127EAW25R0042 - Monument Road Repair 4N47
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 127EAW25R0042
- Agency
-
Forest Service
Department of Agriculture
- Responses due
- Set-aside
- Total Small Business
Opportunity facts
- NAICS code
- 237310 Highway, Street, and Bridge Construction
- Place of performance
- Big Bar, California 96010, United States
- Points of contact
Notice details come from SAM.gov. Updated .
About this opportunity
The U.S. Department of Agriculture Forest Service is seeking contractors to repair roads damaged by the Monument Fire in the Shasta-Trinity National Forest, specifically focusing on the 4N47 (Monument Road/Corral Bottom Road) repair project. The scope includes asphalt road replacement, vegetation removal, base repairs, full depth reclamation, and related construction activities across approximately 10.23 miles of roadway, with work including mobilization, clearing and grubbing, aggregate base installation, roadway reconditioning, asphalt overlay, chip sealing, pothole repair, traffic control, and sign installation. The government will evaluate proposals using a tradeoff process with technical factors weighted approximately equally to price, utilizing an adjectival rating system to assess technical proposals, business proposals, past performance, and pricing. Contractors must submit electronic proposals by 1300 PST on August 5, 2025, including five separate document attachments: Standard Form 1442, price proposal, business proposal, technical proposal, and bid guarantees. All requests for information were required to be submitted to Contracting Officer Greg Cunningham by July 21, 2025, with two rounds of RFI responses already posted as amendments to the solicitation.
This opportunity is designated as a Total Small Business Set-Aside under NAICS code 237310 (Highway, Street, and Bridge Construction), with an estimated project value between $1,000,000 and $5,000,000. No current incumbent contractors are identified in the solicitation documents. The contract includes a mandatory 75-calendar day performance period with an anticipated start date in late summer 2025, though RFI responses indicate a potential Spring/Summer 2026 start date contingent on meeting specific temperature requirements. Work is restricted to non-holiday weekdays from 0700-1900 hours and includes specific requirements for archaeological monitoring, utility protection, and debris disposal. The project will be performed in Big Bar, California, within the Shasta-Trinity National Forest in Trinity County, with the work sites being publicly accessible for contractor inspection prior to proposal submission.
Notice text
3 versions
Update #3 · Latest ·
127EAW25R0042 - Monument Road Repair 4N47 - A00002 - RFI Responses 2
Shasta-Trinity National Forest
This purpose of this solicitation amendment is to post RFI round 2 responses.
Attached is "127EAW25R0042 - RFI Official Responses - 2" which are hereby incorporated into any subsequent contract award. Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.
//////////////////////////////////////////////////////////////////////////////////////////////////
127EAW25R0042 - Monument Road Repair 4N47 - A00001 - RFI Responses
Shasta-Trinity National Forest
This purpose of this solicitation amendment is to post RFI round 1 responses, revised schedule of items, and water drafting info.
Attached are "127EAW25R0042 - RFI Official Responses - 1", "2. Schedule of Items - REVISED 7-28-2025, and "Water Drafting Specifications" which are hereby incorporated into any subsequent contract award. Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.
//////////////////////////////////////////////////////////////////////////////////////////////////
127EAW25R0042 - Monument Road Repair 4N47
Shasta-Trinity National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $1,000,000 and $5,000,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, July 21st, 2025.
A FS organized pre-proposal site visit will NOT be held. The project locations are open to the public and can be viewed by each prospective offeror. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Update #2 ·
127EAW25R0042 - Monument Road Repair 4N47 - A00001 - RFI Responses
Shasta-Trinity National Forest
This purpose of this solicitation amendment is to post RFI round 1 responses, revised schedule of items, and water drafting info.
Attached are "127EAW25R0042 - RFI Official Responses - 1", "2. Schedule of Items - REVISED 7-28-2025, and "Water Drafting Specifications" which are hereby incorporated into any subsequent contract award. Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.
//////////////////////////////////////////////////////////////////////////////////////////////////
127EAW25R0042 - Monument Road Repair 4N47
Shasta-Trinity National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $1,000,000 and $5,000,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, July 21st, 2025.
A FS organized pre-proposal site visit will NOT be held. The project locations are open to the public and can be viewed by each prospective offeror. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Update #1 ·
127EAW25R0042 - Monument Road Repair 4N47
Shasta-Trinity National Forest
FAR 32.204 Disclosure of Magnitude of the Construction Project: Between $1,000,000 and $5,000,000
Set Aside: Total Small Business Set Aside
IMPORTANT NOTES:
See Section L, Paragraph L.2 for the Documents to Submit with Your Proposal
All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, July 21st, 2025.
A FS organized pre-proposal site visit will NOT be held. The project locations are open to the public and can be viewed by each prospective offeror. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Files
Show all 14
Notice history
| Notice | Type | Posted |
|---|---|---|
| 127EAW25R0042 - Monument Road Repair 4N47 | Award Notice | |
| This notice | Solicitation | |
| Forest Service - Disaster, Monument Road Repair 4N47 | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Custer Gallatin National Forest Ashland and Sioux Road Maintenance | Region 6 - Pacific Northwest Region | Total Small Business | |
| Administrative Parking Lot Repairs | Forest Service | Total Small Business | |
| Forest Wide Decommissioning Project | Forest Service | Total Small Business | |
| Jake Rocks Road Reconstruction | Forest Service | Total Small Business | |
| Chino Emergency Repairs | Forest Service | Total Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity