Replacement of Hydraulic System for Penstock #5
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 191BWC25B0003
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y1KA Construction Of Dams
- Place of performance
- Del Rio, Texas 78840, United States
Notice details come from SAM.gov. Updated .
About this opportunity
The United States Section of the International Boundary and Water Commission (USIBWC) is soliciting bids for the replacement of the hydraulic system for Penstock #5 at Amistad Dam in Texas. The penstock has been non-functional for several years, and the project requires a comprehensive approach including site preparation, full system and structural inspection, hydraulic system replacement, debris disposal, quality control testing, and potentially manufacturing a new penstock bulkhead. Contractors must demonstrate minimum qualifications including at least 5 years of experience on similar construction projects, federal government prime contracting experience, hydraulic systems installation for dams, confined space work capabilities, and crane operations expertise. The solicitation is being issued under FAR Part 14 as an Invitation for Bid with a firm-fixed price contract structure, and evaluation will be based on the contractor's ability to meet technical specifications and minimum qualification requirements. The original due date for bids was July 9, 2025, with written questions due by June 18, 2025, and mandatory site visits scheduled as part of the pre-bid process.
This solicitation does not utilize any set-aside designations and is open to all responsible sources. The contract value is estimated between $1,000,000 and $5,000,000, with work to be performed under NAICS Code 237990 (Other Heavy and Civil Engineering Construction). The project timeline spans 485 calendar days total, including 365 days allocated for construction activities and 120 days for final paperwork and contract closeout. Work will be performed at Amistad Dam in Val Verde County, Texas, with specific site constraints including restricted working hours (7:00 am to 3:30 pm, Monday through Friday), limited access through a port of entry, and load capacity restrictions on the Texas Spur 349 bridge (HS-20 rating) and embankment crest road (70,000 pounds). The contractor must provide their own crane and certified operator to handle the existing penstock bulkhead, which weighs approximately 33,000 pounds and measures 14.3 feet wide by 24.6 feet tall.
Notice text
3 versions
Update #3 · Latest ·
NOTE: Date offers due is extended to July 9, 2025, 3 PM MDT.
-----------------------------------------------------------
NOTE: Answers to questions received incorporated into attached Technical Specifications 191BWC25B0003_Penstock_5_Specs_20250624.
The United States Section of the International Boundary and Water Commission (USIBWC) is issuing a Solicitation for the replacement of the hydraulic system for Penstock #5 in Amistad Dam. This penstock has not been functional in several years. The successful Offeror will fully inspect system and structures and replace hydraulic system to fully restore Penstock #5 to full functionality.
The Construction includes, but is not limited to, site preparation, inspection of all systems and structures, replacement of Penstock #5 hydraulic system, disposal of debris and construction waste, quality control testing, and if awarded, the manufacturer of a new penstock bulkhead.
The following site constraints apply:
- The working hours of the adjacent USIBWC facility are 7:00 am to 3:30 pm, Monday through Friday. The Contractor and any subcontractors shall only work onsite during these proposed hours. USIBWC facilities, including the dam, are closed during all Federal Holidays.
- There is currently only 1 penstock bulkhead, located at Amistad Dam and it is moved via mobile crane. Only 1 penstock can be bulk headed at a time for servicing so design inspections must be coordinated with Amistad Field Office AOM through the COR. Amistad Field Office does not have a certified crane operator at this time so the Contractor must provide a crane an certified operator to perform the relocation of the bulkhead. Several relocations may be required. The bulkhead is approximately 14.3 feet wide by 24.6 feet tall. The weight of the bulkhead gate with lifting beam is approximately 33,000 pounds (16.5 Tons).
- Access to the site is made via Texas Spur 349. Texas Spur 349 bridge inventory rating is limited to HS-20. The load capacity of the embankment crest road is 70,000 pounds.
- Workers must pass through the port of entry to access the worksite. The port of entry is open from 10:00 a.m. to 6:00 p.m. DHS may change these hours without notice. If the Contractor requires to begin work prior to the port of entry opening or after closing, this must be coordinated with the Amistad Dam Area Operations Manager. Workers crossing through the port of entry need to have proper documentation for reentry to the United States.
Per FAR 36.204, the magnitude of the project is estimated between $1,000,000 and $5,000,000.
The work is located in Val Verde County, Texas. A site visit date will be listed in the Solicitation. The work will be performed under NAICS Code 237990. The Contract will be firm-fixed price.
All work is proposed to be completed within four hundred and eighty five (485) calendar days after the Notice to Proceed.
- Three sixty-five (365) calendar days are anticipated for construction.
- The final paperwork for closeout of the Contact shall be completed within one hundred and twenty (120) calendar days of completion of construction.
The time for completion of final paperwork is included in the four hundred and eighty five (485) calendar days. The time stated for completion shall include final cleanup of the premises.
This Solicitation will be issued pursuant to FAR Part 14.
All responsible sources must submit a bid to be considered by the Agency.
Please see document named SBU Document Notice for information in receiving additional documentation.
Update #2 ·
NOTE: Answers to questions received incorporated into attached Technical Specifications 191BWC25B0003_Penstock_5_Specs_20250624.
The United States Section of the International Boundary and Water Commission (USIBWC) is issuing a Solicitation for the replacement of the hydraulic system for Penstock #5 in Amistad Dam. This penstock has not been functional in several years. The successful Offeror will fully inspect system and structures and replace hydraulic system to fully restore Penstock #5 to full functionality.
