P09 Construction REVISED SOW - 667-18-119.doc

DOC document 56 KB Posted

Attached to
Z1DA--667-18-119, Upgrade Water Distribution System, Main Hospital
Solicitation number
36C25622R0067
Issued by

About this file

This document is a request for proposal (RFP) to upgrade the water distribution system at the main hospital of the Overton Brooks VA Medical Center in Shreveport, Louisiana. The contractor will be responsible for improving the existing domestic hot and cold water distribution systems to prevent healthcare-associated Legionnaires' disease and comply with the VHA Water Safety Program. Key work includes removing dead legs and asbestos insulation, insulating piping, complying with ICRA requirements, providing new water heaters and recirculation pumps, installing new backflow preventers, replacing check valves and balancing valves, integrating new sensors and monitoring equipment into the building management system, and providing training and service for one year. The contractor must complete all work within 365 days of the notice to proceed. The solicitation number for this opportunity is 36C25622R0067 and is being issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16.

View the file

Other files

File Type Posted
36C25622R0067 0003.pdf PDF
RFIs 36C25622R0067 sheet 1 - OBVA Answered.docx DOCX document
RFIs 36C25622R0067 sheet 2 - OBVA Answered.docx DOCX document
36C25622R0067 0002.pdf PDF
S04 Construction Site Visit 667-18-119.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 2.pdf PDF
36C25622R0067 0001.pdf PDF
Water Distrib - Resubmission - Asbestos Dwgs.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 4.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 2.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 3.pdf PDF
Water Distrib - Resubmission - Plumbing As-Built Riser Diagram Dwgs.pdf PDF
Water Distrib - Resubmission - Plumbing New Work Dwgs 1.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 3.pdf PDF
Water Distrib - Resubmission - Plumbing Dwgs 1.pdf PDF
Water Distribution ICRA FINAL.pdf PDF
Water Distrib - Resubmission - ICRA Dwgs 2.pdf PDF
WD - LA20220031 MOD 3 DATED 6-24-2022.txt TXT text file
36C25622R0067 EXHIBIT B R1.docx DOCX document
36C25622R0067 EXHIBIT E R1.docx DOCX document
Water Distrib - Resubmission - Civil Dwgs.pdf PDF
VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors.docx DOCX document
36C25622R0067 EXHIBIT C R1.docx DOCX document
36C25622R0067 EXHIBIT D R1.docx DOCX document
Water Distrib - Resubmission - General Dwgs.pdf PDF
Water Distrib - Resubmission - Electrical Dwgs.pdf PDF
Water Distribution System Class I Precautions FINAL.pdf PDF
P09 Rev 7-1-22 667-18-111 Combinded Specifications.pdf PDF
36C25622R0067 EXHIBIT A R1.docx DOCX document
Water Distribution Class III Precaution FINAL.pdf PDF
Water Distribution System Preliminary Class 11 FINAL.pdf PDF
Water Distrib - Resubmission - ICRA Dwgs 1.pdf PDF
Cross Connection Sheets.pdf PDF
36C25622R0067 EXHIBIT F R1.docx DOCX document
36C25622R0067 Solicitation.docx DOCX document
Dead Leg Criteria Checklist.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposal To Construct

UPGRADE WATER DISTRIBUTION SYSTEM, MAIN HOSPITAL

Overton Brooks VA Medical Center, Shreveport, LA

Project No. 667-18-119

SCOPE:

Overton Brooks VAMC (OBVAMC) seeks Contractor services to improve the existing domestic water distribution system [Hot Water (HW) and Cold Water (CW) for the Main Hospital, Water Storage Tanks and Cooling Towers to prevent Healthcare-Associated Legionnaire’s Disease (HCA-LD) and comply with the VHA Water Safety Program as described in the VHA Directive 1061.

