This solicitation document requests proposals for maintenance and improvement services at the Second High Reservoir in Washington, DC. The U.S. Army Corps of Engineers, Baltimore District seeks a firm-fixed price contract to replace the brick Sample Building, replace the 24-inch drain line, install mechanical mixers, seal interior joints and cracks, install a spread spectrum radio communications antenna, install a roof sub-drainage system, and replace the perimeter fence. The reservoir outage period is restricted to November 1st through March 31st and must not exceed 90 calendar days. Proposals are due by the date specified in solicitation number W912DR22B0007. The selected contractor will be responsible for necessary permitting, erosion and sediment control, security, and coordination with the Washington Aqueduct to drain and refill the reservoir.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAWING NUMBER PLATE
SCALE: DATE: SHEET:
WASHINGTON AQUEDUCT
WASHINGTON, DC
MAINTENANCE AND IMPROVEMENTS
MARCH 2022
SECOND HIGH RESERVOIR
Nova Consulting
U.S. ARMY ENGINEER DISTRICT, BALTIMORE
CORPS OF ENGINEERS
BALTIMORE, MARYLAND
STEVEN S. EAGLE, PE
NO SCALE
80.2-2.7-03 03
G-03
GENERAL
GENERAL NOTES
GENERAL NOTES
1. REFER TO CIVIL, STRUCTURAL, MECHANICAL, AND ELECTRICAL DRAWINGS FOR
ADDITIONAL GENERAL NOTES, ABBREVIATION AND SYMBOLS.
2. MATERIALS AND SYSTEMS NOTES ARE TYPICAL IN NATURE AND APPLY TO
MULTIPLE DRAWINGS. NOTES ON ANY DRAWING ARE TO BE APPLIED TO ALL
SIMILAR MATERIALS AND SYSTEMS UNLESS NOTED OTHERWISE.
3. ACTUAL SITE CONDITIONS MAY DIFFER FROM THOSE SHOWN ON THE DRAWINGS.
CONTACT THE GOVERNMENT IF A DISCREPANCY IS FOUND.
4. EXISTING UTILITY LOCATIONS AND PROPOSED EASEMENT AND RIGHT-OF-WAY
BOUNDARIES ARE APPROXIMATE ONLY AND ARE BASED ON BEST AVAILABLE
DATA. CONTRACTOR SHALL FIELD VERIFY THESE LOCATIONS AND ELEVATIONS,
AND IDENTIFY ANY UTILITIES NOT SHOWN IN THE DRAWINGS BEFORE
COMMENCING THE WORK. CONTACT MISS UTILITY AT 1-800-257-7777 AND
WASHINGTON AQUEDUCT FOR FIELD LOCATION OF EXISTING UTILITIES. THE
CONTRACTOR SHALL NOTIFY THE OWNER PRIOR TO THE BEGINNING OF ANY
CONSTRUCTION.
5. ALL DIMENSIONS AND ELEVATIONS SHOWN AND ALL EXISTING CONDITIONS ARE
APPROXIMATE AND SHALL BE VERIFIED BY THE CONTRACTOR PRIOR TO
STARTING WORK. THE CONTRACTOR SHALL VISIT THE SITE AND FAMILIARIZE
HIMSELF WITH ALL EXISTING CONDITIONS PRIOR TO BIDDING WORK.
6. IN CASE OF DISCREPANCIES BETWEEN DIMENSIONS AND SCALE, DIMENSIONS
GOVERN. DO NOT SCALE DRAWINGS.
7. THE CONTRACTOR SHALL PROTECT EXISTING TREES AS NECESSARY AND ONLY
REMOVE MARKED TREES OR AS DIRECTED BY THE GOVERNMENT. CONTRACTOR
SHALL NOT REMOVE ANY TREES UNTIL SPECIFIC APPROVAL FROM THE
GOVERNMENT HAS BEEN RECEIVED. CONTRACTOR SHALL BE RESPONSIBLE FOR
APPLYING AND OBTAINING ANY REQUIRED PERMIT.
8. WORK SHALL BE PERFORMED IN AN EXPEDITED MANNER SO AS TO MINIMIZE THE
TIME THE RESERVOIR IS OUT OF SERVICE.THE CONTRACTOR SHALL PLAN ALL
WORK TO BE COMPLETED DURING RESERVOIR OUTAGE, INCLUDING BUT NOT
LIMITED TO WORK ASSOCIATED WITH SAMPLE BUILDING, DRAINING, INSPECTIONS,
REPAIRS, OPERATIONAL TESTING UNDER WET CONDITIONS AND PUNCH LIST
ITEMS TO BE COMPLETED IN THE LOW DEMAND PERIOD (BETWEEN NOVEMBER
1ST TO MARCH 31ST, BOTH INCLUSIVE) SO THAT THE RESERVOIR IS OUT OF
SERVICE FOR NO MORE THAN NINETY (90) CALENDAR DAYS. THERE CAN ONLY BE
ONE RESERVOIR OUTAGE AND THE CONTRACTOR SHALL ENSURE THAT ALL WORK
INSIDE THE RESERVOIR INCLUDING PREFINAL AND FINAL INSPECTION BY THE
GOVERNMENT IS PERFORMED DURING THIS SINGLE OUTAGE
9. CONTRACTOR SHALL REQUEST CONTRACTING OFFICER REPRESENTATIVE TO
CONTACT DC WATER AT LEAST THIRTY (30) CALENDAR DAYS IN ADVANCE IN
ORDER TO REMOVE ANTENNA PRIOR TO THE DEMOLITION OF THE SAMPLE
BUILDING.
10. PRIOR TO COMMENCING WORK TO DEMOLISH THE SAMPLE BUILDING, THE
CONTRACTOR SHALL PROVIDE THE GOVERNMENT SIXTY (60) CALENDAR DAYS
NOTICE.
