This is Amendment 0004 to a solicitation for the Seabright to Manasquan, New Jersey FY 26 Renourishment project (Solicitation W912DS26BA024), issued by the U.S. Army Corps of Engineers (USACE) Endist New York office on August 19, 2026. The bid opening date remains August 25, 2026 at 2:00 P.M. EST and is not extended. Bidders must acknowledge receipt of this amendment by the specified bid date through one of three methods: completing items 8 and 15 and returning copies of the amendment, acknowledging receipt on each copy of the offer submitted, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge the amendment by the specified deadline may result in bid rejection under FAR 14.304 provisions regarding late bids, late modifications, or late withdrawals.

The amendment includes revisions to contract drawings and specifications. Three drawings have been revised but not reissued: G-101, C-113, and C-114. Two specifications have been revised and reissued: 01 45 00 and 01 56 10.00 18. No drawings or specifications were added or deleted. The project is a dredging and beach renourishment effort with an estimated construction magnitude between $25,000,000 and $100,000,000, subject to a March 15 through August 31 environmental window restriction. The amendment includes eleven questions and government responses addressing clarifications on borrow area slopes, contract documentation updates, work schedule requirements, Executive Order 14063 Project Labor Agreement applicability, and air permitting requirements. Updated borrow area survey data in .txt format was provided with this amendment.

View the file

Other files

File Type Posted
W912DS26BA024_Bid Abstract.pdf PDF
Amendment 0005.pdf PDF
Amendment 0004_01 56 10.00 18.pdf PDF
Amendment 0004_1988_80_gsds.pdf PDF
Amendment 0004_1988_78_gsds.pdf PDF
Amendment 0004_1988_74_gsds.pdf PDF
Amendment 0004_1988_71 composite gsd.jpg JPG image
Amendment 0004_1988_80 penetration graphs.jpg JPG image
Amendment 0004_1988_78 composite gsd.jpg JPG image
Amendment 0004_1988_78 penetration graphs.jpg JPG image
Amendment 0004_1988_71 gsds.pdf PDF
Amendment 0004_1988_74 penetration graphs.jpg JPG image
Amendment 0004_1988_74 composite gsd.jpg JPG image
Amendment 0004_1983_10IndividualGSDs.pdf PDF
Amendment 0004_01 45 00.pdf PDF
Amendment 0004_SBOBA_2025_NAD83_2011_NAVD88_30x30 (2) - Copy.txt.txt TXT text file
Amendment 0004_ADDITIONAL BORROW AREA COORDINATES 202660819.docx DOCX document
Amendment 0004_1988_71 penetration graphs.jpg JPG image
Amendment 0003_01 56 10.00 18.pdf PDF
Amendment 0003_01 45 00.pdf PDF
Amendment 0003_Sea Bright FY 26 Renourishment Plan Set Amendment 0003.pdf PDF
Amendment 0003.pdf PDF
Amendment 0003_01 14 00.pdf PDF
Amendment 0003__01 57 19.pdf PDF
Amendment 0002.pdf PDF
Amendment 0002_01 78 00.pdf PDF
Amendment 0002_01 35 30.pdf PDF
Amendment 0002_01 57 19.pdf PDF
Amendment 0002_01 45 00.pdf PDF
Amendment 0002_01 14 00.pdf PDF
Amendment 0002_01 11 00.pdf PDF
Amendment 0002_Section 01 57 19- Monitoring and Protection Plan.pdf PDF
Amendment 0002_01 56 10.00 18.pdf PDF
Amendment 0001.pdf PDF
Specifications.pdf PDF
Plans.pdf PDF
Solicitation - W912DS26BA024.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The purpose of this Amendment 0004:Block 14 (Description of Amendment/Modification):

1) Bid opening remains Aug 25, 2026 @ 2:00 P.M. EST

2) The following DRAWINGS have been REVISED but NOT REISSUED: G-101, C113, C-114

3) The following SPECIFICATIONS have been REVISED and REISSUED: 01 45 00 and 01 56

10.00 18

4) Respond to Bidder Request for information. For information Only.

NOTE: Bidders must acknowledge receipt of this amendment by date specified in the bid (or as amended) by one of the following methods: In the space provided on the SF 1442, by separate letter, or by signing block 15 below. FAILURE TO ACKNOWLEDGE AMENDMENT BY DATE

SPECIFIED MAY RESULT IN REJECTION OF YOUR BID IN ACCORDANCE WITH THE LATE

BID, LATE MODIFICATION OF BID, OR LATE WITHDRAWAL OF BID (FAR 14.304)

Section 01 00 00 - General Requirements

Miscellaneous text in this section has been modified to:

Seabright to Manasquan, New Jersey FY 26 Renourishment

W912DS26BA024

Amendment 0004

TO BIDDERS:

The following changes shall be made to the drawings and specifications.

DRAWINGS:

1. The following DRAWINGS have been and REVISED REISSUED:

NONE

2. The following DRAWINGS have been but : REVISED NOT REISSUED

W912DS26BA0240004

G-101, C113, C-114

3. The following DRAWINGS have been :ADDED

NONE

4. The following DRAWINGS have been DELETED:

NONE

Specifications:

1. The following SPECIFICATIONS have been and REVISED REISSUED:

01 45 00

01 56 10.00 18

2. The following SPECIFICATIONS have been but : REVISED NOT REISSUED

NONE

3. The following SPECIFICATIONS have been ADDED:

NONE

4. The following SPECIFICATIONS have been DELETED:

NONE

BIDDER'S QUESTIONS AND GOVERNMENT REPLY

(Questions that may be of general interest to all Bidders and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s).

Question #1 On Drawing C-114, the borrow area cross section shows the slope to be 1:5. Section 31 24 00,

2.2.4 Slope in the specification states the borrow must not have side slopes steeper than 1 on 3.Please clarify if the slopes in the borrow area should be 1:5 or 1:3.

Response #1: Contractor to use Specification 31 24 00, 2.2.4; Additional borrow area

Question #2: Answers to RFI's included in Amendment 2 to reference a revised SF1442. Does the Government intend to reissue the corrected SF1442 or should the Contract make the edits themselves?

Response #2: : Form 1442 will be updated. The mentioned sections have not been revised and reissued in Amendment 0002. The contractor uses the specification language.

Question #3: Please confirm the estimated magnitude of construction. Form 1442 of the solicitation states it is between $50,000,000 and $100,000,000 but section 01 11 00, Summary of Work, in the specifications states it is between $25,000,000 and $100,000,000.

Response #3: Form 1442 will be updated. The mentioned sections have not been revised and reissued in Amendment 0002. The contractor uses the specification language.

Question #4: Please confirm when the contractor is required to begin work. Form 1442 of the solicitation states it is within 5 days of NTP but section 01 11 00, Summary of Work, in the specifications states it is within 10 days of NTP.

Response #4: Please see amendment 0002

Question #5: Please confirm that all work and not just Option 3 are required to be completed by the March environmental window as note 7 appears to be written as this only applies to Item Number 0007, Option 3 Long Branch.

Response #5: Please see amendment 0002

Question #6: Please confirm that work is allowed to be performed 24/7. Section 01 14 00, 1.2.5 Exclusionary Period states, "No work may be performed during the Government holidays, without prior written approval of the Contracting Officer. This period has not been considered in computing the time allowed for the performance of this contract."

Response #6: Please see amendment 0002

Question #7: Please provide the most recent borrow area survey data.

Response #7: Latest .XYZ uploaded with Amendment 0003. Updated .txt in Amendment 0004

Question #8 Are bids to be delivered in person or will the government be using PIEE?

Response #8: Please see response in Amendment 0001

Question #9: Please confirm that the contractor gets 250 days for the base work and 359 days if all options are awarded to complete the contract. The contractor is just not allowed to work from March 15th to August 31 st

Response #9: Please see responses in Amendment 0002

Question #10: The solicitation includes a requirement that the project is subject to Executive Order 14063 and incorporates FAR 52.222-33, Alternate I, and FAR 52.222-34 regarding Project Labor Agreements.

Comparable recent USACE procurements for projects of similar contract value have not incorporated this PLA requirement. Please confirm whether the PLA requirement was intentionally included and is mandatory for this contract. If the PLA requirement is mandatory, please clarify whether USACE considered any exception under FAR 22.504(d), and if so, why USACE determined that no exception applies.

Response #10: Please follow FAR guidance as stated within the solicitation.

Question #11 Section 01 57 19, 3.5.1, Preconstruction Air Permits states, "Notify the Air Program Manager, through the Contracting Officer, at least 6 months prior to bringing equipment, assembled or unassembled, onto the Installation, so that air permits can be secured. Necessary permitting time must be considered in regard to construction activities. Clean Air Act (CAA) permits must be obtained prior to bringing equipment, assembled or unassembled, onto the Installation. Confirm that these permits have been obtained." This is not a typical requirement for dredging projects. Please confirm that the contractor is not responsible for obtaining these permits.

Response #11: Please see response in Amendment 0003

IDCode: J
Page: 1
Pages: 5
AmendNo: 0004
EffDate: 19 AUG 2026
ReqNo:
ProjNo: A045648
IssCode: W912DS
AdmCode:
IssuedBy: W2SD ENDIST NEW YORK

KO CONTRACTING DIVISION, 26 FEDERAL PLAZA ROOM 16 300

NEW YORK, NY 10278-0004

UNITED STATES

ORLANDO NIEVES, EMAIL: ORLANDO.NIEVES@USACE.ARMY.MIL TELEPHONE: (917) 790-8078

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912DS26BA024
SolDate: 22 JUL 2026
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: See Schedule
ContNameTitle:
CoNameTitle: MATTHEW LUBIAK
ContDate:
CODate: 19 AUG 2026

File details come from the government source that posted it. Updated .