As indicated in the contract documents, contractor shall provide all materials, labor, equipment, and supervision necessary to perform the following work per the specifications, drawings, and applicable code requirements to include the following:

· Remove dead legs, asbestos insulation, and cross connects as required

· Insulate piping per specifications

· Comply with ICRA requirements and complete work after hours as defined in project drawings

· Provide new double wall semi-instantaneous water heater, recirculating pumps, and piping

· Provide new dual assembly of the reduced pressure principle back flow preventer for domestic water system and new double check backflow preventer for the fire sprinkler system at a new location while rerouting piping between the storage tanks and main hospital per drawing phasing plan

· Provide new hot and cold-water supplies with stops and check valves on lavatories and sinks as identified

· Replace identified check balancing valves at the base of the hot water return risers and rebalance system

· Provide sensors for floor HW, CW, and HWR and pumps, integrate into building management system.

· Provide new water meter for the fire sprinkler system and domestic water system

· Provide new strap on temperature monitoring and interface into building management system

· Provide new water quality monitoring stations and supplemental disinfection system at various locations throughout the facility and integrate into the real-time monitoring platform to monitor water quality in the facility

· Provide new master mixing valve stations for the existing and new hot water generators

· Provide new ASSE approved point of use mixing valves for all existing fixtures that are not equipped

· Provide new appropriate back flow preventer to all cold-water supplies to identified machinery

· Provide VA personnel with one year service with all equipment installed as well as adequate training to maintain the system

PERIOD OF PERFORMANCE:

The Contractor shall complete the work 365 Days from the issuance of the Notice to Proceed.

CONTRACTOR SITE VISIT AND FIELD VERIFICATION PRIOR TO BIDDING:

Contractor shall be responsible for attending the Pre-Bid Site Visit prior to bidding to verify all existing conditions and take any necessary measurements required to adequately bid the project. If the Contractor chooses not to attend the Pre-Bid Site Visit, the Contractor may submit their bid at their own risk.

INFECTION CONTROL DURING CONSTRUCTION:

Contractor shall follow and comply with the established Infection Control Risk Assessment (ICRA) specific for the project. Contractor is responsible for dust control during demolition and during hauling operations.

DEMOLITION:

Contractor shall confirm the location, routing, and shut off of all utilities (water, gas, electrical, etc.) prior to any excavation/demo activities. Contractor shall protect all adjacent structures of the hospital, especially windows and doors, during all operations. Repairing any damage shall be the sole responsibility of the Contractor. If any damage is noticed prior to starting work which may be misconstrued as damage caused by the contractor, immediately notify the COR, and the damage shall be documented as existing conditions.

PHASING, NOISE, SMELLS, AND AFTER-HOURS WORK:

Work resulting in extensive noise or odor, shall be performed after hours or on weekends. Any required utility outages shall be scheduled at the convenience of the hospital, and potentially require after hours work or on weekends. The VA may need to perform additional existing site investigations and troubleshooting methods when isolating domestic cold, hot, and hot water return due to the level of complexity and age of the facility water distribution system. The contractor must account for the difficulty of isolating domestic water by providing a flexible schedule to accommodate alternate areas of work. Each area of work must account for separate plumbing risers and branches to allow appropriate timing and troubleshooting for the VA.

DELIVERIES:

Contractor shall coordinate material and equipment deliveries, storage, and handling requirements with COR.

FINAL CLEAN, PRE-FINAL & FINAL INSPECTIONS:

Once all work has been completed, the Contractor shall adequately clean the project site and request a Pre-Final Inspection. Upon completion of the Pre-Final punch list items, the Contractor shall request a Final Inspection. Each of these inspections will be scheduled at the convenience of the hospital.

SUBMITTALS:

Provide 2 hard copies & email an electronic copy (on a CD) to the COR and each copy shall have a completed VA transmittal sheet attached.

Contractor shall provide submittals as detailed in the specifications and samples of all finishes showing the full range of available colors and options to be selected by the VA-ID and COR.

SECURITY:

The C&A requirements do not apply, and that a Security Accreditation Package is not required.