11. CONTRACTOR SHALL PAY ALL COSTS INCURRED IN CONNECTING, CONVERTING,
AND TRANSFERRING THE UTILITIES TO THE WORK, INCLUDING BUT NOT LIMITED
TO PROVIDING BACKFLOW-PREVENTING DEVICES ON CONNECTIONS TO
DOMESTIC WATER LINES; PROVIDING METERS; AND PROVIDING TRANSFORMERS;
AND MAKING DISCONNECTIONS. CONTRACTOR SHALL NOT TAP TO CITY FIRE
HYDRANTS FOR OBTAINING DOMESTIC WATER AND IS RESPONSIBLE FOR HIS OWN
WATER SUPPLY IF NEEDED. THE CONTRACTOR IS RESPONSIBLE PROCURING DC
WATER HYDRANT USE AND TRAFFIC USE PERMITS TO RUN HOSES TO THE
NEAREST HYDRANT.
12. CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING WATER DISCHARGE
PERMIT FOR CONSTRUCTION WASH WATER FROM DCWATER. IN CASE RESERVOIR
DRAIN WATER HAS TO BE DISCHARGED INTO THE STORM SEWER, CONTRACTOR
SHALL ENSURE THAT IT MEETS THE WA GENERAL NPDES REQUIREMENTS.
CONTRACTOR IS RESPONSIBLE FOR SAMPLING AND TESTING REQUIREMENTS AS
DESCRIBED IN SPECIFICATION 01 57 19.
13. CONTRACTOR SHALL COORDINATE THE DRAINING AND THE SUPPLY OF FINISHED
WATER NECESSARY FOR FILLING, TESTING AND START-UP OF THE RESERVOIR
WITH THE WASHINGTON AQUEDUCT, AT LEAST THIRTY (30) CALENDAR DAYS IN
ADVANCE.
14. CONTRACTOR SHALL PROVIDE PERIMETER SITE SECURITY THROUGHOUT
CONSTRUCTION. AT A MINIMUM, CONTRACTOR SHALL INSTALL TEMPORARY
FENCING AND SIGNS ALONG LIMITS OF DISTURBANCE, WHERE EXISTING FENCE
HAS BEEN REMOVED FOR CONSTRUCTION ACTIVITIES OR AS DIRECTED BY THE
GOVERNMENT. TEMPORARY FENCING SHALL BE A SPECIFIC COMPONENT OF THE
CONTRACTOR'S WORK PLAN SUBMITTAL.
15. THE PROPOSED STAGING AREA AS SHOWN ON SHEET C-01 HAS TREES THAT
SHALL BE PROTECTED AT ALL TIMES. IF ADDITIONAL AREA IS REQUIRED, THE
CONTRACTOR MAY UTILIZE AREAS WITHIN THE PROPERTY LIMITS WITH PRIOR
APPROVAL FROM THE WASHINGTON AQUEDUCT. IF OFF-SITE STAGING AREA IS
REQUIRED FOR THE CONTRACTOR’S STAGING NEEDS, THEN THE CONTRACTOR
SHALL MAKE ALL NECESSARY ARRANGEMENTS AT NO ADDITIONAL COST TO THE
WASHINGTON AQUEDUCT.
16. CONTRACTOR SHALL CONFIRM THE BOUNDARY OF PROPERTY OWNERSHIP BY
THE WASHINGTON AQUEDUCT AND MAINTAIN ALL CONSTRUCTION ACTIVITIES
WITHIN THAT BOUNDARY.
17. IF EXISTING FACILITIES OR ANY PRIVATE OR GOVERNMENT PROPERTY IS
DAMAGED DURING THE COURSE OF THE WORK, THE CONTRACTOR SHALL REPAIR
TO THE SATISFACTION OF THE OWNER AT NO EXTRA COST TO THE GOVERNMENT.
18. ALL WORK SHALL CONFORM TO ALL APPLICABLE CODES, STANDARDS, AND
GOVERNING AUTHORITIES.
19. ALL CONCRETE REPAIR MATERIALS AND OTHER PRODUCTS USED FOR WORK
WITHIN THE RESERVOIR SHALL CONFORM TO NSF/ANSI 61 FOR CONTACT WITH
POTABLE WATER SUPPLIES.
20. THE ARCHITECT'S SELECTION OF FENCE MATERIALS AND DETAILS DOES NOT
RELIEVE THE CONTRACTOR FROM VERIFYING WITH THE FENCE MATERIAL
SUPPLIERS THAT THE PROPOSED FENCE MATERIALS ARE CORRECT AND PROPER
FOR THE INTENDED APPLICATION AND USE. PRIOR COORDINATION SHALL BE
MADE WITH THE WASHINGTON AQUEDUCT CHIEF OF SECURITY AND LAW
ENFORCEMENT ABOUT THE LATEST REQUIREMENTS FOR FENCE, CAMERA
SYSTEM AND RELATED WORK.
21. PROVIDE ACCESS PANELS REQUIRED FOR MECHANICAL, ELECTRICAL, PLUMBING,
AND FIRE PROTECTION EQUIPMENT.
22. CONTRACTOR SHALL KEEP THE ROADWAYS CLEAR AND CLEAN OF
CONSTRUCTION DEBRIS AND EQUIPMENT.
23. CONTRACTOR SHALL NOT STORE UNNECESSARY MATERIALS OR EQUIPMENT ON
THE JOB SITE AND SHALL TAKE CARE TO PREVENT ANY STRUCTURE FROM BEING
LOADED WITH A WEIGHT WHICH WILL ENDANGER ITS SECURITY OR THE SAFETY
OF PERSONS.
24. THE CONTRACTOR WORK SHALL COMPLY WITH LIMITS SPECIFIED IN THE DC NOISE
ORDINANCE.
25. UPON COMPLETION OF THE WORK, THE CONTRACTOR IS RESPONSIBLE FOR
REMOVING ALL MATERIAL, EQUIPMENT AND DEBRIS, AND RESTORING THE SITE TO
ITS ORIGINAL CONDITION.
