the following:
1. Footings.
2. Slabs-on-grade.
B. Products installed, but not furnished, under this Section include the following:
1. Anchor rods and embed plates indicated to be cast into cast-in-place concrete, furnished under Division 05 Section "Structural Steel Framing"
1.3 PERFORMANCE REQUIREMENTS
A. Moisture level in finished concrete shall be within limits acceptable to types of finish flooring indicated. Test methods and acceptable limits shall be as specified in Division 09 finish flooring Sections, or as required by finish flooring manufacturer's written product data or certified written statement. General Contractor is responsible for choosing and implementing methods of limiting excessive moisture during construction and curing, or remedial treatment, process, or other means to bring moisture level within acceptable limits, and for assigning and contracting for these responsibilities to installers
1.4 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of the following:
blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume; subject to compliance with requirements.
1.5 SUBMITTALS
A. Product Data:
1. Bar supports
2. Vapor retarders
3. Epoxy Bonding Adhesive
CAST-IN-PLACE CONCRETE 033000 - 2
4. Cartridge Injection Adhesive
5. Form materials
6. Form-release agents
7. Evaporation retarder
8. Curing compound
9. Curing and sealing compound
10. Floor and slab treatments
11. Semirigid joint filler
12. Joint-filler strips
13. Controlled low-strength material, including design mixture.
B. Design Mixtures: For each concrete mixture.
1. Mix design submittals shall include test results and/or trial batch data that meet or exceed the required average compressive strength as required by ACI 301.
2. Trial batches shall consist of identical cementitious materials, fine and course aggregates, and admixtures to be used for mix design.
3. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.
4. Design mixtures shall be coordinated with means of transport from point of delivery to point of placement. Allowances shall be made for changes in properties due to means of transport (from point of delivery to point of placement).
5. For mixes to be transported (i.e. pumped) from point of delivery to point of placement include a statement as to the expected property changes (i.e. unit weight and air content) from point of delivery to point of placement.
C. Steel Reinforcement Shop Drawings:
1. Drawings that detail fabrication, bending, and placement.
2. Include bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, mechanical connections, tie spacing, hoop spacing, and bar supports for concrete reinforcement.
3. Identify all step footing locations and associated reinforcing
4. Identify and dimension all grade beam and tie beam construction joints
5. Include slab on grade construction joint reinforcement
6. Construction Joint Layout: Indicate proposed construction joints required to construct the structure.
a. Location of construction joints is subject to approval of the Architect.
D. Qualification Data:
1. For ready-mix concrete manufacturer.
2. For Cartridge injection adhesive installer. Include manufacturer's training certificates or letter from manufacturer certifying training was complete with a list of individuals that were trained
E. Material Certificates: For each of the following indicating compliance with the required standards and signed by manufacturers:
1. Vapor retarders
CAST-IN-PLACE CONCRETE 033000 - 3
F. Material Test Reports: For the following, from a qualified testing agency, indicating compliance with requirements:
1. Capillary Barriers
G. Research/Evaluation Reports:
1. Submit ICC reports for the following:
a. Cartridge Injection Adhesive
H. Hot Weather Program (As required, see below):
1. Describe in detail procedure for working in Hot Weather when concrete temperatures exceed the specified limits. Included detailed description of methods, materials, and equipment to be used to comply with requirements.
I. Substitutions for Cartridge Injection Adhesive:
1. Substitution requests may only be made using products with ICC-ESR reports for the product in the specific substrate.
2. Substitution request shall include signed and sealed calculations demonstrating that the product is capable of providing equivalent performance of the specified product for each specific location and condition when calculated using the data in the referenced ESR report and in accordance with the appropriate design procedure and standards required by the building code.
3. Substitution request shall specify the diameter and embedment depth of the substituted product
4. Any increase in material cost resulting from the substitution shall be the responsibility of the contractor.
J. Minutes of preinstallation conference.
1.6 QUALITY ASSURANCE
A. Engineering Responsibility: Preparation of Shop Drawings, design calculations, and other structural data by a qualified professional engineer.
B. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated.
C. Installer Qualifications: The installer shall be experienced placing, finishing, curing, treating and protecting concrete equal in material, design and scope to that required for this project
D. Cartridge Injection Adhesive Installer Training: Conduct a thorough training session with the manufacturer's representative. Each individual responsible for the installation of anchors shall attend the training session. Training shall consist of a review of the complete process for the installation of the anchors and the use of proper equipment for drilling and installing the anchors, to include but not limited to:
CAST-IN-PLACE CONCRETE 033000 - 4
1. Hole drilling procedure. Clarify acceptability of rotary hammer drilling and/or core drilling.
2. Hole drilling equipment
3. Type and diameter of drill bits
4. Hole preparation and hole cleaning technique
5. Hole cleaning equipment
6. Adhesive injection technique
7. Adhesive injection equipment
8. Adhesive curing requirements
E. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.
1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities."
F. Testing Agency Qualifications: An independent agency qualified according to ASTM C 1077 and ASTM E 329 for testing indicated.
1. Personnel performing laboratory tests shall be ACI-certified Concrete Strength Testing Technician and Concrete Laboratory Testing Technician - Grade I. Testing Agency laboratory supervisor shall be an ACI-certified Concrete Laboratory Testing Technician - Grade II.
G. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, obtain aggregate from single source, and obtain admixtures from single source from single manufacturer.
H. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:
1. ACI 301, "Specifications for Structural Concrete," Sections 1 through 5 and Section 7, "Lightweight Concrete.”
2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials."
3. ACI 318, “Building Code Requirements for Structural Concrete”.
I. Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures.
J. Preinstallation Conference: Conduct conference at Project site.
1. Review special inspection and testing and inspecting agency procedures for field quality control, cold and hot-weather concreting procedures, curing procedures, construction contraction and isolation joints, joint-filler strips, semirigid joint fillers, forms and form removal limitations, shoring and reshoring procedures, capillary barrier requirements, vapor-retarder installation, anchor rod and anchorage device installation tolerances, steel reinforcement installation, cartridge injection adhesive installer requirements, floor and slab flatness and levelness measurement, concrete repair procedures, and concrete protection.
CAST-IN-PLACE CONCRETE 033000 - 5
1.7 DELIVERY, STORAGE, AND HANDLING
A. Steel Reinforcement:
1. Deliver, store, and handle steel reinforcement to prevent bending and damage.
2. Maintain reinforcement free of dirt and other deleterious materials.
3. Store reinforcing on dunnage or other supports up off of ground.
PART 2 - PRODUCTS
2.1 FORM-FACING MATERIALS
A. Smooth-Formed Finished Concrete: Form-facing panels that will provide continuous, true, and smooth concrete surfaces. Furnish in largest practicable sizes to minimize number of joints.
1. Plywood, metal, or other approved panel materials.
2. Exterior-grade plywood panels, suitable for concrete forms, complying with DOC PS 1, and as follows:
a. High-density overlay, Class 1 or better.
b. Medium-density overlay, Class 1 or better; mill-release agent treated and edge sealed.
c. Structural 1, B-B or better; mill oiled and edge sealed.
d. B-B (Concrete Form), Class 1 or better; mill oiled and edge sealed.
B. Chamfer Strips: Wood, metal, PVC, or rubber strips, 3/4 by 3/4 inch, minimum.
C. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.
1. Formulate form-release agent with rust inhibitor for steel form-facing materials.
D. Form Ties: Factory-fabricated, removable or snap-off metal or glass-fiber-reinforced plastic form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal.
