- NAICS code
- 237990 Other Heavy and Civil Engineering Construction
- PSC
- Y1KA Construction Of Dams
- Place of performance
- Del Rio, Texas 78840, United States
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The United States Section of the International Boundary and Water Commission (USIBWC) is seeking a contractor to replace the hydraulic system for Penstock #5 at Amistad Dam, located in Val Verde County, Texas. The project requires a comprehensive replacement of a non-functional hydraulic system, including site preparation, system inspection, hydraulic replacement, debris disposal, and potential manufacture of a new penstock bulkhead. Contractors must provide a certified crane operator capable of handling a 33,000-pound bulkhead and work within strict operational constraints, including facility hours from 7:00 am to 3:30 pm Monday through Friday. The solicitation will be issued under FAR Part 14 procedures and is expected to be posted around April 4, 2025, with a minimum 30-day availability period. All responsible sources may submit a bid for consideration, with work to be performed under NAICS Code 237990.
The contract is not set aside for any specific category of business and will be awarded as a firm-fixed price contract. The project is estimated between $1,000,000 and $5,000,000, with a total project duration of 485 calendar days, including 365 days for construction and 120 days for final paperwork. The bulkhead to be handled is approximately 14.3 feet wide by 24.6 feet tall, and contractors must navigate site-specific access limitations, including crossing a port of entry with specific operating hours. Workers will need proper documentation for U.S. reentry, and access to the site is limited by bridge and embankment load capacities. The contract requires coordination with the Amistad Field Office Area Operations Manager and adherence to strict logistical and operational guidelines throughout the project's implementation.
Notice text
The United States Section of the International Boundary and Water Commission (USIBWC) is issuing a Solicitation (IFB) for the replacement of the hydraulic system for Penstock #5 in Amistad Dam. This penstock has not been functional in several years. The successful Offeror will fully inspect system and structures and replace hydraulic system to fully restore Penstock #5 to full functionality.
The Construction includes, but is not limited to site preparation, inspection of all systems and structures, replacement of Penstock #5 hydraulic system, disposal of debris and construction waste, quality control testing, and if awarded, the manufacturer of a new penstock bulkhead.
The following site constraints apply:
- The working hours of the adjacent USIBWC facility are 7:00 am to 3:30 pm, Monday through Friday. The Contractor and any subcontractors shall only work onsite during these proposed hours. USIBWC facilities, including the dam, are closed during all Federal Holidays.
- There is currently only 1 penstock bulkhead, located at Amistad Dam and it is moved via mobile crane. Only 1 penstock can be bulk headed at a time for servicing work must be coordinated with Amistad Field Office AOM through the COR. Amistad Field Office does not have a certified crane operator at this time so the Contractor must provide a crane certified operator to perform the relocation of the bulkhead. Several relocations may be required. The bulkhead is approximately 14.3 feet wide by 24.6 feet tall. The weight of the bulkhead gate with lifting beam is approximately 33,000 pounds (16.5 Tons).
- Access to the site is made via Texas Spur 349. Texas Spur 349 bridge inventory rating is limited to HS-20. The load capacity of the embankment crest road is 70,000 pounds.
- Workers must pass through the port of entry to access the worksite. The port of entry is open from 10:00 a.m. to 6:00 p.m. DHS may change these hours without notice. If the Contractor requires to begin work prior to the port of entry opening or after closing, this must be coordinated with the Amistad Dam Area Operations Manager. Workers crossing through the port of entry need to have proper documentation for reentry to the United States.
Per FAR 36.204, the magnitude of the project is estimated between $1,000,000 and $5,000,000.
The work is located in Val Verde County, Texas. A site visit date will be listed in the Solicitation. The work will be performed under NAICS Code 237990. The Contract will be firm-fixed price.
All work is proposed to be completed within four hundred and eighty five (485) calendar days after the Notice to Proceed.
- Three sixty-five (365) calendar days are anticipated for construction.
- The final paperwork for closeout of the Contact shall be completed within one hundred and twenty (120) calendar days of completion of construction.
The time for completion of final paperwork is included in the four hundred and eighty five (485) calendar days. The time stated for completion shall include final cleanup of the premises.
The Solicitation will be issued pursuant to FAR Part 14.
The Solicitation is expected to be posted on or about April 4, 2025 (this is a target date which may slip or change). The Solicitation will be available for a minimum of thirty (30) calendar days.
This is a Presolicitation Notice. The Solicitation will include information on how to obtain the Scope of Work and attachments. All responsible sources may submit a bid to be considered by the Agency.
Files
| File | Type | Posted |
|---|---|---|
| Presolicitation Notice - Replacement of Hydraulic System Penstock 5.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Replacement of Hydraulic System for Penstock #5 | Award Notice | |
| Replacement of Hydraulic System for Penstock #5 | Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Bradbury Dam Outlet Valve Replacement | — | No set-aside |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity