This Statement of Work (SOW) details a road repair project for the USDA Forest Service in the Shasta Trinity National Forest. The project involves repairing Monument Road (4N47 Corral Bottom Road) damaged by the Monument Fire, with work including asphalt road replacement, vegetation removal, base repairs, full depth reclamation, and related activities. The primary objectives are to restore road functionality, ensure public safety, and meet road use standards.
Key project specifications include: 2-inch asphalt pavement on a 16-24 foot wide roadway, road reconditioning, clearing and grubbing, aggregate base installation, and traffic control. The project has a desired start date in summer 2025 with a 75-calendar day performance period. Optional work items include replacing chip seal with asphalt, pavement markings, and installing a 60-inch culvert pipe. The project is estimated between $1-5 million and is set aside for small businesses. Work is restricted to non-holiday weekdays from 0700-1900 hours, with specific requirements for archaeological monitoring, utility protection, and debris disposal.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Disaster, Monument Road Repair 4N47
Shasta Trinity National Forest
Contents Project General Information
1.0 Scope of Work
1.1 Mobilization
1.2 Reconditioning
1.3 Clearing and Grubbing
1.4 Aggregate Base
1.5 Full Depth Reclamation
1.6 Asphalt Concrete
1.7 Double Chip Seal
1.8 Temporary Traffic Control
1.9 Replacing Single Post and Double Post Signs
2.0 Location
4.0 Estimated Start Date / Period of Performance
5.0 Drawings and Specifications
6.0 Restrictions on Work
6.0 Camping and Housing
7.0 Required Submittals
Contractor Requirements
8.0 Technical Requirements / Tasks
9.0 Contractor’s Key Personnel
10.0 Additional Information
11.0 Options
Project Disaster, Monument Road Repair 4N47
General Information
1.0 Scope of Work
This project is located on three Forest Service roads 4N47 Corral Bottom Road.
The scope of this project entails repairing roads damaged by the Monument Fire and suppression activities on 4N47 road. The work involves asphalt road replacement, vegetation removal, base repairs and full depth reclamation, and other related activity due to heat damage, base failure, fire damage, and suppression activities. The project aims to restore the roads and features to a functional state that meets standards for public use, ensuring safety and usability of the roads through necessary repairs and alterations.
Except as otherwise noted, the Contractor shall furnish all labor, materials, equipment, supervision, and transportation necessary for the successful completion of the work described in this contract. The Forest will provide existing undamaged materials salvaged from demolition activities.
1.1 Mobilization
Includes mobilization and demobilization to and from the project locations. This item also includes fire protection, equipment cleaning, movement of boulders, permits, and other incidentals.
1.2 Reconditioning
Road reconditioning includes clearing and grubbing up to 4 feet from the existing roadway and or from ditch edge, removing of vegetation and debris over 6 inches within the roadbed, shoulders, and compact and shape the roadbed according to the established line, grade, and cross-section needed with proper moisture content prior to an asphalt overlay. This work also includes but not limited to shoulders, turnouts, ditches, culverts, and all drainage features.
Roadbed shall be approved by COR (Contracting Officer Representative) prior to asphalt placement. For paved surfaces, pay item includes cleaning road surface of all debris or organic material.
1.3 Clearing and Grubbing
This work consists of work outlined in Section 20. This item work in conjunction with Reconditioning pay item. It involves the clearing and grubbing within designated limits - 10 feet, encompassing the removal of trees, brush, downed timber, and other vegetation, while ensuring the preservation of any designated vegetation. This process includes cutting trees to specified heights, grubbing to eliminate stumps and roots, and backfilling any resultant holes to match the surrounding ground level. The disposal of merchantable timber and debris will be conducted through scattering, with the stipulation that such scattering shall not occur on private lands. All activities will adhere to pertinent regulations and standards to ensure environmental protection and compliance with the contract specifications. Work will be performed on each side of the roadway where it applies and is intended for sight distance purposes only. A clean and neat final appearance is a requirement and the contractors responsibility.
1.4 Aggregate Base
This work consists of constructing one or more courses of aggregate on a prepared surface for the use of within the contact and project areas. Compaction will be required after placement and all depths are compacted depth in plans.
Rocking the shoulders and turnouts and other roadside features are within the scope and in the plans. Aggregate base will be placed 1-foot width along both shoulders that runs the length of the roadway being paved or otherwise staked by COR. Compaction will be required after placement aggregate base.
1.5 Full Depth Reclamation
This work consists of pulverizing an existing pavement and base in-place, adding crushed aggregate as required, mixing this material with water, and shaping and compacting the mix to produce a base. Establish profile and cross slope control. Maintain the existing cross slope or crown if none is established. Before pulverizing, remove and dispose of unsuitable material as directed by the CO. Replace unsuitable material with crushed aggregate which is incidental to work item. Protect manholes, valve covers, and other buried facilities from damage. Depth is 4-6 inches FDR and is contractors’ responsibility to ensure base is to standards before paving. Base will need COR approval before paving work begins.