1. Furnish units that will leave no corrodible metal closer than 1 inch to the plane of exposed concrete surface.
2. Furnish ties that, when removed, will leave holes no larger than 1 inch in diameter in concrete surface.
3. Furnish ties with integral water-barrier plates to walls indicated to receive dampproofing or waterproofing.
2.2 STEEL REINFORCEMENT
A. Reinforcing Bars:
CAST-IN-PLACE CONCRETE 033000 - 6
1. ASTM A706, deformed, Grade as indicated, Grade 60 uno.
B. Plain-Steel Wire: ASTM A 82/A 82M, as drawn.
C. Plain-Steel Welded Wire Reinforcement: ASTM A 185/A 185M, plain, fabricated from as-drawn steel wire into flat sheets.
2.3 REINFORCEMENT ACCESSORIES
A. Joint Dowel Bars: ASTM A 615/A 615M, Grade 60, plain-steel bars, cut true to length with ends square and free of burrs.
B. Bar Supports: Concrete Brick, Standees, Bolsters, chairs, spacers, supplementary reinforcing steel and other devices for spacing, supporting, and fastening reinforcing bars and welded wire reinforcement in place including measures for supporting and anchoring reinforcing intermediate and top layers of reinforcing. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows:
1. For concrete surfaces exposed to view where legs of wire bar supports contact forms, use CRSI Class 1 plastic-protected steel wire or CRSI Class 2 stainless-steel bar supports.
2. Concrete brick supports are limited to use in supporting the bottom mat of below grade foundation reinforcing steel. Concrete brick supports shall consist of solid units of unit strength equal to or greater than associated foundation concrete. Submit material test reports for approval.
C. Cartridge Injection Adhesive: A two part adhesive injection system for anchorage of new reinforcing steel to existing concrete construction.
1. Where adhesive manufacturer is not indicated, subject to compliance with requirements and acceptance by the Architect, provide the following or approved equal:
a. Hilt HIT RE 500 V3 Adhesive Anchorage System, ICC ESR-3814.
2. Where specifically indicated in the contract documents provide the following:
a. Hilti HIT –HY 200 Adhesive Anchorage System, ICC ESR-3187
2.4 CONCRETE MATERIALS
A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source, throughout Project:
1. Portland Cement: ASTM C 150, Type I, Type I/II or Type III unless noted otherwise.
Supplement with Fly Ash: ASTM C 618, Class F.
CAST-IN-PLACE CONCRETE 033000 - 7
B. Normal-Weight Aggregates: ASTM C 33, graded. Provide aggregates from a single source with documented service record data of at least 10 years' satisfactory service in similar applications and service conditions using similar aggregates and cementitious materials.
1. Coarse Aggregate
a. Maximum Coarse-Aggregate Size: 3/4 inch nominal.
b. Class: Per ASTM C33 requirements for the concrete use and region of the project
2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.
C. Water: ASTM C 94/C 94M and potable.
2.5 ADMIXTURES
A. Air-Entraining Admixture: ASTM C 260.
B. Chemical Admixtures: Provide admixtures certified by manufacturer to be compatible with other admixtures and that will not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.
1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A.
2. Retarding Admixture: ASTM C 494/C 494M, Type B.
3. Accelerating Admixture: Non-Chloride, ASTM C494/494M, Type C.
4. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D.
5. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F.
6. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type G.
7. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II.
2.6 CAPILLARY BARRIERS:.
A. A clean, compactable and trimmable granular fill with material passing the No. 200 sieve having less than 3 percent clay or friable particles. The material shall remain stable and support construction traffic and complying with one of the following:
1. A local state DOT approved road base material with 100 percent passing the 1 ½” sieve, 15 to 55 percent passing the No. 4 sieve, and less than 5% passing the No. 200 sieve.
2. A material complying with ASTM D1241, Type I with less than 5% passing the No. 200 sieve.
2.7 CURING MATERIALS
A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.
CAST-IN-PLACE CONCRETE 033000 - 8
B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.
C. Water: Potable.
D. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating, certified by curing compound manufacturer to not interfere with bonding of floor covering.
