About this opportunity

The Department of the Army Corps of Engineers, New York District is soliciting fixed-price bids for coastal beach renourishment in Sea Bright, Monmouth Beach, and Long Branch, New Jersey, with bids due August 27, 2026 at 2:00 PM EST. The procurement carries no set-aside and is 100% unrestricted full and open competition with HUBZone price evaluation preference under NAICS 237990 (size standard $37,000,000).

Place of performance is Sea Bright, New Jersey. The base contract requires placement of approximately 595,000 cubic yards of beachfill, with multiple options totaling up to 791,000 cubic yards. Construction cost is estimated between $25,000,000 and $100,000,000. The contractor must mobilize within 5 calendar days of Notice to Proceed and complete base work within 250 calendar days; Amendment 0002 reduced the base contract duration to 115 days from NTP. The contract includes an option for remobilization and demobilization and strict environmental windows with no work permitted between March 1 and October 15 annually. All work must be completed and equipment removed by March 15 unless otherwise approved.

The contractor must supply endangered species observers year-round aboard hopper dredges to monitor sea turtles, Atlantic sturgeon, and whales at 100% coverage, with separate private quarters and officer-standard meals provided at no separate payment. Dredge intake screening devices must prevent passage of materials greater than 1.25 inches; discharge screening must retain items 0.75 inches or larger. A qualified Munitions and Explosives of Concern Safety Specialist must oversee compliance in a designated World War I munitions dumping site, with UXO Technicians (minimum two, one at Technician III level) required for 24-hour, 7-days-per-week support during operations. The contractor must protect Seabeach Amaranth by encircling live plants with symbolic fencing and a 3-meter buffer, transplanting plants likely destroyed, and scraping top 6–8 inches of sand in high-density areas to preserve seedbank. Piping Plover protection requires a qualified monitor with at least 40 hours field experience and graduated buffer zones (300 to 1,000 meters depending on date) if plovers are observed after March 1.

The Quality Control Manager must hold a Bachelor's degree in engineering or construction management, current New York professional engineer registration, minimum 10 years construction experience including 4 years as QC Manager, and must complete Construction Quality Management course certification within 90 days of award. A Contractor Quality Control Plan is required within 30 days of NTP. A Project Labor Agreement per Executive Order 14063 must be submitted by the apparent successful offeror before award. Performance and payment bonds are required within 10 calendar days of award; bid guarantee is 20% of bid price or $3,000,000, whichever is less. Liquidated damages are $2,974.00 per day (first tier) and $744.00 per day (second tier) for delays. Bid validity is 60 calendar days. Amendment 0005 (August 24) extended the bid opening from August 25 to August 27 and revised the magnitude range from $50–100 million to $25–100 million. Amendments 0001 through 0004 added FAR clauses, clarified work schedules, extended design plan sets, and provided updated borrow area survey data and coordinates.

Notice text

2 versions

Update #2 · Latest ·

The Project plan for the FY26 renourishment provides for coastal storm risk management through the construction of a beach berm in the communities of Sea Bright, Monmouth Beach and Long Branch in Monmouth County, NJ. The approximate quantity of Beachfill in the base bid is 595,000 cubic yards (CY). There are multiple options of quantities varying from 155,000 CY to 348,000 CY, totaling to 791,000 CY of optional Beachfill placement in the contract and an option for remobilization/demobilization due to environmental windows and a strict no-work period between March 1 and October 15.

The Elberon to Loch Arbour Reach is located within Sandy Hook to Barnegat Inlet Section I which was initiated in response to continued beach erosion and damages incurred along the coast of New Jersey as a result of coastal storms such as hurricanes and nor’easters. The project was originally authorized by the River and Harbor Act of July 3, 1958, in accordance with House Document No. 332, 85th Congress, second session, and further modified by Section 854 of the Water Resources Development Act (WRDA) of 1986, (P.L. 99-662).

Construction cost is in the range of $25,000,000 to $100,000,000.

OPERATIONAL CONSTRAINTS

The Contractor will conform to all local, state, and federal laws while carrying out the construction process for this project.

The Contractor shall prepare and submit a site-specific safety and health plan to the government for approval prior to mobilization. 

