PART I—THE SCHEDULE
SECTION B-- SCHEDULE OF ITEMS
B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)
PROJECT: Monument Road Repair 4N47
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 15101 |
| Mobilization |
| 1 |
| Lump Sum |
| $___________ |
| $___________ |
| 20103 |
| Clearing and grubbing, disposal method scattering (Roadside) |
| 10.23 |
| Mile |
| $___________ |
| $___________ |
| 30103 |
| Aggregate base w/compaction method <D> |
| 3,700.00 |
| Cubic Yard |
| $___________ |
| $___________ |
| 30315 |
| Roadway reconditioning |
| 10.23 |
| Mile |
| $___________ |
| $___________ |
| 40304 |
| CalTrans 1/2 PG 64-16 w/ Coat Depth 2.0'' |
| 5.15 |
| Mile |
| $___________ |
| $___________ |
| 40701 |
| Chip Seal Double 1/2'' and 3/8'' w/fog seal |
| 5.12 |
| Mile |
| $___________ |
| $___________ |
| 30403 |
| Full Depth Reclamation (FDR) 4-6'' |
| 22,000.00 |
| SY |
| $___________ |
| $___________ |
| 41802 |
| Pothole Patch/Repair for Asphalt Overlay |
| 650.00 |
| SY |
| $___________ |
| $___________ |
| 63501 |
| Traffic Control |
| 1.00 |
| Lum Sum |
| $___________ |
| $___________ |
| 71801 |
| Sign Install |
| 8.00 |
| EA |
| $___________ |
| $___________ |
B.2 SCHEDULE OF ITEMS - (OPTION 1)
PROJECT: Monument Road Repair 4N47 – OPTION 1
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 40304OP1 |
| CalTrans 1/2 PG 64-16 Depth 2.0'' Overlay w/Tack Coat |
| 5.12 |
| Mile |
| $___________ |
| $___________ |
| 40701OP1 |
| **REMOVE**Chip Seal Double 1/2'' and 3/8'' w/Fog Seal |
| 1 |
| LS |
| $___________ |
| $___________ |
| OPTION 1 TOTAL: |
| $___________ |
B.3 SCHEDULE OF ITEMS - (OPTION 2)
PROJECT: Monument Road Repair 4N47 – OPTION 2
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
| 63401OP2 |
| Pavement Marking - Fog Lines, Stop Bars & Yield |
| 108,200.00 |
| LF |
| $___________ |
| $___________ |
| OPTION 2 TOTAL: |
| $___________ |
B.4 SCHEDULE OF ITEMS - (OPTION 3)
PROJECT: Monument Road Repair 4N47 – OPTION 3
| Item |
| Construction Items |
| Qty |
| UNIT |
| Unit Price |
| Total Price |
60201-
60OP3
| 60-inch Pipe Culvert, Metal Pipe |
| 60.00 |
| LF |
| $___________ |
| $___________ |
| OPTION 3 TOTAL: |
| $___________ |
| BASE + OPTION 1, 2, & 3 TOTAL: |
| $__________________ |
B.2 SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.
* One award will be made from this solicitation, contractors must submit pricing for all items.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
| Company Name: |