26. THE CONTRACTOR SHALL PLAN FOR LEAKAGE THROUGH VALVES, JOINT LEAKS IN
MAINS, ROOF AND WALLS, AND SHALL HAVE THE NECESSARY PUMPS AND LINES
AVAILABLE SO AS NOT TO ALLOW ANY LEAKAGE TO IMPEDE PROJECT PROGRESS.
27. IT HAS BEEN DETERMINED THAT THE RESERVOIR HAS INFILTRATION WHEN IT IS
EMPTY. THE CONTRACTOR SHALL ASSUME WET WORKING CONDITIONS INSIDE
THE RESERVOIR.
28. THE CONTRACTOR SHALL PROCURE ALL NECESSARY PERMITS FOR STREET
OPENINGS, TRAFFIC CONTROL, AND SEDIMENT AND EROSION CONTROL RELATED
TO PERFORMING EXCAVATION IN THE VICINITY OF THE RESERVOIR FOR WORK
UNDER THIS CONTRACT. THE CONTRACTOR SHALL COMPLY WITH THE
PROVISIONS OF THESE PERMITS.
29. THE ACQUISITION OF A DDOT/URBAN FORESTRY DIVISION SPECIAL TREE
REMOVAL PERMIT MAY BE REQUIRED FOR ANY TREE REMOVAL. THE REMOVAL OF
TREES GREATER OR EQUAL TO 100 INCHES IN CIRCUMFERENCE IS PROHIBITED.
30. ALL EROSION CONTROL MEASURES SHALL BE INSPECTED IMMEDIATELY
FOLLOWING INITIAL INSTALLATION, WEEKLY THEREAFTER, AND WITHIN 24 HOURS
AFTER A RAINFALL EVENT PRODUCING 1/2 INCH OR GREATER OF RAIN. MEASURES
SHALL BE REPAIRED OR REPLACED AS NECESSARY.
PROJECT DESCRIPTION
THE PROJECT INVOLVES MAINTENANCE AND IMPROVEMENTS WORK TO THE SECOND
HIGH RESERVOIR. THE CONTRACTOR SHALL PROCURE ALL NECESSARY PERMITS FOR
STREET OPENINGS, TRAFFIC CONTROL, EROSION AND SEDIMENT CONTROL AND ANY
OTHER WORK RELATED TO PERFORMING WORK UNDER THIS CONTRACT. THE
CONTRACTOR SHALL COMPLY WITH THE PROVISIONS OF THESE PERMITS AT ALL
TIMES. THE CONTRACTOR SHALL ALSO BE RESPONSIBLE FOR INSTALLING
TEMPORARY CONSTRUCTION ENTRANCE, TREE PROTECTION FENCE, ALL PERIMETER
SOIL EROSION AND SEDIMENT CONTROL DEVICES, AND SILT FENCE AS SHOWN ON
PLAN PRIOR TO ANY SITE DISTURBANCE OR CONSTRUCTION. THE MAJOR FEATURES
OF THIS PROJECT INCLUDE THE FOLLOWING:
1. SITE WORK INCLUDING BUT NOT LIMITED TO INSTALLATION OF SUB-DRAINAGE
SYSTEM ON TOP OF THE ROOF WITH DRAIN INTO AIR-GAP CHAMBER,
CONNECTION OF SUBDRAIN SYSTEM TO 8-INCH PVC DRAIN AND ELECTRICAL SITE
WORK.
2. DEMOLITION OF EXISTING AND INSTALLATION OF NEW 24-INCH TERRA COTTA
DRAIN LINE, VALVE, STEM AND ACTUATOR AND ADDITION OF A REDUNDANT
DRAIN VALVE ON NEW 24-INCH DRAIN LINE OUTSIDE RESERVOIR.
3. DEMOLITION OF EXISTING AND CONSTRUCTION OF NEW SAMPLE BUILDING
CONSISTING OF TWO COMPARTMENTS. ONE COMPARTMENT SHALL BE
MECHANICALLY VENTILATED AND DESIGNED TO BE FREE OF CHLORINE FUMES
AND HOUSE THE SCADA, ELECTRICAL AND SECURITY EQUIPMENT, AND THE
OTHER COMPARTMENT SHALL CONTAIN THE ACCESS HATCHES AND HOUSE
SAMPLING EQUIPMENT. THE NEW SAMPLE BUILDING SHALL HAVE NO
ATTACHMENTS AND ALL PENETRATIONS SHALL BE SUBSURFACE.
4. REPAIR WORK ASSOCIATED WITH EXISTING AREA ON THE WEST SIDE OF THE
RESERVOIR INCLUDING BUT NOT LIMITED TO FILLING WITH SUITABLE MATERIAL
TO MATCH PROPOSED GRADE AND PLACING SOD.
5. JOINT STRUCTURAL INSPECTION OF THE INTERIOR OF THE RESERVOIR WITH THE
WASHINGTON AQUEDUCT AND THEIR A/E FIRM.CONTRACTOR SHALL BE
RESPONSIBLE FOR ALL SECURITY AND SAFETY PROTOCOLS FOR WORK WITHIN A
CONFINED SPACE. ENTRY SPACE INCLUDING BUT NOT LIMITED TO AIR
MONITORING, CSE, BLOWERS, ETC, NEEDED TO PERFORM THIS INSPECTION. THIS
INSPECTION SHALL BE COORDINATED WITH THE GOVERNMENT AT LEAST FIFTEEN
(15) CALENDAR DAYS IN ADVANCE AND SHALL TAKE PLACE AS SOON AS THE
RESERVOIR IS TAKEN OUT OF SERVICE. THE OBJECTIVE OF THIS INSPECTION IS
TO VERIFY AND CONFIRM TYPES AND QUANTITIES OF CONCRETE REPAIRS
NEEDED.
6. CONTRACTOR WILL BE RESPONSIBLE FOR DRAINING THE RESERVOIR IN
COORDINATION WITH THE WASHINGTON AQUEDUCT. CONTRACTOR SHALL
SUBMIT A RESERVOIR DRAINING AND DECHLORINATION PLAN DESCRIBING
DECHLORINATION, DRAINAGE AND DISCHARGE PROTOCOLS NO LATER THAN
FIFTEEN (15) CALENDAR DAYS AFTER NTP AND OBTAIN APPROVAL FROM THE
WASHINGTON AQUEDUCT PRIOR TO RESERVOIR OUTAGE COORDINATION.