The Construction includes, but is not limited to, site preparation, inspection of all systems and structures, replacement of Penstock #5 hydraulic system, disposal of debris and construction waste, quality control testing, and if awarded, the manufacturer of a new penstock bulkhead.
The following site constraints apply:
- The working hours of the adjacent USIBWC facility are 7:00 am to 3:30 pm, Monday through Friday. The Contractor and any subcontractors shall only work onsite during these proposed hours. USIBWC facilities, including the dam, are closed during all Federal Holidays.
- There is currently only 1 penstock bulkhead, located at Amistad Dam and it is moved via mobile crane. Only 1 penstock can be bulk headed at a time for servicing so design inspections must be coordinated with Amistad Field Office AOM through the COR. Amistad Field Office does not have a certified crane operator at this time so the Contractor must provide a crane an certified operator to perform the relocation of the bulkhead. Several relocations may be required. The bulkhead is approximately 14.3 feet wide by 24.6 feet tall. The weight of the bulkhead gate with lifting beam is approximately 33,000 pounds (16.5 Tons).
- Access to the site is made via Texas Spur 349. Texas Spur 349 bridge inventory rating is limited to HS-20. The load capacity of the embankment crest road is 70,000 pounds.
- Workers must pass through the port of entry to access the worksite. The port of entry is open from 10:00 a.m. to 6:00 p.m. DHS may change these hours without notice. If the Contractor requires to begin work prior to the port of entry opening or after closing, this must be coordinated with the Amistad Dam Area Operations Manager. Workers crossing through the port of entry need to have proper documentation for reentry to the United States.
Per FAR 36.204, the magnitude of the project is estimated between $1,000,000 and $5,000,000.
The work is located in Val Verde County, Texas. A site visit date will be listed in the Solicitation. The work will be performed under NAICS Code 237990. The Contract will be firm-fixed price.
All work is proposed to be completed within four hundred and eighty five (485) calendar days after the Notice to Proceed.
- Three sixty-five (365) calendar days are anticipated for construction.
- The final paperwork for closeout of the Contact shall be completed within one hundred and twenty (120) calendar days of completion of construction.
The time for completion of final paperwork is included in the four hundred and eighty five (485) calendar days. The time stated for completion shall include final cleanup of the premises.
This Solicitation will be issued pursuant to FAR Part 14.
All responsible sources must submit a bid to be considered by the Agency.
Please see document named SBU Document Notice for information in receiving additional documentation.
Update #1 ·
The United States Section of the International Boundary and Water Commission (USIBWC) is issuing a Solicitation for the replacement of the hydraulic system for Penstock #5 in Amistad Dam. This penstock has not been functional in several years. The successful Offeror will fully inspect system and structures and replace hydraulic system to fully restore Penstock #5 to full functionality.
The Construction includes, but is not limited to, site preparation, inspection of all systems and structures, replacement of Penstock #5 hydraulic system, disposal of debris and construction waste, quality control testing, and if awarded, the manufacturer of a new penstock bulkhead.
The following site constraints apply:
- The working hours of the adjacent USIBWC facility are 7:00 am to 3:30 pm, Monday through Friday. The Contractor and any subcontractors shall only work onsite during these proposed hours. USIBWC facilities, including the dam, are closed during all Federal Holidays.
- There is currently only 1 penstock bulkhead, located at Amistad Dam and it is moved via mobile crane. Only 1 penstock can be bulk headed at a time for servicing so design inspections must be coordinated with Amistad Field Office AOM through the COR. Amistad Field Office does not have a certified crane operator at this time so the Contractor must provide a crane an certified operator to perform the relocation of the bulkhead. Several relocations may be required. The bulkhead is approximately 14.3 feet wide by 24.6 feet tall. The weight of the bulkhead gate with lifting beam is approximately 33,000 pounds (16.5 Tons).
- Access to the site is made via Texas Spur 349. Texas Spur 349 bridge inventory rating is limited to HS-20. The load capacity of the embankment crest road is 70,000 pounds.
- Workers must pass through the port of entry to access the worksite. The port of entry is open from 10:00 a.m. to 6:00 p.m. DHS may change these hours without notice. If the Contractor requires to begin work prior to the port of entry opening or after closing, this must be coordinated with the Amistad Dam Area Operations Manager. Workers crossing through the port of entry need to have proper documentation for reentry to the United States.
Per FAR 36.204, the magnitude of the project is estimated between $1,000,000 and $5,000,000.
The work is located in Val Verde County, Texas. A site visit date will be listed in the Solicitation. The work will be performed under NAICS Code 237990. The Contract will be firm-fixed price.
All work is proposed to be completed within four hundred and eighty five (485) calendar days after the Notice to Proceed.
- Three sixty-five (365) calendar days are anticipated for construction.
- The final paperwork for closeout of the Contact shall be completed within one hundred and twenty (120) calendar days of completion of construction.
The time for completion of final paperwork is included in the four hundred and eighty five (485) calendar days. The time stated for completion shall include final cleanup of the premises.
This Solicitation will be issued pursuant to FAR Part 14.
All responsible sources must submit a bid to be considered by the Agency.
Please see document named SBU Document Notice for information in receiving additional documentation.
Files
Show all 20
Notice history
| Notice | Type | Posted |
|---|---|---|
| Replacement of Hydraulic System for Penstock #5 | Award Notice | |
| This notice | Solicitation | |
| Replacement of Hydraulic System for Penstock #5 | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Bradbury Dam Outlet Valve Replacement | — | No set-aside |