E. Clear, Waterborne, Membrane-Forming Curing and Sealing Compound: ASTM C 1315, Type 1, Class A.
2.8 RELATED MATERIALS
A. Expansion- and Isolation-Joint-Filler Strips: Provide one of the following.
1. Flexible lightweight, non-staining, polyethylene, closed cell, non-absorbent, uv stable, compressible foam with a pre-scored removable strip to allow for clean and uniform sealant joint as follows:
a. Density: ASTM D1751
b. Compression: ASTM D3575
1) 10% Deflection: 10 psi maximum
2) 80% Deflection: 126 psi maximum
c. Water absorption: ASTM D3575, 0.5% volume maximum
2. Resilient, flexible, non-extruding, asphalt-saturated cellulosic fiber with preformed cap to allow for clean and uniform sealant joint
a. Density: ASTM D 1751
B. Semirigid Joint Filler: Two-component, semirigid, 100 percent solids, epoxy resin with a Type A shore durometer hardness of 80 per ASTM D 2240.
C. Epoxy Bonding Adhesive: ASTM C 881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to suit requirements, and as follows:
1. Type V, for bonding freshly mixed concrete to hardened concrete.
2.9 CONCRETE MIXTURES, GENERAL
A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301.
1. Use a qualified independent testing agency for preparing and reporting proposed mixture designs based on laboratory trial mixtures.
CAST-IN-PLACE CONCRETE 033000 - 9
B. Compressive Strengths: Compressive strengths specified are as required for structural design.
Compressive strength provided shall be increased as required by ACI 318 for exposure class or as required for specialty treatments or finishing of concrete (i.e. polishing)
C. Air Content: Shall be adjusted as required for exposure class, specialty treatments or finishing of concrete.
D. Exposure Class: Unless noted otherwise in drawings or specifications concrete shall be considered exposure class F0, S0, W0 and C0.
E. Coordination with means of transport (from point of delivery to point of placement):
1. Design mixtures shall be coordinate with means of transport from point of delivery to point of placement. Allowances shall be made in the mix design for changes in properties due to means of transport (from point of delivery to point of placement). Specifically an allowance shall be made for loss of air entrainment due to transport methods (i.e concrete pump) when air entrainment is explicitly specified or where air entrainment is used as part of achieving lightweight concrete.
2. Coordinate with schedule of special inspections for instances in which concrete properties are to be explicitly confirmed at point of placement.
F. Admixtures: Use admixtures as noted in mix design and according to manufacturer's written instructions.
1. Use water-reducing, high-range water-reducing or plasticizing admixture in concrete, as required, for placement and workability.
2. Use water-reducing and retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions.
3. Use water-reducing admixture in pumped concrete, concrete for heavy-use industrial slabs and parking structure slabs, concrete required to be watertight, and concrete with a water-cementitious materials ratio below 0.50.
4. Use accelerating admixture in concrete as required for cold weather conditions.
2.10 CONCRETE MIXTURES FOR BUILDING ELEMENTS
A. Footings: Proportion normal-weight concrete mixture as follows:
1. Minimum Compressive Strength: 3000 psi at 28 days.
B. Slabs-on-Grade: Proportion normal-weight concrete mixture as follows:
1. Minimum Compressive Strength:
a. Typical Slabs: 3000 psi at 28 days.
b. Polished Finished Slabs: Minimum 3500 psi at 28 days, but not less than typical slab strength
CAST-IN-PLACE CONCRETE 033000 - 10
2. Dry Unit Weight: 145 lb/cu. ft. plus or minus 3 lb/cu. ft.
3. Air Content:
a. Coordinate target air content with exposure requirements
b. Maximum air content for slabs to receive trowel finish shall be 3 percent at point of placement.
4. Cementitious Materials:
a. Minimum Cementitious Materials Content: Per ACI 301 requirements based on max aggregate size
b. For slabs to receive a polished finish fly ash shall not be permitted
2.11 FABRICATING REINFORCEMENT
A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."
