This is a specification section for closeout submittals for the FY26 Sea Bright to Manasquan Renourishment project, a federal construction contract under USACE management (Amendment 0002, effective 08/06/26).
The specification establishes comprehensive requirements for as-built drawings, record drawings, and project documentation. Contractors must maintain as-built drawings throughout construction using red-lined hard copies or PDF files, then submit them 30 days prior to project completion. Record drawings must be prepared in AutoCAD 2018 DWG format compatible with Windows 11, incorporating all changes from approved working as-built markups. Markup guidelines require color-coding changes (blue for special information, red for deletions, green for additions) with frequent written explanations. Final record drawing packages must be submitted within 20 days of substantial completion and include one set of electronic CAD files, two sets of ANSI D size prints, and approved working record drawings. Additional deliverables include: final approved shop drawings (30 days after facility transfer), construction contract specifications in PDF format (30 days after transfer), EPA and USDA designated item certifications with specific language, PDF versions of contract drawings, redline/markup PDFs, and GeoReferenced GeoDatabase files in .mdb format using SDSFIE standards for information outside building walls. The contractor must develop a warranty management plan at least 30 days before the pre-warranty conference, detailing roles, contact information, equipment lists, and warranty terms. Performance bonds must remain effective throughout the construction and warranty period. Quality control requirements mandate that all additions and corrections match original drawing standards in line colors, weights, lettering, layering conventions, and symbols.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY26 Sea Bright to Manasquan Renourishment SEABRIGHTRENOUR Amendment 0002 08/06/26
SECTION 01 78 00
CLOSEOUT SUBMITTALS
05/19, CHG 1: 08/21
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 As-Built Drawings
As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to submitted Requests for Information (RFI's); direction from the Contracting Officer; design that is the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site and or red-lined PDF files . These files serve as the basis for the creation of the record drawings.
1.1.2 Record Drawings
The record drawings are the final compilation of actual conditions reflected in the as-built drawings.
Produce the record drawings from the Record Model(s) and do not include annotations indicating revisions.
1.1.3 Record Model
A model reflecting approved changes during construction including red-lines, requests for information (RFI's), and contract modifications.
Include updated construction phase facility/site data for components.
1.1.4 USACE CAD/BIM Technology Center
The USACE CAD/BIM Technology Center hosts all standard content for USACE.
This content can be accessed through the CAD/BIM Technology Center website, https://cadbimcenter.erdc.dren.mil/ .
1.2 SOURCE DRAWING FILES
Request the full set of electronic drawings, in the source format, for Record Drawing preparation, after award and at least 30 days prior to required use.
1.2.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse is at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The
SECTION 01 78 00 Page 1
Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CAD drawing files are not construction documents.
Differences may exist between the CAD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CAD files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction drawings and data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
1.3 RECORD DRAWINGSThe Government will provide pdf and or program files at the preconstruction conference that contains one set of "as-designed" electronic CAD files in the specified software and format revised to reflect all amendments and the final contract PDF drawings. The CAD files are provided to enable preparation of as-built or as-constructed drawings. If discrepancies exist between the CAD files and the contract PDF drawings, correct the CAD files to show the contract PDF drawings.
1.3.1 Variation with Contract Drawings
The electronic files provided are not part of the contract documents. If there is any discrepancy between the electronic files and the contract drawings, the contract drawings govern. The Government has no responsibility to modify any Government furnished materials (GFM) due to changes in the design that occur after award.
Evaluate the content and quality of the GFM upon receipt. If major discrepancies or omissions occur in the GFM, notify the Contracting Officer and indicate the nature of such variations.
1.3.2 Data Loss, Corruption, and Error
Transfer of GFM files may result in corrupted files resulting in data loss and errors. Use of GFM files at own risk. Verify data integrity upon receipt and request a replacement if necessary. Make any adjustment in file structure, format, or software version as needed to make GFM compatible with computer systems and/or software to meet the requirements of the contract.
1.3.3 Modeling Completeness and Quality
The Government makes no guarantee that the GFM provide the level of completeness or quality as required by the contract. Further, the Government makes no guarantee that identified variations will be corrected upon notification.