DECHLORINATION AND DISCHARGE ACTIVITIES SHALL BE IN COMPLIANCE WITH
NPDES PERMITTING REQUIREMENTS, (REFER TO SPECIFICATION 01 57 19 FOR
PERMITTING REQUIREMENTS).
7. CONCRETE REPAIRS ALONG CEILING, FLOOR, WALLS, COLUMNS AND JOINTS
INSIDE THE RESERVOIR INCLUDING TAPING OF FLOOR JOINTS. THIS WORK
INCLUDES HANDLING AND DISPOSAL OF CONSTRUCTION JOINT MATERIAL THAT
HAS BEEN DETERMINED TO CONTAIN ASBESTOS.
8. MECHANICAL UPGRADES INSIDE THE RESERVOIR, INCLUDING BUT NOT LIMITED
TO, INSTALLATION AND TESTING OF NEW BUTTERFLY VALVE, MIXERS,
SUBMERSIBLE LEVEL TRANSDUCERS AND PIPES.
9. DISINFECTING AND REFILLING OF THE RESERVOIR IN ACCORDANCE WITH AWWA
C652-11, SEC 4.3. THE CONTRACTOR SHALL OBTAIN PRIOR APPROVAL FROM
WASHINGTON AQUEDUCT NO LATER THAN FIFTEEN (15) CALENDAR DAYS FROM
NTP FOR THE METHOD TO BE APPLIED. THE CONTRACTOR SHALL ENSURE THAT
ALL AREAS OF THE RESERVOIR WHERE WORK WAS CONDUCTED AND WHERE
POSSIBLY WERE CONTAMINATED BY THE WORK INSIDE THE RESERVOIR ARE
DISINFECTED, INCLUDING BUT NOT LIMITED TO CONTROL VALVES, WALL PIPES,
DRAIN LINES, AND INFLUENT AND EFFLUENT MAINS, AS APPLICABLE.
10. CLEANING OF THE FLOOR INSIDE THE RESERVOIR AND ANY OTHER AREAS THAT
ARE AFFECTED BY CONTRACTOR'S ACTIVITIES USING POTABLE WATER IN
ACCORDANCE WITH AWWA C-652-11, SEC 4.1. THE CONTRACTOR SHALL
PRESSURE WASH WITH PRESSURE NOT EXCEEDING 2,500 PSI AND SHALL
DECREASE THE PRESSURE AS NEEDED SO AS NOT TO CAUSE DAMAGE TO THE
RESERVOIR. WASH WATER DISPOSAL SHALL FOLLOW SPECIFICATION 01 57 19
AND SHALL BE IN ACCORDANCE WITH NPDES PERMIT REQUIREMENTS.
11. DECHLORINATION AND MAINTAINING COMPLIANCE WITH NPDES (PERMIT NUMBER
DC0000019), INCLUDING SAMPLING AND TESTING PRIOR TO DISCHARGE DURING
DRAINING OF THE RESERVOIR.
12. INSTALLATION OF A NEW BUG/RODENT SCREEN ON THE DIP DISCHARGE LINE
INSIDE THE AIR-GAP CHAMBER.
13. WATERPROOFING MEMBRANE REPAIRS TO AREAS BENEATH THE NEW SAMPLE
BUILDING.
14. INSTALLATION OF A 4-INCH DISCHARGE LINE FROM SAMPLE WATER DISCHARGE
TO AN EXISTING SANITARY SEWER MANHOLE LOCATED AT WARREN STREET NW.
15. INSTALLATION OF UTILITY POLE AND YAGI POLE TYPE ANTENNA.
16. DEMOLITION OF THE EXISTING CHAIN LINK FENCE AND GATES AND INSTALLATION
OF THE NEW 8-FOOT HIGH PICKET FENCE AND GATES IN A MANNER SO THAT
SECOND HIGH RESERVOIR IS NEVER WITHOUT A SECURE FENCE, AND THAT THE
SECURITY CAMERA SYSTEM (LOCATED ON INDEPENDENT POLES JUST INSIDE
THE EXISTING FENCE LINE) ARE NOT DISTURBED, IMPACTED OR DAMAGED.
CONTRACTOR SHALL ENSURE THAT NO GAP IN FENCING SHALL BE LEFT
UNATTENDED AT ANY TIME AND THE CONTRACTOR SHALL VERIFY AT THE END OF
EACH WORK DAY THAT NO GAP EXISTS THAT COMPROMISES THE SECURITY OF
THE RESERVOIR. TEMPORARY FENCING SHALL BE INSTALLED, REPAIRED AND
UTILIZED AS REQUIRED AT NO ADDITIONAL COST TO THE OWNER.
17. SALVAGED SECURITY EQUIPMENT MUST BE REINSTALLED BY THE
GOVERNMENT'S SECURITY CONTRACTOR AND SHALL BE COMPLETED AND
TESTED PRIOR TO THE END OF THE WORK ON THIS CONTRACT. THE
CONTRACTOR SHALL ENSURE THAT THERE IS NO LAPSE IN SITE SECURITY
COVERAGE AT ANY TIME DURING THIS CONTRACT. THE CONTRACTOR SHALL
COORDINATE THE REQUIRED REINSTALLATION AND RETESTING WITH A MINIMUM
OF THIRTY (30) CALENDAR DAYS NOTICE AND PRIOR TO COMPLETION OF THE
WORK IN THIS CONTRACT.
18. RESTORATION OF DISTURBED AREAS TO ORIGINAL OR BETTER CONDITIONS,
INCLUDING BUT NOT LIMITED TO SODDING, SIDEWALK AND PAVEMENT REPAIRS,
PEDESTRIAN WALKWAYS, ETC.
