SBU_Document_Notice.pdf

PDF 83 KB Posted

Attached to
Replacement of Hydraulic System for Penstock #5
Solicitation number
191BWC25B0003
Issued by

About this file

This document is a Request for Proposal (RFP) notice for the Replacement of Amistad Penstock #5 Hydraulic System (Solicitation Number 191BWC25B0003) issued by the International Boundary and Water Commission (IBWC). The solicitation requires contractors to complete a nondisclosure agreement (IBWC Form 358) to access sensitive but unclassified (SBU) documents related to the project, with access limited to two email addresses per contractor.

The RFP details a complex dam infrastructure project involving the replacement of a non-functional penstock hydraulic system at Amistad Dam in Val Verde County, Texas. The project is estimated between $1-5 million, with a total project timeline of 485 calendar days (including 365 days for construction) and will require specialized skills including site preparation, system inspection, hydraulic system replacement, debris disposal, and bulkhead handling. Specific site constraints include working hours from 7:00 am to 3:30 pm Monday through Friday, coordination with port of entry access, and limitations on equipment load capacities. The contract will be firm-fixed price under NAICS Code 237990, with contractors required to provide their own crane and certified operator for bulkhead relocation.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 191BWC25B0003 - Replacement of Amistad Penstock #5

Hydraulic System

The documents listed below will be made available to interested contractors once a IBWC Form 358

Nondisclosure Agreement has been completed and provided to seone.jones@ibwc.gov and adrian.knights@ibwc.gov. Access will be granted for no more than two email addresses per contractor.

All unsuccessful contractors must submit IBWC Form 358A-Nondisclosure Agreement Release within seven days of receiving notice of their unsuccessful offer.

AVAILABLE SBU DOCUMENTS

SBU_00_31_19_01_1-4-A-1_USACE_Amistad_Penstock_#5_Trip_Report_20190610.pdf

SBU_00_31_19_01_1-4-A-2_Amistad_Dam_Irrigation_Penstock_Gate_Study_200610_REDACTED.pdf

SBU_00_31_19_01_1-4-A-3_Opening_Gates_in_Penstock_4_19860506.pdf

SBU_00_31_19_01_1-4-B_Amistad_Specifications_Vol_I_UDA_65-3.pdf

SBU_00_31_19_01_1-4-B_Amistad_Specifications_Vol_II_UDA_65-3.pdf

SBU_00_31_19_01_1-4-D_Amistad_Dam_1971_O-M_Manual.pdf

SBU_00_31_19_01_1-4-E_Report_on_Control_Changes_to_Penstock_Gates_4_and_5_19701119.pdf

SBU_00_31_19_01_Table_1_1_of_3_Penstock_5_Drawings.pdf

SBU_00_31_19_01_Table_1_2_of_3_Penstock_5_Drawings.pdf

SBU_00_31_19_01_Table_1_3_of_3_Penstock_5_Drawings.pdf

SBU_01_55_26_01_1-6-C-4_Amistad_Dam_Structural_Analysis_of_Bridge_Deck_200601.pdf

All forms are available at: www.ibwc.gov/resources-info/ mailto:seone.jones@ibwc.gov mailto:adrian.knights@ibwc.gov https://www.ibwc.gov/resources-info/