This document outlines infection control precautions for a Class III water distribution upgrade project at the Overton Brooks VA Medical Center in Shreveport, Louisiana. The project, solicitation number 36C25622R0067, aims to upgrade the main hospital's water distribution system through a construction contract awarded by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16. The precautions specify protective measures to be implemented during construction such as maintaining negative air pressure and HEPA filtration within the work site, carefully removing barriers once work is complete, and scheduling a terminal cleaning. Exceptions to the precautions require approval on a case by case basis from Infection Prevention.

View the file

Other files

File Type Posted
36C25622R0067 0003.pdf PDF
RFIs 36C25622R0067 sheet 1 - OBVA Answered.docx DOCX document
RFIs 36C25622R0067 sheet 2 - OBVA Answered.docx DOCX document
36C25622R0067 0002.pdf PDF
S04 Construction Site Visit 667-18-119.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 2.pdf PDF
36C25622R0067 0001.pdf PDF
Water Distrib - Resubmission - Asbestos Dwgs.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 4.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 2.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 3.pdf PDF
Water Distrib - Resubmission - Plumbing As-Built Riser Diagram Dwgs.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 1.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 3.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 1.pdf PDF
Water Distribution ICRA FINAL.pdf PDF
Water Distrib - Resubmission - ICRA Dwgs 2.pdf PDF
WD - LA20220031 MOD 3 DATED 6-24-2022.txt TXT text file
36C25622R0067 EXHIBIT B R1.docx DOCX document
36C25622R0067 EXHIBIT E R1.docx DOCX document
Water Distrib - Resubmission - Civil Dwgs.pdf PDF
VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.docx DOCX document
36C25622R0067 EXHIBIT C R1.docx DOCX document
36C25622R0067 EXHIBIT D R1.docx DOCX document
Water Distrib - Resubmission - General Dwgs.pdf PDF
Water Distrib - Resubmission - Electrical Dwgs.pdf PDF
Water Distribution System Class I Precautions FINAL.pdf PDF
P09 Rev 7-1-22 667-18-111 Combinded Specifications.pdf PDF
P09 Construction REVISED SOW - 667-18-119.doc DOC document
36C25622R0067 EXHIBIT A R1.docx DOCX document
Water Distribution System Preliminary Class 11 FINAL.pdf PDF
Water Distrib - Resubmission - ICRA Dwgs 1.pdf PDF
Cross Connection Sheets.pdf PDF
36C25622R0067 EXHIBIT F R1.docx DOCX document
36C25622R0067 Solicitation.docx DOCX document
Dead Leg Criteria Checklist.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VAMC Infection Control Precautions for Class III Projects

Based on the Infection Control Risk Assessment of this construction/remodel project, the following activities are required.

Project: Upgrade Water Distribution System 667-18-119

During Construction Project: Upon Completion of Project:

C la ss

II

I

1. Seal unused doors with duct tape.

2. Block off and seal air vents if the HVAC system is removed or isolated.

3. Place dust mat at entrance and exit of work area

4. Remove or Isolate HVAC system in area where work is being done if required to prevent contamination of adjacent areas.

5. Complete all critical barriers i.e. sheetrock, plywood, plastic, to seal area from non-work area or implement control cube method (cart with plastic covering and sealed connection to work site with HEPA vacuum for vacuuming prior to exit) before construction begins.

6. Maintain negative air pressure within work site with filtration and pressure monitoring. Utilize HEPA equipped air filtration units if air is recirculated within the building.

7. Construction Waste

a. Transport in tightly covered container,

b. Containers without tight fitting solid lids must have covering taped in place BEFORE transport outside the project area,

c. Outside of containers must be cleaned when visibly soiled

8. When removing construction debris, utilize only the designated construction route.

9. Minimize construction worker traffic within the facility.

1. Wipe work surfaces with cleaner/disinfectant.

2. Handle construction waste the same as during construction.

3. Do not remove barriers from work area until completed project is inspected by Engineering Service, Infection Prevention and the area is thoroughly cleaned.

4. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.

5. Wet mop area with cleaner/disinfectant.

6. Upon completion, restore HVAC system where work was performed.

7. Schedule EMS Terminal Clean once all is complete.

Maintain control measures until ALL Work is completed. Exceptions must be approved by Infection Prevention on a case by case basis.

Lined items are deleted from these precautions due to the nature of the work being performed outdoors.

Preliminary Approved Based on 35% Design Final

2/9/2022

X Vickie L. Moore Vickie L. Moore MA, CIC, VHA-CM Infection Prevention Program Manager Signed by: VICKIE L. MOORE 193380

X Vickie L. Moore MA, CIC, VHA-CM Infection Prevention Program Manager