2.12 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M, and furnish batch ticket information.
1. Unless a detailed hot weather concrete plan incorporating the recommendations of ACI 305 has been submitted and approved comply with the following:
a. When air temperature is between 85 and 90 deg F, reduce mixing and delivery time from 1-1/2 hours to 75 minutes.
b. When air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.
PART 3 - EXECUTION
3.1 FORMWORK
A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.
B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117.
C. Limit concrete surface irregularities, designated by ACI 347 as abrupt or gradual, as follows:
1. Smooth-formed finished surfaces: Class A, 1/8 inch
2. Rough-formed finished surfaces: Class D, 1 inch
D. Construct forms tight enough to prevent loss of concrete mortar.
CAST-IN-PLACE CONCRETE 033000 - 11
E. Fabricate forms for easy removal without hammering or prying against concrete surfaces. Provide crush or wrecking plates where stripping may damage cast concrete surfaces. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.
1. Install keyways, reglets, recesses, and the like, for easy removal.
2. Do not use rust-stained steel form-facing material.
F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds.
G. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.
H. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work. Determine sizes and locations from trades providing such items.
I. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.
J. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.
K. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.
3.2 EMBEDDED ITEMS
A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.
1. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of AISC's "Code of Standard Practice for Steel Buildings and Bridges."
2. Anchor rods and embeds shall be securely fastened in formwork prior to placing concrete, and concrete vibrated around the anchor or embed to ensure proper flow of concrete around anchors and embeds.
3.3 REMOVING AND REUSING FORMS
A. General: Formwork for sides of beams, walls, columns, and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F for 24 hours after placing concrete. Concrete has to be hard enough to not be damaged by form-removal operations and curing and protection operations need to be maintained.
CAST-IN-PLACE CONCRETE 033000 - 12
1. Leave formwork for beam soffits, joists, slabs, and other structural elements that supports weight of concrete in place until concrete has achieved its 28-day design compressive strength.
2. Remove forms only if shores have been arranged to permit removal of forms without loosening or disturbing shores.
B. Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated, or otherwise damaged form-facing material will not be acceptable for exposed surfaces. Apply new form-release agent.
C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints. Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete surfaces unless approved by Architect.
3.4 CAPILLARY BARRIERS:
A. General: Place capillary barrier on compacted subgraded beneath vapor retarder for all slabs on grade unless noted otherwise.
1. Compact capillary barrier with mechanical equipment to an elevation tolerance of plus 0 and minus ¾ inch.
2. Capillary barriers are not required where mud slabs and below slab sheet waterproofing are indicated.
3. Ensure surface of capillary barrier is uniform to prevent damage to vapor retarders.
4. Ensure capillary barrier is compacted to a uniform surface free of ruts, divots or other anomalies from construction traffic. Repair any anomalies immediately prior to concrete placement.
3.5 STEEL REINFORCEMENT
A. General: Comply with CRSI's "Manual of Standard Practice" for placing reinforcement.
1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.
B. Clean reinforcement of loose rust and mill scale, earth, ice, and other foreign materials that would reduce bond to concrete.
C. Anchorage of reinforcement into hardened concrete using cartridge injection adhesive anchors shall only be used where specifically indicated on plans or with written direction from the Engineer of Record for a specific location.
D. Accurately position, support, and secure reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars.
1. Foundation reinforcing steel may be supported on solid concrete brick units of strength equal to or greater than foundation concrete.
CAST-IN-PLACE CONCRETE 033000 - 13
E. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.
F. Welded Wire Reinforcement:
1. Install welded wire reinforcement in longest practicable lengths
2. Locate welded wire reinforcement in top 1/3 of slab on grades unless noted otherwise
3. Locate welded wire reinforcement at mid-depth of concrete slab thickness over deck flutes unless noted otherwise.
4. Lap edges and ends of adjoining sheets at least one mesh spacing plus 2”, but not less than 6”.
Lace overlaps with wire.