19. CLOSE-OUT ACTIVITIES INCLUDING BUT NOT LIMITED TO REMOVAL OF EROSION
AND SEDIMENT CONTROL, TESTING AND COMMISSIONING TO THE SATISFACTION
OF THE GOVERNMENT, PRE-FINAL INSPECTION, CORRECTIVE WORK IF
APPLICABLE BASED ON GOVERNMENT INSPECTION, AS-BUILT SUBMITTAL,
PREPARATION OF PUNCH LIST, SUBMISSION OF INSTALLED EQUIPMENT AND
DEMOBILIZATION.
20. ANY INCIDENTAL WORK ASSOCIATED WITH THE PROJECT DESCRIPTION
DESCRIBED ABOVE.
CONSTRUCTION SEQUENCE
THE FOLLOWING CONSTRUCTION SEQUENCE IS SUGGESTED FOR THIS PROJECT.
THIS IS NOT ALL-INCLUSIVE AS MAY NOT INCLUDE ALL CONSTRUCTION ACTIVITIES
ASSOCIATED WITH THIS PROJECT. THE CONTRACTOR IS RESPONSIBLE FOR
DEVELOPING A CONSTRUCTION SEQUENCING AND SCHEDULE BASED ON EXISTING
CONDITIONS ENCOUNTERED.
PHASE I – MOBILIZATION
1. INSTALL TEMPORARY CONSTRUCTION ENTRANCE, TREE PROTECTION FENCE, ALL
PERIMETER SOIL EROSION AND SEDIMENT CONTROL DEVICES, AND SILT FENCE AS
SHOWN ON PLAN, PRIOR TO ANY SITE DISTURBANCE OR CONSTRUCTION.
2. ALL EROSION CONTROL MEASURES SHALL BE INSPECTED IMMEDIATELY
FOLLOWING INITIAL INSTALLATION, WEEKLY THEREAFTER, AND WITHIN 24 HOURS
AFTER EACH RAINFALL EVENT PRODUCING 1/2 INCH OR GREATER OF RAIN.
MEASURES SHALL BE REPAIRED OR REPLACED AS NECESSARY.
3. CONTRACTOR TO ENSURE THAT THE EXISTING SAMPLE BUILDING, CONTROL
SYSTEM AND RELATED DEVICES, SECURITY SYSTEM AND RELATED DEVICES,
ACCESS CONTROLS AND ALL SITE UTILITIES REMAIN IN SERVICE AT ALL TIMES THAT
THE SECOND HIGH RESERVOIR IS IN SERVICE. THIS IS AN ABSOLUTE REQUIREMENT
AND SUPERSEDES ANY OTHER PROVISION OF THESE CONTRACT DOCUMENTS
RELATED TO ALLOWABLE OUTAGES. COORDINATION WITH THE GOVERNMENT
SHALL BE PERFORMED TO SUFFICIENTLY PLAN FOR REQUIRED OUTAGES AND TO
ENSURE THAT THE ASSOCIATED WORK IS COMPLETED WHILE THE SECOND HIGH
RESERVOIR IS OUT OF SERVICE.
PHASE II – WORK PRIOR TO RESERVOIR OUTAGE
1. ONCE PERIMETER AND INLET PROTECTION MEASURES HAVE BEEN INSTALLED,
CONTRACTOR SHALL BEGIN SUBDRAINAGE TRENCH EXCAVATION
2. THE CONTRACTOR SHALL PERFORM SITE WORK PRIOR TO TAKING THE RESERVOIR
OUT OF SERVICE, INCLUDING BUT NOT LIMITED TO, INSTALLATION OF
SUB-DRAINAGE SYSTEM WITH DRAIN INTO AIR-GAP CHAMBER, CONNECTION OF
SUBDRAIN SYSTEM TO 8-INCH PVC DRAIN, AND ELECTRICAL SITE WORK.
3. PLUGGING EXISTING DRAIN, AIRGAP SHEETING/SHORING, CONSTRUCTION OF NEW
AIRGAP STRUCTURE AND INSTALLATION OF NEW 24-INCH DIP, 24-INCH HDPE
OVERFLOW PIPE, PVC PIPING AND 24-INCH BUTTERFLY VALVE.
4. CONTRACTOR SHALL PERFORM REPAIR WORK ASSOCIATED WITH APPROXIMATELY
70 SY OF EXISTING AREA ON THE WEST SIDE OF THE RESERVOIR INCLUDING BUT
NOT LIMITED TO FILLING WITH SUITABLE MATERIAL TO MATCH PROPOSED GRADE
AND PLACING SOD.
5. SURPLUS SOIL FROM SUB-DRAIN INSTALLATION SHALL BE HAULED AWAY AS
NECESSARY.
6. THE CONTRACTOR SHALL INFORM THE GOVERNMENT AT LEAST SIXTY (60)
CALENDAR DAYS IN ADVANCE AND OBTAIN PRIOR APPROVAL FROM THE
GOVERNMENT, PRIOR TO COMMENCING WORK INSIDE THE RESERVOIR.
7. THE CONTRACTOR SHALL BE RESPONSIBLE FOR DECHLORINATION AND
MAINTAINING COMPLIANCE WITH NPDES (PERMIT NUMBER DC0000019), INCLUDING
SAMPLING AND TESTING PRIOR TO DISCHARGE DURING DRAINING OF THE
RESERVOIR.
PHASE III – WORK INSIDE THE RESERVOIR DURING OUTAGE (TO BE PERFORMED
BETWEEN NOVEMBER 1 AND MARCH 31 WHILE NOT EXCEEDING A TOTAL OF 90
CALENDAR DAYS)
1. CONTRACTOR SHALL BE RESPONSIBLE FOR DRAINING OF THE RESERVOIR IN
COORDINATION WITH THE WASHINGTON AQUEDUCT, AT LEAST THIRTY (30)
CALENDAR DAYS IN ADVANCE.