1.6 Asphalt Concrete
This work consists of constructing asphalt concrete pavement using a hot or warm mix asphalt (HMA or WMA). Asphalt will be consistent with 2-inch asphalt with a single-lane and or two-lane roadway width of 16 to 24 feet +-. Compaction testing and finishing will be required and enforced for each segment prior to beginning the mixing operations on the next segment. Uniformly mix of asphalt from one source will be used and enforced. Asphalt will only be land when surface is prepared. See plans for technical requirements but all repairs/defects in pavement must be repaired before asphalt paving begins. This is the same for overlay operations
Contractor Testing (Asphalt Compaction)
Testing performed by the contractor to ensure that the Hot Mix Asphalt-HMA being produced or placed meets the requirements of the specifications in the FP-14 and FSSS. Control testing of aggregates and HMA quality characteristics must be performed at a specified minimum frequency. Sampling should be performed at locations such as plant, windrow, or mat to assure that quality control test results are not influenced by sampling location. Sampling must be random. The contractor performs quality control testing for asphalt rubber binder, gradation, and fabric content of crumb rubber modifier, aggregate and recycled asphalt pavement moisture, and recycled asphalt pavement gradation and binder contents. See table 403-2 FP-14: Testing done 3 per 700 tons in place after compacting.
1.7 Double Chip Seal
This work consists of constructing a double layer of chip seal with fog coat. Work will conform to the specification in section 407 of the FP-14. Test strips will be conducted with COR present. All flow rates will conform to standards and will be required to document and record during project. Conduct work on a prepared surface or a repaired surface only. Pay item includes all incidental to include but not limited to compaction testing, all coats or sealers, and water.
1.8 Temporary Traffic Control
This work consists of furnishing, installing, maintaining, relocating, and removing temporary traffic control devices and services as ordered for the control and protection of public traffic through the project. Advance warning arrow board, barricade, and warning light types are designated in the MUTCD. Allow traffic through project with minimal delays and when it is safe. Contractor will implement a traffic control plan in accordance with all specification. Plan may require personal to manage traffic on both ends of roadway. Plan must be submitted to CO and COR for pre-approval before work begins.
Note: Project area has private property and residences in the area. Contractor will need to notify and allow reasonable access for residents during reconstruction.
1.9 Replacing Single Post and Double Post Signs
This work consists of supplying, furnishing, and installing signs specified within the plans. Signs will be installed in accordance with all standards and manuals to ensure compliance with MUTCD and Forest Sign standards. Install signs at COR staked locations and ensure sign accuracy with COR before manufacturing and installation. See FP-14 section 718 for more details.
2.0 Location
Starting from eureka way in Redding, California, head north on Ca-273/eureka way for about 7.6 miles. Continue onto ca-299 west and drive for approximately 58.7 miles. Take the exit for Corral Bottom Road and proceed for about 5.6 miles, which should take Around 14 minutes. Turn left onto corral bottom road, then make a slight right to stay on corral bottom road. Continue For about 5.5 miles to reach your final destination 4N47.
GPS coordinates 40.7119004. -123.2864034.
4.0 Estimated Start Date / Period of Performance
The desired start date is summer 2025. The period of performance is 75 calendar days after the Notice to Proceed is issued.
5.0 Drawings and Specifications
Refer to “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-14.
[X] Construction Standard Institute (CSI) specifications These specifications are physically incorporated in the solicitation.
6.0 Restrictions on Work
• Work hours are limited to non-holiday weekdays, Monday – Friday, 0700 – 1900. Work site much be clear by noon the Friday before a Monday holiday.
• In accordance with the fire plan, if included in Section J.
• When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.
• For sites requiring archaeology monitoring, contractor must notify COR at least 24 hours prior to any ground disturbing activities and no ground disturbing activities may occur without a Forest Service archaeologist on site.
• When the Contracting Officer or designated representative determines that work must stop due to the presence of archaeological artifacts.
• Contractor is responsible for the security of their tools and equipment at all times.
• Contractor is responsible for removal and disposal all excavated dirt and shall not leave excavated dirt scattered over the site, unless approved by the COR.
• All trash and loose materials shall be secured by the contractor daily.
• The Contractor is responsible for installing sediment control devices, such as straw wattles, to prevent sediment runoff to nearby areas. Excavation work shall not commence until sediment control devices have been installed and approved by the COR.
• The Contractor shall not use Government trash facilities without the COR’S approval.
• All construction debris remains the property of the Contractor and shall be properly disposed of off National
Forest Land.
