Water Distribution ICRA FINAL.pdf

PDF 198 KB Posted

Attached to
Z1DA--667-18-119, Upgrade Water Distribution System, Main Hospital
Solicitation number
36C25622R0067
Issued by

About this file

This document contains an Infection Control Risk Assessment (ICRA) for an upcoming water distribution system upgrade project at the Overton Brooks VA Medical Center. The ICRA identifies the construction project as a Type B activity due to replacement and installation of components that will result in loss of environmental controls. It further specifies that the project will affect medium risk patient areas. Based on these factors, the ICRA matrix classifies the precaution level for the project as Class II. The ICRA receives preliminary approval and must be posted on site once construction begins.

The related federal contract opportunity is solicitation number 36C25622R0067 for project 667-18-119 to upgrade the main hospital's water distribution system issued by the Department of Veterans Affairs Veterans Health Administration VISN 16. The purpose of the posting is to solicit bids for the project.

View the file

Other files

File Type Posted
36C25622R0067 0003.pdf PDF
RFIs 36C25622R0067 sheet 1 - OBVA Answered.docx DOCX document
RFIs 36C25622R0067 sheet 2 - OBVA Answered.docx DOCX document
36C25622R0067 0002.pdf PDF
S04 Construction Site Visit 667-18-119.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 2.pdf PDF
36C25622R0067 0001.pdf PDF
Water Distrib - Resubmission - Asbestos Dwgs.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 4.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 2.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 3.pdf PDF
Water Distrib - Resubmission - Plumbing As-Built Riser Diagram Dwgs.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 1.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 3.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 1.pdf PDF
Water Distrib - Resubmission - ICRA Dwgs 2.pdf PDF
WD - LA20220031 MOD 3 DATED 6-24-2022.txt TXT text file
36C25622R0067 EXHIBIT B R1.docx DOCX document
36C25622R0067 EXHIBIT E R1.docx DOCX document
Water Distrib - Resubmission - Civil Dwgs.pdf PDF
VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.docx DOCX document
36C25622R0067 EXHIBIT C R1.docx DOCX document
36C25622R0067 EXHIBIT D R1.docx DOCX document
Water Distrib - Resubmission - General Dwgs.pdf PDF
Water Distrib - Resubmission - Electrical Dwgs.pdf PDF
Water Distribution System Class I Precautions FINAL.pdf PDF
P09 Rev 7-1-22 667-18-111 Combinded Specifications.pdf PDF
P09 Construction REVISED SOW - 667-18-119.doc DOC document
36C25622R0067 EXHIBIT A R1.docx DOCX document
Water Distribution Class III Precaution FINAL.pdf PDF
Water Distribution System Preliminary Class 11 FINAL.pdf PDF
Water Distrib - Resubmission - ICRA Dwgs 1.pdf PDF
Cross Connection Sheets.pdf PDF
36C25622R0067 EXHIBIT F R1.docx DOCX document
36C25622R0067 Solicitation.docx DOCX document
Dead Leg Criteria Checklist.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VAMC Infection Prevention & Control Construction Risk Assessment (ICRA)

*A preliminary ICRA is required for contracting purposes only; do not post during construction. The FINAL ICRA must be posted at the construction site.

Project: Upgrade Water Distribution 667-18-119 Preliminary Assessment* by: Vickie L. Moore Date: 9/20/19

FINAL ICRA Determined and Processed by: Final Date:

STEP ONE: CIRCLE the Type of Construction Project based on scope and expected activity (Type A-D)

TYPE

A

Inspection and Non-Invasive Activities. Includes, but is not limited to:

removal of ceiling tiles for visual inspection only, e.g., limited to 1 tile per 50 square feet painting (but not sanding) wallcovering, electrical trim work, minor plumbing, activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.

TYPE

B

Small scale, short duration activities which create minimal dust Includes, but is not limited to:

installation of telephone and computer cabling access to chase spaces cutting of walls or ceiling where dust migration can be controlled.

Project Specific: Replacement/installation of components that result in a loss of environmental control (HVAC)

TYPE

C

Work generates a moderate/high level of dust or requires demolition/removal of any fixed building components or assemblies Includes, but is not limited to:

sanding of walls for painting or wall covering removal of floorcoverings, ceiling tiles and casework; new wall construction minor duct work or electrical work above ceilings major cabling activities any activity which cannot be completed within a single work shift.

TYPE

D

Major demolition and construction projects Includes, but is not limited to:

activities which require consecutive work shifts requires heavy demolition, removal of a complete cabling system, or excavation new construction.

STEP TWO: CIRCLE the affected Patient Risk Groups. If more than one risk group will be affected, select the higher risk group.

Low Risk Medium Risk High Risk Highest Risk Office areas Kitchen storage area Public access, hallways, elevator Lobby

Non-clinical vacated, engineering space (sub-basement, mechanical rooms)

Cardiology Echocardiography Endoscopy Nuclear Medicine Physical Therapy Radiology/MRI Respiratory

Therapy Kitchen – food preparation area

Step Down Unit Emergency Room Laboratories (specimen) Medical Units Outpatient Surgery Pharmacy Post Anesthesia Care Unit Surgical Units Minor Procedure Rooms Sterile Supply storage/distribution

Immunocompromised patient care areas

Cardiac Cath Lab Sterile Processing Service Preparation Area Decontamination Area

Intensive Care Unit Negative pressure isolation rooms Oncology Operating rooms

STEP THREE: Using the IC Matrix CIRCLE the Class of Precautions as determined by Construction Type and Patient Risk

Construction Project Type Patient Risk Group TYPE A TYPE B TYPE C TYPE D

IC

M at ri x LOW Risk Group I II II III/IV

MEDIUM Risk Group I II III IV

HIGH Risk Group I II III/IV IV

HIGHEST Risk Group II III/IV III/IV IV

Preliminary ICRA Based on 35% Design Approved Final ICRA Approved

X Vickie L. Moore MA, CIC, VHA-CM Infection Prevention Program Manager

2/9/2022

X Vickie L. Moore Vickie L. Moore MA, CIC, VHA-CM Infection Prevention Program Manager Signed by: VICKIE L. MOORE 193380