5. Slabs on Grade 4” or less in thickness: Support welded wire reinforcement on chairs, bolsters or bar supports spaced to minimize sagging, and as required to support construction traffic
a. Alternately, welded wire reinforcement may be placed on grade and “hooked”/pulled to the proper location
b. Placement of welded wire reinforcement after placement of concrete and “walking in” is not permitted.
6. Slabs on Grade greater than 4” in thickness: Support welded wire reinforcement on chairs, bolsters or bar supports spaced to minimize sagging, and as required to support construction traffic
a. Placement of welded wire reinforcement on grade or deck and “hooked”/pulled up into slab as concrete is placed is not permitted.
b. Placement of welded wire reinforcement after placement of concrete and “walking in” is not permitted.
7. Elevated slabs: Support welded wire reinforcement on chairs, bolsters or bar supports spaced to minimize sagging, and as required to support construction traffic
a. Alternately, welded wire reinforcement may be placed on grade and “hooked”/pulled to the proper location
b. Placement of welded wire reinforcement after placement of concrete and “walking in” is not permitted.
3.6 CARTRIDGE INJECTION ADHESIVE
A. Where manufacturer recommends the use of special tools for installation of anchors, such tools shall be used.
B. All facets of hole drilling, hole cleaning, anchor installation, anchor torqueing shall be in strict accordance with the ICC-ESR report and manufacturer’s data.
C. Drill holes perpendicular to substrate surface.
D. Drill holes with rotary impact hammer drills using carbide-tipped bits or core drills using diamond core bits as indicated in the ICC-ESR report.
CAST-IN-PLACE CONCRETE 033000 - 14
E. Drill bits and core bits shall be of diameters indicated in the ICC-ESR report.
F. All holes shall be cleaned with compressed air to remove all drilling dust and other deleterious substances.
G. Remove water from holes to attain a surface dry condition unless specifically permitted otherwise by ICC-ESR report.
H. Base Material Strength: Unless otherwise specified, do not drill holes in concrete or masonry until concrete has achieved full design strength.
I. Hilti HIT-HY200 system adhesive shall be installed using the Hilti Safe Set Technology.
1. The Hilti hollow drill bit and Hilt vacuum system shall be employed.
J. Embedded Items: Identify position of reinforcing steel and other embedded items prior to drilling holes for anchors. Exercise care in coring or drilling to avoid damaging existing reinforcing or embedded items. Notify the Engineer if reinforcing steel or other embedded items are encountered during drilling. Take precautions as necessary to avoid damaging prestressing tendons, electrical and telecommunications conduit, and gas lines.
K. Inject adhesive into holes proceeding from the bottom of the hole and progressing toward the surface in such a manner as to avoid introduction of air pockets in the adhesive.
L. Follow manufacturer recommendations to ensure proper mixing of adhesive components.
M. Sufficient adhesive shall be injected in the hole to ensure that the annular gap is filled to the surface.
N. Remove excess adhesive from the surface.
O. Shim reinforcement with suitable device to center the reinforcement in the hole.
P. Do not disturb or load reinforcment before manufacturer specified cure time has elapsed.
Q. Observe manufacturer recommendations with respect to installation temperatures.
3.7 JOINTS
A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.
B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Architect.
1. Place joints perpendicular to main reinforcement.
2. Continue reinforcement across construction joints unless otherwise indicated.
3. Provide supplemental reinforcing and/or smooth dowels where indicated at joints.
4. Strip bulkheads from footings, beams, grade beams, tie beams, and slabs and roughen surface of concrete to a minimum 1/4" amplitude while concrete is still plastic.
CAST-IN-PLACE CONCRETE 033000 - 15
5. Form keyed joints unless indicated otherwise. Embed keys at least 1-1/2 inches into concrete unless noted otherwise.
6. Locate joints for beams, slabs, joists, and girders in the middle third of spans. Offset joints in girders a minimum distance of twice the beam width from a beam-girder intersection.