SECTION 01 78 00 Page 2
1.4 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-03 Product Data
Warranty Management Plan
SD-08 Manufacturer's Instructions
Posted Instructions
SD-11 Closeout Submittals
As-Built Drawings ; G, RO
Record Drawings ; G, RO
Warranted Equipment and Materials
Final Approved Shop Drawings ; G, RO
Construction Contract Specifications ; G, RO
Certification of EPA Designated Items ; G, RO
Certification Of USDA Designated Items ; G, RO
1.5 QUALITY CONTROL
Additions and corrections to the contract drawings must be equal in quality and detail to that of the originals. Line colors, line weights, lettering, layering conventions, and symbols must be the same as the original line colors, line weights, lettering, layering conventions, and symbols.
1.6 WARRANTY MANAGEMENT
1.6.1 Warranty Management Plan
Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction. At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan narrative must contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. The term "status" as indicated below must include due date and whether item has been submitted or was accomplished. Submit warranty information, made available during the construction phase, to the Contracting Officer for approval prior to each monthly pay estimate.
SECTION 01 78 00 Page 3
Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period must begin on the date of project acceptance and continue for the full product warranty period. Conduct a joint 4 month and 9 month warranty inspection, measured from time of acceptance; with the Contractor, Contracting Officer and the Customer Representative. The warranty management plan must include, but is not limited to, the following:
a. Roles and responsibilities of personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors, subcontractors, manufacturers or suppliers involved.
b. For each warranty, the name, address, telephone number, and e-mail of each of the guarantor's representatives nearest to the project location.
c. A list and status of delivery of Certificates of Warranty for extended warranty items, including roofs, HVAC balancing, pumps, motors, transformers, and for commissioned systems, such as fire protection and alarm systems, sprinkler systems, and lightning protection systems.
d. Warranted Equipment and Materials list for each warranted equipment, item, feature of construction or system indicating:
(1) Name of item.
(2) Model and serial numbers.
(3) Location where installed.
(4) Name and phone numbers of manufacturers or suppliers.
(5) Names, addresses and telephone numbers of sources of spare parts.
(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have warranties longer than one year must be indicated with separate warranty expiration dates.
(7) Cross-reference to warranty certificates as applicable.
(8) Starting point and duration of warranty period.
(9) Summary of maintenance procedures required to continue the warranty in force.
(10) Cross-reference to specific pertinent Operation and Maintenance manuals.
(11) Organization, names and phone numbers of persons to call for warranty service.
(12) Typical response time and repair time expected for various warranted equipment.
1.6.2 Performance Bond
The Performance Bond must remain effective throughout the construction and warranty period.
a. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
SECTION 01 78 00 Page 4
b. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the Contractor's expense, the Contracting Officer will have the right to recoup expenses from the bonding company.
c. Following oral or written notification of required construction warranty repair work, respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
1.6.3 Pre-Warranty Conference
Prior to contract completion, and at a time designated by the Contracting Officer, meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. At this meeting, establish and review communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty In connection with these requirements and at the time of the Contractor's quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contact must be located within the local service area of the warranted construction, be continuously available, and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in connection with other portions of this provision.
PART 2 PRODUCTS
2.1 RECORD DRAWINGS
Prepare the CAD drawing files in AutoCAD 2018 DWG File format compatible with a Windows 11 operating system.
2.1.1 Additional Drawings
If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings. The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings.
2.1.1.1 Sheet Numbers and File Names
If a sheet needs to be added between two sequential sheets, append a Supplemental Drawing Designator in accordance with ERDC/ITL TR-24-3 Adding a drawing sheet, and ERDC/ITL TR-23-1 Adding or deleting drawing sheets and index sheet procedures.
2.2 CERTIFICATION OF EPA DESIGNATED ITEMS
Submit the Certification of EPA Designated Items as required by FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items and FAR 52-223-17 Affirmative Procurement of EPA designated items in Service and Construction Contracts. Include on the certification form the following information: project name, project
SECTION 01 78 00 Page 5 number, Contractor name, license number, Contractor address, and certification. The certification will read as follows and be signed and dated by the Contractor. "I hereby certify the information provided herein is accurate and that the requisition/procurement of all materials listed on this form comply with current EPA standards for recycled/recovered materials content. The following exemptions may apply to the non-procurement of recycled/recovered content materials:
a. The product does not meet appropriate performance standards;
b. The product is not available within a reasonable time frame;
c. The product is not available competitively (from two or more sources);
d. The product is only available at an unreasonable price (compared with a comparable non-recycled content product)."