2. THE CONTRACTOR SHALL FACILITATE A JOINT STRUCTURAL INSPECTION WITH THE
WASHINGTON AQUEDUCT AND THEIR A/E FIRM. CONTRACTOR WILL BE
RESPONSIBLE FOR ALL SECURITY AND SAFETY PROTOCOLS (I.E., AIR MONITORING,
CSE, BLOWERS, ETC) NEEDED TO UNDERTAKE THIS INSPECTION. STRUCTURAL
INSPECTION WILL TAKE PLACE AS SOON AS THE RESERVOIR IS TAKEN OUT OF
SERVICE AND IS AIMED AT VERIFYING ACTUAL TYPES AND QUANTITIES OF REPAIRS
NEEDED.
3. THE CONTRACTOR SHALL PERFORM CONCRETE REPAIRS ALONG CEILING, FLOOR,
WALLS, COLUMNS AND JOINTS INSIDE THE RESERVOIR.
4. THE CONTRACTOR SHALL PERFORM MECHANICAL UPGRADES INSIDE THE
RESERVOIR, INCLUDING BUT NOT LIMITED TO, INSTALLATION AND TESTING OF NEW
BUTTERFLY VALVE, MIXERS AND PIPES.
5. THE CONTRACTOR SHALL ALSO BE RESPONSIBLE FOR CLEANING THE FLOOR
INSIDE THE RESERVOIR AND ANY OTHER AREAS THAT ARE AFFECTED BY THEIR
ACTIVITIES USING POTABLE WATER IN ACCORDANCE WITH AWWA C-652-11, SEC 4.1.
THE CONTRACTOR SHALL PRESSURE WASH WITH PRESSURE NOT EXCEEDING 2,500
PSI AT ANY TIME AND SHALL DECREASE THE PRESSURE AS NEEDED SO AS NOT TO
CAUSE DAMAGE TO THE RESERVOIR. THE WATER USED FOR CLEANING NEEDS TO
BE REMOVED FROM THE RESERVOIR IN ACCORDANCE WITH SECTION 01 57 19
TEMPORARY ENVIRONMENTAL CONTROLS, AND ANY OTHER APPLICABLE PERMIT
CONDITIONS.
6. THE CONTRACTOR IS RESPONSIBLE FOR DISINFECTING AND REFILLING OF THE
RESERVOIR IN ACCORDANCE WITH C-652-11, SEC 4.3. THE CONTRACTOR SHALL
ADHERE TO METHOD 1 AND ANY DEVIATION FROM THIS SHALL BE SUBMITTED BY
THE CONTRACTOR AS A REQUEST FOR APPROVAL BY THE GOVERNMENT. THE
CONTRACTOR SHALL OBTAIN PRIOR APPROVAL FROM WASHINGTON AQUEDUCT NO
LATER THAN FIFTEEN (15) CALENDAR DAYS FROM NTP FOR THE METHOD TO BE
APPLIED. THE CONTRACTOR SHALL ENSURE THAT ALL COMPONENTS OF THE
RESERVOIR POSSIBLY CONTAMINATED BY THE WORK INSIDE THE RESERVOIR NEED
TO BE DISINFECTED, INCLUDING BUT NOT LIMITED TO CONTROL VALVES, WALL
PIPES, DRAIN LINES, AND INFLUENT AND EFFLUENT MAINS, AS APPLICABLE.
7. THE CONTRACTOR SHALL COMPLETE WORK ASSOCIATED WITH NEW SAMPLE
BUILDING, INCLUDING BUT NOT LIMITED TO BRICKWORK, ELECTRICAL, HVAC AND
PAINTING.
8. CONTRACTOR SHALL BE RESPONSIBLE FOR INSTALLATION OF UTILITY POLE AND
YAGI POLE TYPE ANTENNA.
9. REMOVE EXISTING SIDEWALK AND REPLACE IT WITH A NEW SIDEWALK
CONNECTING TO THE EXISTING SAMPLE BUILDING AND STAIRS.
10. CONTRACTOR SHALL REPAIR THE WATERPROOFING MEMBRANE BENEATH THE
NEW SAMPLE BUILDING AS SHOWN IN THE DRAWINGS.IN THE EVENT OF ANY OTHER
DAMAGE TO THE WATERPROOFING MEMBRANE AS A RESULT OF CONSTRUCTION
ACTIVITIES, THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING THE
REPAIRS AT NO ADDITIONAL COST TO THE GOVERNMENT.
11. THE CONTRACTOR SHALL PLAN ALL WORK INSIDE THE RESERVOIR INCLUDING
DRAINING, INSPECTIONS, REPAIRS, OPERATIONAL TESTING UNDER WET
CONDITIONS, POTENTIAL CORRECTIVE WORK AFTER PRELIMINARY WALKTHROUGH,
FINAL WALKTHROUGH, PUNCH LIST ITEMS FILLING OF RESERVOIR, CHLORINATION
AND DEMOBILIZATION TO BE COMPLETED IN THE LOW DEMAND PERIOD (BETWEEN
NOVEMBER 1ST TO MARCH 31ST, BOTH INCLUSIVE) SO THAT THE RESERVOIR IS
OUT OF SERVICE FOR NO MORE THAN NINETY (90) CALENDAR DAYS. THE
CONTRACTOR MAY BE REQUIRED TO CONDUCT 16-HOUR DAYS, EITHER THROUGH
DOUBLE SHIFTS OR THROUGH MULTIPLE CREWS, AS APPLICABLE AND APPROVED
BY WASHINGTON AQUEDUCT WHILE BEING COMPLIANT WITH LOADING LIMITS ON
THE RESERVOIR. THE CONTRACTOR SHALL INFORM AND OBTAIN PRIOR APPROVAL
FROM WASHINGTON AQUEDUCT AND THEIR A/E AT LEAST SIXTY (60) CALENDAR
DAYS IN ADVANCE BEFORE SCHEDULING WORK INSIDE THE RESERVOIR.
12. CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING THE SUPPLY OF
FINISHED WATER NECESSARY FOR FILLING, TESTING AND START-UP OF THE
RESERVOIR WITH THE WASHINGTON AQUEDUCT, AT LEAST THIRTY (30) CALENDAR
DAYS IN ADVANCE.