7. Locate joints in slabs on steel deck as follows:
a. Joints parallel to joists (perpendicular to girders) shall be located at the midpoint between two adjacent joists.
b. Joints parallel to girders (perpendicular to joists) shall be located at the midpoint of two adjacent girders.
c. Stagger and offset joints as required to meet the requirements.
8. Locate horizontal joints in walls and columns at underside of floors, slabs, beams, and girders and at the top of footings or floor slabs.
9. Space vertical joints in walls as indicated. Locate joints beside piers integral with walls, near corners, and in concealed locations where possible.
10. Use epoxy-bonding adhesive at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces.
C. Contraction Joints in Slabs-on-Grade: Form weakened-plane contraction joints, sectioning concrete into areas as indicated. Construct contraction joints for a depth equal to at least [one-fourth of concrete thickness as follows:
1. Grooved Joints: Form contraction joints after initial floating by grooving and finishing each edge of joint to a radius of 1/8 inch. Repeat grooving of contraction joints after applying surface finishes. Eliminate groover tool marks on concrete surfaces.
2. Sawed Joints: Form contraction joints with power saws equipped with shatterproof abrasive or diamond-rimmed blades. Cut 1/8-inch wide joints into concrete.
a. Cut joints as soon as cutting action will not tear, abrade, or otherwise damage surface , but not more than 12 hours after finished, and before concrete develops random contraction cracks.
3.8 CONCRETE PLACEMENT
A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections have been performed.
B. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301 and as follows.
1. Do not add water to concrete unless the batched water is specifically noted as less than the mix design and is indicated as such on the batch ticket.
2. Do not add more water than the amount of withheld water which is specifically identified on the batch ticket.
3. Do not add water to concrete after adding high-range water-reducing admixtures to mixture.
CAST-IN-PLACE CONCRETE 033000 - 16
C. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete will be placed on concrete that has hardened enough to cause seams or planes of weakness.
If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.
1. Deposit concrete in horizontal layers of depth to not exceed formwork design pressures and in a manner to avoid inclined construction joints.
2. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301.
3. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations to rapidly penetrate placed layer and at least 6 inches into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to lose plasticity. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mixture constituents to segregate.
D. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.
1. Consolidate concrete during placement operations so concrete is thoroughly worked around reinforcement and other embedded items and into corners.
2. Maintain reinforcement in position on chairs during concrete placement.
3. Screed slab surfaces with a straightedge and strike off to correct elevations.
4. Slope surfaces uniformly to drains where required.
5. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane, before excess bleedwater appears on the surface. Do not further disturb slab surfaces before starting finishing operations.
E. Concrete placed over metal deck shall be placed and screeded level and flat to the specified tolerances, maintaining at least the minimum specified slab thickness as shown on drawings. The contractor shall increase slab thickness as required to compensate for metal deck deflection, residual beam camber and beam deflection in order to achieve a level and flat floor within the specified tolerance.
F. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.
1. When average high and low temperature is expected to fall below 40 deg F for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301.
2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.
3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.
G. Hot-Weather Placement: Comply with ACI 305.1 and as follows:
1. Maintain concrete temperature below 90 deg F at time of placement unless a detailed hot weather concrete plan incorporating the recommendations of ACI 305.1 has been
CAST-IN-PLACE CONCRETE 033000 - 17
submitted and approved. At no time shall concrete temperature exceed 95 deg F at time of placement.
2. Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option.
3. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete. Keep subgrade uniformly moist without standing water, soft spots, or dry areas.
3.9 FINISHING FORMED SURFACES
A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defects repaired and patched. Remove fins and other projections that exceed specified limits on formed-surface irregularities.
1. Apply to concrete surfaces not exposed to public view
B. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defects.
