This is a Summary of Work section from a federal construction contract for the FY26 Sea Bright to Manasquan Renourishment project in New Jersey. The contract involves placement of beach fill material and incidental related work at the specified coastal location. The estimated project value is between $25,000,000.00 and $100,000,000.00, falling under DFARS 236.204 disclosure requirements for construction projects of this magnitude.
The contractor must commence work within 105 calendar days of receiving the Notice to Proceed and complete the base work ready for use within 250 calendar days of the NTP, with final cleanup included in this timeline. Additional days will be added if contract options are exercised as detailed in Section 00 10 00 Bidding Schedule. All work must comply with attached drawings, specifications, and instructions provided by the Contracting Officer, who maintains supervisory authority over all work details. The contractor bears full responsibility for managing existing work by preventing damage, making required repairs or replacements to match existing conditions, and obtaining Contracting Officer approval prior to any alterations to existing structures, utilities, dunes, roads, or other improvements. Any damage resulting from contractor operations must be repaired and restored at contractor expense, with all restoration work subject to Contracting Officer approval.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY26 Sea Bright to Manasquan Renourishment SEABRIGHTRENOUR Amendment 0002 08/06/26
SECTION 01 11 00
SUMMARY OF WORK
02/24, CHG 1: 05/25
PART 1 GENERAL
1.1 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. The Contractor must be required to (i) commence work under this contract within 105 calendar days after the date the Contractor receives the Notice to Proceed (NTP),(ii) prosecute the work diligently, and (iii)complete the base work ready for use not later than 250115 calendar days after the date the Contractor receives the notice to proceed. The date stated for completion must include final cleanup of the premises. Additional days will be added if contract options are exercised as noted in Section 00 10 00 Bidding Schedule.
b. All work must be in accordance with the drawings and specifications or instructions attached hereto and made a part thereof, or to be furnished hereafter by the Contracting Officer and subject, in every detail, to his supervision, direction, and instructions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes placement of the beach fill material and incidental related work.
1.2.2 Location
The work is located at the Sea bright to Manasquan in New Jersey; The exact location is shown in the bid documents.
1.3 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS
This project is estimated between $25,000,000.00 and $100,000,000.00
1.4 EXISTING WORK
Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
The Contractor is responsible for the repair, restoration, or for all cost of damage resulting therefrom. If the Contractor elects to have alterations made to any existing structure, utility, dune, road, or other improvements, contractor must make arrangements with the Contracting officer for such alteration and the arrangements must be approved by the Contracting Officer prior to making alterations. Repair and restoration must comply with contract requirements and must also be approved by the
SECTION 01 11 00 Page 1
FY26 Sea Bright to Manasquan Renourishment SEABRIGHTRENOUR Amendment 0002 08/06/26
Contracting Officer
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
| 01 11 00 - SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.1 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK |
| 1.2 WORK COVERED BY CONTRACT DOCUMENTS |
| 1.2.1 Project Description |
| 1.2.2 Location |
| 1.3 DFARS 236.204, DISCLOSURE OF THE MAGNITUDE OF CONSTRUCTION PROJECTS |
| 1.4 EXISTING WORK |
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
File details come from the government source that posted it. Updated .