31. CONTRACTOR TO ENSURE THAT THE EXISTING SAMPLE BUILDING, CONTROL
SYSTEM AND RELATED DEVICES, SECURITY SYSTEM AND RELATED DEVICES,
ACCESS CONTROLS AND ALL SITE UTILITIES REMAIN IN SERVICE AT ALL TIMES
THAT THE SECOND HIGH RESERVOIR IS IN SERVICE. THIS IS AN ABSOLUTE
REQUIREMENT AND SUPERSEDES ANY OTHER PROVISION OF THESE CONTRACT
DOCUMENTS RELATED TO ALLOWABLE OUTAGES. COORDINATION WITH THE
GOVERNMENT SHALL BE PERFORMED TO SUFFICIENTLY PLAN FOR REQUIRED
OUTAGES AND TO ENSURE THAT THE ASSOCIATED WORK IS COMPLETED WHILE
THE SECOND HIGH RESERVOIR IS OUT OF SERVICE.
32. CONTRACTOR SHALL RESTORE DISTURBED AREAS TO ORIGINAL OR BETTER
CONDITION .
33. SANDBLASTING CANNOT BE PERFORMED INSIDE THE RESERVOIR UNDER ANY
CIRCUMSTANCES.
34. NO WORK TO BE PERFORMED DURING FEDERAL HOLIDAYS AS ESTABLISHED BY
THE FEDERAL LAW (5 U.S.C. 6103). THE LIST OF FEDERAL HOLIDAYS CAN BE
ACCESSED FROM THE U.S. OFFICE OF PERSONNEL MANAGEMENT (OPM)
WEBSITE THROUGH THE FOLLOWING LINK -
(https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/). THE
CONTRACTOR SHALL NOTIFY WASHINGTON AQUEDUCT AT LEAST 15 CALENDAR
DAYS PRIOR TO THE HOLIDAY AND RECEIVE APPROVAL IF THEY NEED TO
PERFORM WORK ON THE FEDERAL HOLIDAYS
35. THE OWNER SHALL HAVE THE AUTHORITY TO ORDER WORK STOPPED OR
PROHIBITED THAT WOULD IN HIS OPINION, UNREASONABLY RESULT IN
INTERRUPTING THE NECESSARY FUNCTIONS OF THE PLANT OPERATIONS.
36. PARKING FOR PERSONAL VEHICLES OF CONSTRUCTION PERSONNEL SHALL NOT
BE ALLOWED ALONG VAN NESS ST NW. THE GENERAL CONTRACTOR SHALL BE
RESPONSIBLE FOR PROVIDING ACCESS TO AND FOR PREPARING AND
MAINTAINING/APPROVED PARKING AREAS.
SAFETY REQUIREMENTS
1. ALL WORK IN THE INTERIOR OF THE RESERVOIR IS CONSIDERED WORK WITHIN
PERMIT REQUIRED CONFINED SPACE AND THE CONTRACTOR SHALL BE
RESPONSIBLE FOR ALL PERMIT ACQUISITION, COMPLIANCE AND SAFETY
REQUIREMENTS, AS WELL AS ARRANGING SUITABLE LIGHTING, VENTILATION,
MOISTURE CONTROL, ETC, TO COMPLETE THE WORK. REFER TO USACE'S EM
385-1-1, SECTION 34 (AND OSHA GENERAL INDUSTRY 1910.146) FOR SPECIFIC
DETAILS.
2. WHEN PREPARING FOR CONFINED SPACE WORK, CONTRACTOR SHALL TEST FOR
SIGNIFICANTLY HIGH LEVELS OF CHLORINE AS PART OF THE REQUIRED
MULTI-GAS METER TESTING.
3. AS PART OF EM 385-1-1, CONTRACTOR SHALL COMPLETE AND SUBMIT FORM A-02
ACCIDENT PREVENTION PLAN CHECKLIST AT OR BEFORE THE
PRE-CONSTRUCTION MEETING.
SECURITY INSTRUCTION NOTES
1. THE WASHINGTON AQUEDUCT AND ASSOCIATED PROPERTIES ARE CONSIDERED
SECURE SITES. THE CONTRACTOR SHALL PROVIDE PERSONNEL INFORMATION,
COMPLY WITH SECURITY POLICIES, AND MAINTAIN SECURE ACCESS TO THE SITE
AT ALL TIMES.
2. THE CONTRACTOR SHALL ACCESS THE SITE THROUGH THE CARD READER
SLIDING GATE AND KEEP THE GATE LOCKED, IF NOT IN USE, AT ALL TIMES.
3. ALL CONTRACTORS AND SUBCONTRACTORS ARE REQUIRED TO BE US CITIZENS
OR LEGAL US RESIDENTS. THE AT/OPSEC REQUIREMENTS IN THE SOLICITATION
ALSO APPLY, INCLUDING THE E-VERIFY PROGRAM. FOREMAN IS REQUIRED TO
COMPLETE FORM DA 1999 WITH IDENTITY OF ALL INDIVIDUALS ENTERING AND
EXITING THE SITE. THESE FORMS ARE TO BE SUBMITTED TO WASHINGTON
AQUEDUCT'S CHIEF OF SECURITY AND LAW ENFORCEMENT ON A WEEKLY BASIS.
4. THE CONTRACTOR SHALL COORDINATE THE DEMOLITION AND REPLACEMENT OF
THE EXISTING FENCE AND GATES IN A MATTER THAT AT NO TIME THE SECOND
HIGH RESERVOIR IS WITHOUT A SECURE FENCE. NO GAP SHALL BE LEFT
UNATTENDED AT ANY TIME AND THE CONTRACTOR SHALL VERIFY AT THE END OF
THE WORK DAY THAT NO GAP EXISTS THAT COMPROMISES THE SECURITY OF
THE RESERVOIR. TEMPORARY FENCING SHALL BE INSTALLED AND UTILIZED AS
REQUIRED AT NO ADDITIONAL COSTS TO THE GOVERNMENT.