Remove fins and other projections that exceed specified limits on formed-surface irregularities.
1. Apply to concrete surfaces exposed to public view, to be covered with a coating or covering material applied directly to concrete coordinate with Architectural drawings and specifications.
3.10 FINISHING FLOORS AND SLABS
A. General: Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.
B. Scratch Finish: While still plastic, texture concrete surface that has been screeded and bull-floated or darbied. Use stiff brushes, brooms, or rakes to produce a profile amplitude of 1/4 inch in one direction.
1. Apply scratch finish to surfaces to receive concrete floor toppings or to receive mortar setting beds for bonded cementitious floor finishes.
C. Float Finish: Consolidate surface with power-driven floats or by hand floating if area is small or inaccessible to power driven floats. Restraighten, cut down high spots, and fill low spots. Repeat float passes and restraightening until surface is left with a uniform, smooth, granular texture.
1. Apply float finish to surfaces to receive trowel finish, trowel and fine broom finish, or to be covered with fluid-applied or sheet waterproofing, built-up or membrane roofing, or sand-bed terrazzo.
2. Apply to mud slabs.
CAST-IN-PLACE CONCRETE 033000 - 18
D. Trowel Finish: After applying float finish, apply first troweling and consolidate concrete by hand or power-driven trowel. Continue troweling passes and restraighten until surface is free of trowel marks and uniform in texture and appearance. Grind smooth any surface defects that would telegraph through applied coatings or floor coverings.
1. Apply a trowel finish to surfaces to be covered with resilient flooring, carpet, ceramic or quarry tile set over a cleavage membrane, paint, epoxy terrazzo, polished or another thin-film-finish coating system.
E. Trowel and Fine-Broom Finish: Apply a first trowel finish to surfaces where ceramic or quarry tile is to be installed by either thickset or thin-set method without cleavage membrane. While concrete is still plastic, slightly scarify surface with a fine broom.
1. Comply with flatness and levelness tolerances for trowel-finished floor surfaces.
F. Broom Finish: Apply a broom finish to exterior concrete platforms, steps, ramps, and elsewhere as indicated.
1. Immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route. Coordinate required final finish with Architect before application.
3.11 MISCELLANEOUS CONCRETE ITEMS
A. Filling In: Fill in holes and openings left in concrete structures after work of other trades is in place unless otherwise indicated. Mix, place, and cure concrete, as specified, to blend with in-place construction. Provide other miscellaneous concrete filling indicated or required to complete the Work.
B. Curbs: Provide monolithic finish to interior curbs by stripping forms while concrete is still green and by steel-troweling surfaces to a hard, dense finish with corners, intersections, and terminations slightly rounded.
C. Equipment Bases and Foundations: Provide machine and equipment bases and foundations as shown on Drawings. Set anchor bolts for machines and equipment at correct elevations, complying with diagrams or templates from manufacturer furnishing machines and equipment.
D. Steel Pan Stairs: Provide concrete fill for steel pan stair treads, landings, and associated items. Cast-in inserts and accessories as shown on Drawings. Screed, tamp, and trowel finish concrete surfaces.
3.12 CONCRETE PROTECTING AND CURING
A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and ACI 301 for hot-weather protection during curing.
CAST-IN-PLACE CONCRETE 033000 - 19
B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations.
Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.
C. Formed Surfaces: Cure formed concrete surfaces, including underside of beams, supported slabs, and other similar surfaces. If forms remain during curing period, moist cure after loosening forms. If removing forms before end of curing period, continue curing for the remainder of the curing period.
D. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including floors and slabs, concrete floor toppings, and other surfaces.
E. Foundations:
1. Protect top sides of footings to receive masonry or concrete construction from dirt and debris.
2. Excavations:
a. Do not allow excavations directly adjacent to or beneath footings to the absolute greatest extent possible.
b. Where excavations must occur beneath in place footings or slabs the area shall be careful excavated as to not damage…