Amendment 0002_01 14 00.pdf

PDF 13 KB Posted

Attached to
SEA BRIGHT TO MANASQUAN, NEW JERSEY FY 26 RENOURISHMENT
Solicitation number
W912DS26BA024
Issued by

About this file

This document is Section 01 14 00 (Work Restrictions) from the FY26 Sea Bright to Manasquan Renourishment project specification, effective Amendment 0002 dated 08/06/26.

The contractor must submit a List of Contact Personnel for preconstruction approval by the Government. Contractor personnel must comply with all Activity regulations including safety, fire, traffic, and security requirements, wear appropriate PPE in designated areas, and maintain a current list of contact information for the contractor and all subcontractors for emergency purposes. Smoking is prohibited throughout the project site except in designated areas identified by the Contracting Officer. Dredging and beachfill operations are permitted 24 hours daily, including Sundays and Government holidays, contingent upon local government approval for compliance with ordinances. Beachfill placement must proceed continuously along the shoreline moving generally South to North starting in Monmouth Beach, with maximum 1,000-foot-wide beach work zone/closure areas at any one time. The contractor may pump fill material in both directions from the landed pipeline, prioritizing southward placement first, then northward. Beach access for each community must be maintained at all times outside active work zones.

Environmental restrictions require compliance with the Migratory Bird Treaty Act of 1918 and the Migratory Bird Conservation Act of 1929. Work beyond March 1 must be avoided and requires an approved bird monitor if necessary. No work may occur within nesting areas between March 15 and August 31, with all work and equipment required to be completed and removed from the beach by March 15 of any year unless otherwise approved. Nesting areas are defined as those occupied by plovers demonstrating breeding behavior within the past three breeding seasons. If work cannot be completed by March 15 in non-nesting areas, the contractor must submit written approval requests at least 30 days prior. No work may be performed during Government holidays without prior written Contracting Officer approval, and this exclusionary period is not considered in computing the time allowed for contract performance.

View the file

Other files

File Type Posted
W912DS26BA024_Bid Abstract.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004_01 56 10.00 18.pdf PDF
Amendment 0004_1988_80_gsds.pdf PDF
Amendment 0004_1988_78_gsds.pdf PDF
Amendment 0004_1988_74_gsds.pdf PDF
Amendment 0004_1988_71 composite gsd.jpg JPG image
Amendment 0004.pdf PDF
Amendment 0004_1988_80 penetration graphs.jpg JPG image
Amendment 0004_1988_78 composite gsd.jpg JPG image
Amendment 0004_1988_78 penetration graphs.jpg JPG image
Amendment 0004_1988_71 gsds.pdf PDF
Amendment 0004_01 45 00.pdf PDF
Amendment 0004_SBOBA_2025_NAD83_2011_NAVD88_30x30 (2) - Copy.txt.txt TXT text file
Amendment 0004_ADDITIONAL BORROW AREA COORDINATES 202660819.docx DOCX document
Amendment 0004_1988_71 penetration graphs.jpg JPG image
Amendment 0004_1988_74 penetration graphs.jpg JPG image
Amendment 0004_1988_74 composite gsd.jpg JPG image
Amendment 0004_1983_10IndividualGSDs.pdf PDF
Amendment 0003_01 56 10.00 18.pdf PDF
Amendment 0003_01 45 00.pdf PDF
Amendment 0003_Sea Bright FY 26 Renourishment Plan Set Amendment 0003.pdf PDF
Amendment 0003.pdf PDF
Amendment 0003_01 14 00.pdf PDF
Amendment 0003__01 57 19.pdf PDF
Amendment 0002.pdf PDF
Amendment 0002_01 78 00.pdf PDF
Amendment 0002_01 35 30.pdf PDF
Amendment 0002_Section 01 57 19- Monitoring and Protection Plan.pdf PDF
Amendment 0002_01 56 10.00 18.pdf PDF
Amendment 0002_01 57 19.pdf PDF
Amendment 0002_01 45 00.pdf PDF
Amendment 0002_01 11 00.pdf PDF
Amendment 0001.pdf PDF
Specifications.pdf PDF
Solicitation - W912DS26BA024.pdf PDF
Plans.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY26 Sea Bright to Manasquan Renourishment SEABRIGHTRENOUR Amendment 0002 08/06/26

SECTION 01 14 00

WORK RESTRICTIONS

11/22, CHG 5: 05/25

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the project become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, including delivery vehicles, are clearly identified with their company name.

1.2.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.2 No Smoking Policy

Smoking is prohibited within and outside of the Project site, except in designated smoking areas. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Working Hours

Working hours for dredging are 24 hours a day including Sunday and Government holidays. Local government approval is required to ensure compliance with local ordinances and local Boards.

1.2.3 Order Of Work

Proceed with the placement of the beachfill in a continuous manner along

SECTION 01 14 00 Page 1

FY26 Sea Bright to Manasquan Renourishment SEABRIGHTRENOUR Amendment 0002 08/06/26 the shoreline, moving generally South to North starting in Monmouth Beach, or as directed by the Contracting Officer. Contractor will be allowed to pump fill material in both directions from landed pipeline on condition that the contractor will pump fill material first to the south, then to the north.

Place beachfill in maximum 1,000-foot-wide beach work zone/closure areas.

Working in more than one closure area at a time shall be at the discretion of the COR and with coordination with local communities. Access to the beach for each community shall be maintained at all times except within the active established beach fill work zone(s).

1.2.4 ENVIRONMENTAL RESTRICTIONS

Comply with the Migratory Bird Treaty act of 1918 and the migratory bird conservation act of 1929 requirements to protect bird species that may potentially nest within the project area by implementing restrictions.

Work beyond March 1 should be avoided to the maximum extent possible. Any work beyond March 1 is required to have an approved bird monitor.

No work may occur within a nesting area between March 15 - August 31. All work must be completed and all equipment must be removed from the beach by March 15 of any year unless otherwise approved. Nesting areas are defined as areas that have been occupied by plovers demonstrating breeding behavior or nesting at any point within the past three breeding seasons.

Breeding behaviors by plovers include courtship, territorial, and/or nesting activities.

If work is unable to be completed by March 15 in a non-nesting area, the contractor must submit a written request for approval a minimum of 30 days prior.

1.2.5 Exclusionary Period

No work may be performed during the Government holidays, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 14 00 Page 2

01 14 00 - WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
1.2.1.1 Subcontractors and Personnel Contacts
1.2.1.2 No Smoking Policy
1.2.2 Working Hours
1.2.3 Order Of Work
1.2.4 ENVIRONMENTAL RESTRICTIONS
PART 2 PRODUCTS
PART 3 EXECUTION