TEMPORARY POWER
1. CONTRACTOR TO COORDINATE AND REQUEST APPROVAL FROM WASHINGTON
AQUEDUCT AT LEAST FIFTEEN (15) CALENDAR DAYS IN ADVANCE BEFORE
DISCONNECTING POWER, NETWORK AND PHONE SERVICES TO THE SAMPLE
BUILDING.
2. IF TEMPORARY POWER WILL BE REQUIRED ON THE PROJECT SITE, PROVIDE A
TEMPORARY POWER PLAN AND SKETCH REQUIREMENT FOR GOVERNMENT
REVIEW AND ACCEPTANCE AT LEAST THIRTY (30) CALENDAR DAYS IN ADVANCE.
SEALANT NOTES
1. SEAL EXTERIOR JOINTS AROUND DOORS, WINDOWS AND LOUVER FRAMES AND
PENETRATIONS OF MECHANICAL, ELECTRICAL, AND PLUMBING ELEMENTS TO
PREVENT AIR INFILTRATION AND WATER LEAKAGE.
2. ALL SEALANT JOINTS SHALL BE SIZED AS RECOMMENDED BY MANUFACTURER IN
THEIR INSTALLED POSITION.
3. ALL SEALANT JOINTS SHALL MAINTAIN CONTACT WITH THE ADJOINING PARTS
WITHIN ALLOWABLE DIMENSIONED CHANGES IN THE JOINT SIZE. ALL SEALANT
JOINTS SHALL MAINTAIN DURABILITY AND INTEGRITY UNDER ALL SPECIFIED
CONDITIONS AND CONDITIONS OF THE LOCALITY WHERE THE PROJECT IS
LOCATED.
4. ALL SEALANTS SHALL BE INSTALLED WITH APPROPRIATE JOINT FILLER.
5. PROVIDE CUSTOM COLORS FOR SEALANTS EXPOSED TO VIEW, AS SELECTED BY
THE OWNER'S REPRESENTATIVE.
6. ALL EXPOSED JOINTS SUBJECT TO MOVEMENT ARE TO HAVE CONCEALED
BACKUP WITH CAPTIVE SEALANT AND JOINT FILLER OR BOND BREAKER TAPE IN
ACCORDANCE WITH SEALANT MANUFACTURER'S MINIMUM PUBLISHED
REQUIREMENTS.
7. ALL JOINTS TO BE BACKED UP BY PROPERLY SIZED CLOSED CELL BACKER ROD.
8. AREAS OF JOINT WORK SHALL BE COMPLETELY DRY PRIOR TO ADDING AND/OR
REPLACING THE JOINT FILLER.
PHASE IV – CLOSEOUT
1. DEMOLITION OF THE EXISTING CHAIN LINK FENCE AND GATES AND INSTALLATION
OF THE NEW 8-FOOT HIGH PICKET FENCE AND GATES IN A MANNER SO THAT
SECOND HIGH RESERVOIR IS NEVER WITHOUT A SECURE FENCE, AND THAT THE
SECURITY CAMERA SYSTEM (LOCATED ON INDEPENDENT POLES JUST INSIDE THE
EXISTING FENCE LINE) ARE NOT DISTURBED, IMPACTED OR DAMAGED.
CONTRACTOR SHALL ENSURE THAT NO GAP IN FENCING SHALL BE LEFT
UNATTENDED AT ANY TIME AND THE CONTRACTOR SHALL VERIFY AT THE END OF
EACH WORK DAY THAT NO GAP EXISTS THAT COMPROMISES THE SECURITY OF THE
RESERVOIR. TEMPORARY FENCING SHALL BE INSTALLED, REPAIRED AND UTILIZED
AS REQUIRED AT NO ADDITIONAL COST TO THE GOVERNMENT.
2. SALVAGED SECURITY EQUIPMENT MUST BE REINSTALLED BY THE GOVERNMENT'S
SECURITY CONTRACTOR AND SHALL BE COMPLETED AND TESTED PRIOR TO THE
END OF THE WORK ON THIS CONTRACT. THE CONTRACTOR SHALL ENSURE THAT
THERE IS NO LAPSE IN SITE SECURITY COVERAGE AT ANY TIME DURING THIS
CONTRACT. THE CONTRACTOR SHALL COORDINATE THE REQUIRED
REINSTALLATION AND RETESTING WITH A MINIMUM OF THIRTY (30) CALENDAR DAYS
NOTICE AND PRIOR TO COMPLETION OF THE WORK IN THIS CONTRACT.
3. UPON COMPLETION OF CONSTRUCTION, CONTRACTOR TO RESTORE SITE TO
ORIGINAL OR BETTER CONDITIONS AND PROVIDE SODDING AND/OR SEEDING AT
ALL AREAS DISTURBED AS PART OF THE ACTIVITIES INCLUDED IN THE PROJECT
DESCRIPTION, AS APPLICABLE.
4. CONTRACTOR TO PERFORM CLOSE-OUT ACTIVITIES INCLUDING BUT NOT LIMITED
TO REMOVAL OF EROSION AND SEDIMENT CONTROL, TESTING AND
COMMISSIONING, PRE-FINAL INSPECTION, CORRECTIVE WORK IF APPLICABLE
BASED ON GOVERNMENT INSPECTION, AS-BUILT SUBMITTAL, PREPARATION OF
PUNCH LIST, SUBMISSION OF INSTALLED EQUIPMENT AND DEMOBILIZATION TO THE
SATISFACTION OF THE GOVERNMENT.
1 5/2022 AMENDMENT 0002 SSE
AutoCAD SHX Text
REV
AutoCAD SHX Text
DATE
AutoCAD SHX Text
DESCRIPTION
AutoCAD SHX Text
BY
AutoCAD SHX Text US Army Corps
AutoCAD SHX Text of Engineers
AutoCAD SHX Text
A/E PRINCIPAL
AutoCAD SHX Text
SEAL:
AutoCAD SHX Text