Update #1 ·

The Project plan for the FY26 renourishment provides for coastal storm risk management through the construction of a beach berm in the communities of Sea Bright, Monmouth Beach and Long Branch in Monmouth County, NJ. The approximate quantity of Beachfill in the base bid is 595,000 cubic yards (CY). There are multiple options of quantities varying from 155,000 CY to 348,000 CY, totaling to 791,000 CY of optional Beachfill placement in the contract and an option for remobilization/demobilization due to environmental windows and a strict no-work period between March 1 and October 15.

The Elberon to Loch Arbour Reach is located within Sandy Hook to Barnegat Inlet Section I which was initiated in response to continued beach erosion and damages incurred along the coast of New Jersey as a result of coastal storms such as hurricanes and nor’easters. The project was originally authorized by the River and Harbor Act of July 3, 1958, in accordance with House Document No. 332, 85th Congress, second session, and further modified by Section 854 of the Water Resources Development Act (WRDA) of 1986, (P.L. 99-662).

Construction cost is in the range of $50,000,000 to $100,000,000.

OPERATIONAL CONSTRAINTS

The Contractor will conform to all local, state, and federal laws while carrying out the construction process for this project.

The Contractor shall prepare and submit a site-specific safety and health plan to the government for approval prior to mobilization. 

Files

File Type Posted
W912DS26BA024_Bid Abstract.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004_01 56 10.00 18.pdf PDF
Amendment 0004_1988_80_gsds.pdf PDF
Amendment 0004_1988_78_gsds.pdf PDF
Amendment 0004_1988_74_gsds.pdf PDF
Amendment 0004_1988_71 composite gsd.jpg JPG image
Amendment 0004_01 45 00.pdf PDF
Amendment 0004_SBOBA_2025_NAD83_2011_NAVD88_30x30 (2) - Copy.txt.txt TXT text file
Amendment 0004_ADDITIONAL BORROW AREA COORDINATES 202660819.docx DOCX document
Amendment 0004_1988_71 penetration graphs.jpg JPG image
Amendment 0004.pdf PDF
Amendment 0004_1988_80 penetration graphs.jpg JPG image
Amendment 0004_1988_78 composite gsd.jpg JPG image
Amendment 0004_1988_78 penetration graphs.jpg JPG image
Amendment 0004_1988_71 gsds.pdf PDF
Amendment 0004_1988_74 penetration graphs.jpg JPG image
Amendment 0004_1988_74 composite gsd.jpg JPG image
Amendment 0004_1983_10IndividualGSDs.pdf PDF
Amendment 0003_01 56 10.00 18.pdf PDF
Amendment 0003_01 45 00.pdf PDF
Amendment 0003_Sea Bright FY 26 Renourishment Plan Set Amendment 0003.pdf PDF
Amendment 0003.pdf PDF
Amendment 0003_01 14 00.pdf PDF
Amendment 0003__01 57 19.pdf PDF
Amendment 0002_Section 01 57 19- Monitoring and Protection Plan.pdf PDF
Amendment 0002_01 56 10.00 18.pdf PDF
Amendment 0002.pdf PDF
Amendment 0002_01 78 00.pdf PDF
Amendment 0002_01 35 30.pdf PDF
Amendment 0002_01 57 19.pdf PDF
Amendment 0002_01 45 00.pdf PDF
Amendment 0002_01 14 00.pdf PDF
Amendment 0002_01 11 00.pdf PDF
Amendment 0001.pdf PDF
Specifications.pdf PDF
Solicitation - W912DS26BA024.pdf PDF
Plans.pdf PDF
Show all 38

Notice history

Notice Type Posted
This notice Latest solicitation Solicitation
Sea Bright to Manasquan, New Jersey FY 26 Renourishment Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Pass-a-grille-pass, maintenance dredging, pinellas county, florida NAICS 237990 ENDIST Jacksonville Total Small Business
Tybee Island Shoreline Protection Project Tybee Island, Chatham County, Georgia. Tybee Island, Georgia 31328, United States · NAICS 237990 ENDIST Savannah No set-aside
Delaware Avenue Revetment, Cape May, NJ 08204 · NAICS 237990 ENDIST Philadelphia No set-aside
Maintenance Dredging of the Isle au Haut Thoroughfare near Isle au Haut, Maine NAICS 237990 ENDIST New England Total Small Business
Timucuan Ecological and Historic Preserve TIMU-335 NAICS 237990 National Office No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors