Second High Reservoir Maintenance and Improvements, Washington Aqueduct, Washington DC
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- W912DR22B0007
- Agency
-
ENDIST Baltimore
US Army Corps of Engineers, Department of Defense
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237110 Water and Sewer Line and Related Structures Construction
- Place of performance
- Washington, District of Columbia 20016, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Army Corps of Engineers, Baltimore District seeks to award a firm-fixed-price construction contract to implement upgrades and improvements to the Second High Reservoir in Washington, D.C. The solicitation seeks replacement of the brick sample building, installation of mechanical mixers and communication equipment, sealing of interior joints and cracks, replacement of the 24-inch drain line and perimeter fence, and addition of a roof sub-drainage system. Bids are due by May 25, 2022 and will be evaluated for price and technical compliance with the solicitation. Any questions regarding the solicitation must be submitted by May 15, 2022.
There is no set-aside designation. The primary NAICS code is 237110 and PSC code is C-41. The incumbent contractor is unknown. The government estimate is $5-7 million to complete the upgrades over a 462 calendar day period, with work restricted to the November 1 through March 31 timeframe to minimize water service disruptions. The place of performance is the Second High Reservoir facility located at Van Ness Street and 44th Street NW in Washington, D.C.
Notice text
2 versions
Update #2 · Latest ·
PROJECT DESCRIPTION:
The U.S. Army Corps of Engineers, Baltimore District (NAB), has been tasked to solicit for and award construction services for Reservoir Maintenance and Improvements at Washington Aqueduct Division in Washington, DC. The proposed project will be a competitive, firm-fixed-price, contract procured in accordance with FAR 14, Sealed Bidding, via an Invitation for Bid (IFB).
The Washington Aqueduct provides potable water to approximately one million people in the District of Columbia and Northern Virginia. As part of the water treatment and supply system, the Washington Aqueduct maintains and operates the Dalecarlia and McMillan Water Treatment Plants (WTPs). Potable water from these WTPs is pumped via the second high service to the Second High Reservoir. This reservoir is an approximate 419 LF x 294 LF subsurface structure that is 24 feet deep that was built in 1931. It has a capacity of 15 MG and is located at the intersection of Van Ness Street and 44th Street, NW, Washington. DC.
The project consists of implementing upgrades and improvements to the Second High Reservoir to address operational and sanitary survey issues previously identified. This will result in improved water quality and operation within the distribution system. The work includes the replacement of a brick Sample Building; the replacement of the 24” drain line; installation of mechanical mixers; sealing of all interior joints and cracks; installation of a spread spectrum radio communications antenna; installation of a roof sub-drainage system and the replacement of the perimeter fence. This reservoir is a critical component of the distribution system and so the reservoir outage period is restricted.
May 25, 2022 - Attached Bid Abstract
Update #1 ·
PROJECT DESCRIPTION:
The U.S. Army Corps of Engineers, Baltimore District (NAB), has been tasked to solicit for and award construction services for Reservoir Maintenance and Improvements at Washington Aqueduct Division in Washington, DC. The proposed project will be a competitive, firm-fixed-price, contract procured in accordance with FAR 14, Sealed Bidding, via an Invitation for Bid (IFB).
The Washington Aqueduct provides potable water to approximately one million people in the District of Columbia and Northern Virginia. As part of the water treatment and supply system, the Washington Aqueduct maintains and operates the Dalecarlia and McMillan Water Treatment Plants (WTPs). Potable water from these WTPs is pumped via the second high service to the Second High Reservoir. This reservoir is an approximate 419 LF x 294 LF subsurface structure that is 24 feet deep that was built in 1931. It has a capacity of 15 MG and is located at the intersection of Van Ness Street and 44th Street, NW, Washington. DC.
The project consists of implementing upgrades and improvements to the Second High Reservoir to address operational and sanitary survey issues previously identified. This will result in improved water quality and operation within the distribution system. The work includes the replacement of a brick Sample Building; the replacement of the 24” drain line; installation of mechanical mixers; sealing of all interior joints and cracks; installation of a spread spectrum radio communications antenna; installation of a roof sub-drainage system and the replacement of the perimeter fence. This reservoir is a critical component of the distribution system and so the reservoir outage period is restricted.
Files
Show all 25
Notice history
| Notice | Type | Posted |
|---|---|---|
| Second High Reservoir Maintenance and Improvements, Washington Aqueduct, Washington DC | Award Notice | |
| This notice | Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| HAVO 326181 Rehabilitate Rainshed&Water Treatment | National Office | No set-aside |