• The contractor will be able to utilize the Forest Service Roads; however, the Contractor will be responsible for any damage to the roads due to construction activities. The contractor shall be responsible for obtaining permission to use all other roads and staging areas.
6.0 Camping and Housing
Camping is not permitted in US Forest Service campgrounds. Contractor [ ] will [X] will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right.
7.0 Required Submittals
Submittals for this project include, but are not limited to:
o Bonds:
o Bid Bond o Performance Bond o Payment Bond o Materials Approval and Slips:
o Material: Approval of all materials o Material Delivery Tickets: Documentation of materials delivered to the site, including quantities and specifications.
o Material Certification: Certification that materials meet the specified standards and requirements.
o Testing:
o Material Testing Reports: Results from testing materials to ensure compliance with project specifications.
o Quality Assurance Testing: Documentation of tests conducted to verify the quality of work and materials.
o Compaction:
o Compaction Test Results: Reports detailing the compaction tests performed on the road base and subgrade materials.
o Compaction Certification: Certification that compaction meets the required standards.
o Site Safety Plan:
o Safety Plan Submission: A detailed plan outlining safety measures and protocols to be followed on-site.
o Proposed Project Plan / Project Updates Weekly:
o Defining the responsibilities, timeline, risks and milestones of contract objectives.
o Weekly Progress Reports: Regular updates on the project's status, including completed work, upcoming tasks, and any issues encountered.
o Schedule Updates: Revised project schedules reflecting any changes or delays.
Contractor Requirements
8.0 Technical Requirements / Tasks
The Contractor shall possess all necessary licenses required by the State of California to perform road repair work under this contract. Furthermore, the Contractor is responsible for obtaining any necessary permits prior to commencing work, ensuring compliance with all applicable Federal, State, and local laws and regulations.
9.0 Contractor’s Key Personnel
Contractor’s representative or work site superintendent is a required key personnel. Must be present at all times when the sub-contractor(s) and/or contractor’s employees are working on the site and when the contractor is not present.
Must have experience in projects with similar levels of deliverables, complexity, and value. A resume of this key personnel shall be provided for review to the government before work starts. The government reserves the right to deny or accept this personnel after reviewing their qualifications
10.0 Additional Information
Utilities Contractor shall handle water or use given water locations and must always be protecting above and below ground utilities in the project area.
Use of Utilities Water is available on/near site and shall be coordinated with the Contracting Officer’s Representative (COR) for access/map of approved drafting location. If water is unavaible do to time of year or drout the contractors is responable for water needed. Cellular phone service may be available/ limited for this project location.
Protection of Existing Improvements The Contractor shall protect existing pavement, buildings, landscaping, and other existing improvements. The Contractor shall handle repairing any damage to existing facilities and improvements.
Disposal
Cleanup and remove debris around immediate and surrounding building or work areas and removal from Gov’t property to a permitted disposal facility.
11.0 Options
Option Item #1
This item removes the Chip Seal from the Base contract and replaces it with Asphalt for the same distance and miles.
Option Item #2
Pavement Marking – Fog Lines, Stop Bars, and Yield.
The pavement marking work, as specified in Section 634 of the FP-14 guidelines, encompasses the installation of fog lines, stop bars, and yield markings. Fog lines will be applied along the edges of the travel lanes to improve visibility and delineate the roadway, while stop bars will be positioned at intersections to indicate the required stopping point for vehicles. Yield markings will be installed to designate areas where drivers must yield to oncoming traffic. All markings will be executed in accordance with applicable standards for visibility, durability, and reflective characteristics, ensuring compliance with traffic safety regulations and enhancing overall roadway safety. Conform with CalTrans standards for application and type and beads.
Option #3
60-inch Culvert Pipe, Metal Pipe
This work consists of supplying, furnishing, and installing culvert with compaction at designated location. Removal and disposal of pipe off government property at appropriate disposal site. Bedding materials and bands and all other work is included in this pay item. It is the contractor's responsibility to ensure stability and alignment with COR and technical staff before final installation.
| Project |
| General Information |
| 1.0 Scope of Work |
| 1.1 Mobilization |
| 1.2 Reconditioning |
| 1.3 Clearing and Grubbing |
| 1.4 Aggregate Base |
| 1.5 Full Depth Reclamation |
| 1.6 Asphalt Concrete |
| 1.7 Double Chip Seal |
| 1.8 Temporary Traffic Control |
| 1.9 Replacing Single Post and Double Post Signs |
| 2.0 Location |
| 4.0 Estimated Start Date / Period of Performance |
| 5.0 Drawings and Specifications |
| 6.0 Restrictions on Work |
| 6.0 Camping and Housing |
| 7.0 Required Submittals |
| Contractor Requirements |