2.3 CERTIFICATION OF USDA DESIGNATED ITEMS
Submit the Certification of USDA Designated Items as required by FAR 52-223-1 Bio-based Product Certifications and FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. Include on the certification form the following information:
project name, project number, Contractor name, license number, Contractor address, and certification. The certification will read as follows and be signed and dated by the Contractor. "I hereby certify the information provided herein is accurate and that the requisition/procurement of all materials listed on this form comply with current USDA standards for biobased materials content. The following exemptions may apply to the non-procurement of biobased content materials:
a. The product does not meet appropriate performance standards;
b. The product is not available within a reasonable time frame;
c. The product is not available competitively (from two or more sources);
d. The product is only available at an unreasonable price (compared with a comparable bio-based content product)."
2.3 PDF AS-BUILT FILES
Provide electronic PDF "plots" of all contract drawings sheets associated with the as-built drawing submittal. Compile and organize the PDF set to match the contract drawings.
2.4 REDLINES AND MARKUPS
Provide PDFs of the current working redlines and/or markups complying with the as-builts drawing and markup requirements contained in this specification.
2.5 GEO-DATA-BASE FILES
Provide a SDSFIE/FGDC GeoReferenced personal GeoDataBase. For all information outside of the building walls, provide a personal GeoDataBase in .mdb format using the latest version of Spatial Data Standard for
SECTION 01 78 00 Page 6
Facilities, Infrastructure, and Environment (SDSFIE) as the database structure. Provide a shell database to define the projection and database structure.
For all drawings within and including the exterior walls, utilize the advanced modeling formats described and referenced herein. Provide a short GeoDataBase read-me file explaining the deliverable. The read-me file will include a description of the software used to create the data, projection, and include the attribute tables used.
2.6 AS-BUILT REQUIREMENTS
If elements of an as-built submittal or advanced modeling package are rejected, provide the following for each re-submission, in addition to any information required in Section 01 33 00 SUBMITTAL PROCEDURES:
a. Re-submit all components required under paragraph As-Builts or Advanced Modeling Package, including a new Advanced Modeling Submittal Checklist and updated content in response to Government comments.
b. Provide a copy of all Government review comments.
c. Provide a disposition/response to each Government review comment for a back-check of the re-submission deliverable.
PART 3 EXECUTION
3.1 AS-BUILT DRAWINGS
Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings. Maintain the as-builts throughout construction as red-lined hard copies on site or red-lined PDF files.
Submit As-Built Drawings 30 days prior to Project completion date.
3.1.1 Markup Guidelines
Make comments and markup the drawings complete without reference to letters, memos, or materials that are not part of the As-Built drawing.
Show what was changed, how it was changed, where item(s) were relocated and change related details. These working as-built markup prints must be neat, legible and accurate as follows:
a. Use base colors of red, green, and blue. Color code for changes as follows:
(1) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes.
(2) Deletions (Red) - Over-strike deleted graphic items (lines), lettering in notes and leaders.
(3) Additions (Green) - Added items, lettering in notes and leaders.
b. Provide a legend if colors other than the "base" colors of red, green, and blue are used.
c. Add and denote any additional equipment or material facilities, service lines, incorporated under As-Built Revisions if not already shown in legend.
SECTION 01 78 00 Page 7
d. Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision.
e. Use legible lettering and precise and clear digital values when marking prints. Clarify ambiguities concerning the nature and application of change involved.
f. Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on all other sheets.
g. For deletions, cross out all features, data and captions that relate to that revision.
h. For changes on small-scale drawings and in restricted areas, provide large-scale inserts, with leaders to the applicable location.
i. Indicate one of the following when attaching a print or sketch to a markup print:
(1) Add an entire drawing to contract drawings
(2) Change the contract drawing to show changes on the drawing.
(3) Provided for reference only to further detail the initial design.
j. Incorporate all shop and fabrication drawings into the markup drawings.
3.1.2 As-Built Drawings Content
Revise As-Built Drawings in accordance with ERDC/ITL TR-23-1 . Keep these working as-built markup drawings current on a weekly basis and at least one set available on the jobsite at all times. Changes from the contract drawings which are made during construction or additional information which might be uncovered in the course of construction must be accurately and neatly recorded as they occur by means of details and notes. Submit the working as-built markup drawings for approval prior to submission of each monthly pay estimate. For failure to maintain the working and final record drawings as specified herein, the Contracting Officer will withhold 10 percent of the monthly progress payment until approval of updated drawings. Show on the as-built drawings, but not limited to, the following information:
a. The actual location, kinds and sizes of all sub-surface utility lines. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, show by offset dimensions to two permanently fixed surface features the end of each run including each change in direction on the record drawings. Locate valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point. Also record the average depth below the surface of each run.
b. The location and dimensions of any changes within the building structure.
c. Layout and schematic drawings of electrical circuits and piping.
SECTION 01 78 00 Page 8
d. Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans.
e. Changes in details of design or additional information obtained from working drawings specified to be prepared or furnished by the Contractor; including but not limited to shop drawings, fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment, and foundations.
f. The topography, invert elevations and grades of drainage installed or affected as part of the project construction.
g. Changes or Revisions which result from the final inspection.
h. Where contract drawings or specifications present options, show only the option selected for construction on the working as-built markup drawings.
i. If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, furnish a contour map of the final borrow pit/spoil area elevations.
j. Systems designed or enhanced by the Contractor, such as HVAC controls, fire alarm, fire sprinkler, and irrigation systems.
k. Changes in location of equipment and architectural features.
l. Modifications.
m. Actual location of anchors, construction and control joints, etc., in concrete.
n. Unusual or uncharted obstructions that are encountered in the contract work area during construction.
o. Location, extent, thickness, and size of stone protection particularly where it will be normally submerged by water.
3.2 RECORD DRAWING FILES
If additional drawings are required, prepare them using the specified electronic file format applying the same graphic standards specified for original drawings. The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings. Accomplish additions and corrections to the contract drawings using CAD files. Provide all program files and hardware necessary to prepare final PDF record drawings. The Contracting Officer will review final PDF record drawings for accuracy and return them to the Contractor for required corrections, changes, additions, and deletions.
3.2.1 Rename the CAD Drawing files
Rename the CAD Drawing files using the contract number as the Project Code field,(e.g., W91238-15-C-10A-102. DWG) as instructed in the Pre-Construction conference. Use only those renamed files for the Marked-up changes. Make all changes on the layer/level as the original item.
SECTION 01 78 00 Page 9
a. For AutoCAD files (DWG), enter all as-built delta changes and notations on the AS-BUILT layer.
b. When final revisions have been completed, show the wording "RECORD DRAWING AS-BUILTS" followed by the name of the Contractor in letters at least 3/16 inch high on the cover sheet drawing. Date RECORD DRAWING AS-BUILTS" drawing revisions in the revision block.
c. Within 20 days after Government approval of all of the working record drawings for a phase of work, prepare the final CAD record drawings for that phase of work and submit PDF drawing files and two sets of prints for review and approval. The Government will promptly return one set of prints annotated with any necessary corrections. Within 10 days revise the CAD files accordingly at no additional cost and submit one set of final prints for the completed phase of work to the Government. Within 20 days of substantial completion of all phases of work, submit the final record drawing package for the entire project.
Submit one set of electronic CAD files, and one set of the approved working record PDF and or programfiles with two sets of prints. The CAD files must be complete in all details and identical in form and function to the CAD drawing files supplied by the Government. Prepare AutoCAD files for transmittal using e-Transmit. Make any transactions or adjustments necessary to accomplish this. The Government reserves the right to reject any drawing files it deems incompatible with the customer's CAD system. Paper prints, drawing files and storage media submitted will become the property of the Government upon final approval. Failure to submit final record PDF drawing files, CAD files and marked prints as specified will be cause for withholding any payment due under this contract. Approval and acceptance of final record drawings must be accomplished before final payment is made.
3.3 RECORD DRAWINGS
Prepare final record drawings after the completion of each definable feature of work as listed in the Contractor Quality Control Plan (such as Foundations, Utilities, or Structural Steel as appropriate for the project). Transfer the changes from the approved working as-built markup drawings to the original electronic CAD drawing files. Modify the as-built CAD drawing files to correctly show the features of the project as-built by bringing the working CAD drawing set into agreement with approved working as-built markup drawings, and adding such additional drawings as may be necessary. Refer to ERDC/ITL TR-23-1 . Jointly review the working as-built markup drawings with printouts from working as-built CAD drawing PDF files for accuracy and completeness. Monthly review of working as-built CAD drawing PDF file printouts must cover all sheets revised since the previous review. These PDF drawing files are part of the permanent records of this project. Any drawings damaged or lost must be satisfactorily replaced at no expense to the Government.
Drawing revisions (include within change order price the cost to change working and final record drawings to reflect revisions) and compliance with the following procedures.
a. Follow directions in the revision for posting descriptive changes.
b. The revision delta size must be 5/16 inch unless the area where the delta is to be placed is crowded. Use a smaller size delta for crowded areas.
SECTION 01 78 00 Page 10
c. Place a revision delta at the location of each deletion.
d. For new details or sections which are added to a drawing, place a revision delta by the detail or section title.
e. For minor changes, place a revision delta by the area changed on the drawing (each location).
f. For major changes to a drawing, place a revision delta by the title of the affected plan, section, or detail at each location.
g. For changes to schedules or drawings, place a revision delta either by the schedule heading or by the change in the schedule.
3.3.1 Final Record Drawing Package
Submit the final record PDF and CAD drawings package for the entire project within 20 days of substantial completion of all phases of work.
Submit one set of ANSI D size PDF and CAD files, two sets of ANSI D size prints and one set of the approved working record drawings. The package must be complete in all details and identical in form and function to the contract drawing files supplied by the Government.
3.4 FINAL APPROVED SHOP DRAWINGS
Submit final approved project shop drawings 30 days after transfer of the completed facility.
3.5 CONSTRUCTION CONTRACT SPECIFICATIONS
Submit final PDF file record construction contract specifications, including revisions thereto, 30 days after transfer of the completed facility.
3.6 CLEANUP
Leave premises "broom clean." Sweep paved areas and rake clean landscaped areas. Remove waste and surplus materials, rubbish and construction facilities from the site.
-- End of Section --
SECTION 01 78 00 Page 11
| 01 78 00 - CLOSEOUT SUBMITTALS |
| PART 1 GENERAL |
| 1.1 DEFINITIONS |
| 1.1.1 As-Built Drawings |
| 1.1.2 Record Drawings |
| 1.1.3 Record Model |
| 1.1.4 USACE CAD/BIM Technology Center |
| 1.2 SOURCE DRAWING FILES |
| 1.2.1 Terms and Conditions |
| 1.3 RECORD DRAWINGSThe Government will provide pdf and or program files at |
| 1.3.1 Variation with Contract Drawings |
| 1.3.2 Data Loss, Corruption, and Error |
| 1.3.3 Modeling Completeness and Quality |
| 1.4 SUBMITTALS |
| 1.5 QUALITY CONTROL |
| 1.6 WARRANTY MANAGEMENT |
| 1.6.1 Warranty Management Plan |
| 1.6.2 Performance Bond |
| 1.6.3 Pre-Warranty Conference |
| PART 2 PRODUCTS |
| 2.1 RECORD DRAWINGS |
| 2.1.1 Additional Drawings |
| 2.1.1.1 Sheet Numbers and File Names |
| 2.2 CERTIFICATION OF EPA DESIGNATED ITEMS |
| 2.3 PDF AS-BUILT FILES |
| 2.4 REDLINES AND MARKUPS |
| 2.5 GEO-DATA-BASE FILES |
| 2.6 AS-BUILT REQUIREMENTS |
| PART 3 EXECUTION |
| 3.1 AS-BUILT DRAWINGS |
| 3.1.1 Markup Guidelines |
| 3.1.2 As-Built Drawings Content |
| 3.2 RECORD DRAWING FILES |
| 3.2.1 Rename the CAD Drawing files |
| 3.3 RECORD DRAWINGS |
| 3.3.1 Final Record Drawing Package |
| 3.4 FINAL APPROVED SHOP DRAWINGS |
| 3.5 CONSTRUCTION CONTRACT SPECIFICATIONS |
| 3.6 CLEANUP |