Section 12000.pdf

PDF 28 KB Posted

Attached to
Alaska National Guard Multiple Award Task Order Contract Federal contract opportunity
Solicitation number
W91ZRU10R0004
Issued by
Department of the Army Alaska Army National Guard

About this file

Attachment 1 - Master Specs (10 of 13)

View the file

Other files for this federal contract opportunity

Other files attached to Alaska National Guard Multiple Award Task Order Contract, newest first.
File Type Posted
Award Matrix.pdf PDF
10-R-0004 Amendment 03.pdf PDF
A-13 MATOC EXHIBITS A-D F and G 1 July.pdf PDF
A-14 Questions and Answers.pdf PDF
A-13 MATOC EXHIBITS A-D F and G 21 Jun.pdf PDF
Attachment 5 Questions and Answers.pdf PDF
10-R-0004 Amendment 02.pdf PDF
Attachment 4 Attendee List updated 15 June 2010.pdf PDF
SECTION 05000.pdf PDF
10-R-0004-0001.pdf PDF
SECTION 08000.pdf PDF
Section 10100.pdf PDF
Section 06000.pdf PDF
Section 04000.pdf PDF
A-14 Preproposal minutes.pdf PDF
SECTION 02000.pdf PDF
SECTION 07000.pdf PDF
Section 03000.pdf PDF
A-14 Questions and Answers.pdf PDF
Presentation3.ppt PPT presentation
SECTION 14000.pdf PDF
SECTION 16000.pdf PDF
Section 09000.pdf PDF
SECTION 15000.pdf PDF
A-14 Attendee List.pdf PDF
sf330_Part2_e.pdf PDF
sf330_F_e.pdf PDF
SF330_Sec_E_e.pdf PDF
SF 330.pdf PDF
A-13 MATOC EXHIBITS A-D F and G Apr 10.doc DOC document
A-13 MATOC EXHIBIT E and E-1 Apr 10.doc DOC document
W91ZRU-10-R-0004 AK MATOC.pdf PDF
A-13 MATOC EXHIBITS A-G May 10.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FLOOR MATS AND FRAMES 12690 - 1

SECTION 12511 - HORIZONTAL LOUVER BLINDS

PART 1 - GENERAL

RELATED DOCUMENTS

Drawings and general provisions of Contract, including General and Division 1 Specification Sections, apply to this Section.

SUMMARY

This Section includes basic window treatment as follows:

Provide horizontal blinds.

SUBMITTALS

General: Submit the following in accordance with Conditions of Contract and Division 1 Specification Sections.

Product data and installation instructions for each type of window treatment unit required. Include methods of installation for each kind of opening and supporting structure.

Shop drawings showing location and extent of blinds and for special components and application conditions that are not fully dimensioned or detailed in manufacturer's product data. Show relationships to adjoining work.

Maintenance data to include in Operating and Maintenance Manual specified in Division 1.

Samples for initial selection of colors, in form of manufacturer's color charts consisting of sections of exposed components with integral or applied finishes showing full range of colors and materials.

Samples for Verification Purposes: One 12-inch-long slat for each color slat selected.

QUALITY ASSURANCE

General: Provide units produced by one manufacturer for each type required, with complete standard assemblies including hardware accessory items, mounting brackets, and fastenings.

Installer Qualifications: Engage an experienced Installer who has specialized in installing blinds similar to those required for this Project.

Furnish materials in colors and patterns as selected by Contracting Officer from manufacturer's full range of colors and patterns.

PROJECT CONDITIONS

FLOOR MATS AND FRAMES 12690 - 2

Field Measurements: Check openings by field measurements before fabrication. Show recorded measurements on shop drawings. Coordinate fabrication schedule with construction progress to avoid delay in the Work.

Coordinate wall and ceiling construction to ensure that actual opening dimensions correspond to guaranteed dimensions.

PART 2 - PRODUCTS

HORIZONTAL BLINDS

Headrail: Channel-shaped section approximately 1" high x 1-1/2" wide complete with tilting mechanism, top and end braces, top cradles, cord lock, and accessory items required for type of blind and installation.

Bottom Rail: Tubular steel bottom rail, designed to withstand twisting or sagging. Contour top surface to match slat curvature, with flat or slightly curved bottom. Close ends with metal or plastic end caps of same color as rail. Finish rail in same color as slats.

Slats: Spring-tempered aluminum (louver blades), rounded corners with forming burrs removed, as follows:

Slat Width: 1-inch (25 mm) nominal slats, 0.008" nominal thickness, with other components sized to suit.

Ladders: Designed to support and maintain slats at proper spacing and alignment in open and closed positions, as follows:

Braided polyester cord design consisting of vertical components of not less than 0.043-inch nor more than 0.068-inch in diameter and integrally braided ladder rungs of not less than 4 threads;

space ladders not further than 23 inches apart and 7 inches from ends of slats.

Tilting Mechanism: Assembly including disengaging worm and gear mechanism to eliminate overdrive, low-friction gear tilter, drum and cradle at each ladder, tilt rod, tape clips, and grommet guides to prevent wear on ladder and cords; designed to hold slats at any angle and prevent movement of slats due to vibration, operated as follows:

Wand Operator: Detachable clear plastic wand, of proper length to suit blind installation, detachable without tools by raising locking sleeve.

Lifting Mechanism: Crashproof cord locks with cord separators and braided polyester or nylon lift cords.

Size cord to suit blind type. Include self-aligning cord equalizers designed to maintain horizontal blind position.

Installation Brackets: Designed to facilitate removal of head channels. Provide intermediate brackets at spacing recommended by blind manufacturer. Include hardware necessary for secure attachment of

FLOOR MATS AND FRAMES 12690 - 3

brackets to adjoining construction and to headrails. Design brackets to support safely the weight of blind assemblies plus forces applied to operate blinds.

Finish: Provide finishes indicated below. Finish exposed accessories and hardware to match rail color.

Provide corrosion-resistant finish to concealed items of hardware.

Steel Components: Galvanize and either phosphate coat or prime exposed steel surfaces. Finish with baked-on synthetic resin enamel finish.

Aluminum Slats: Chemical conversion coat followed with baked-on synthetic resin enamel finish coat.

Manufacturers: Subject to compliance with requirements, provide products of one of the following:

Bali Graber Contract, "Bali Classics Mini Blinds".

Hunter Douglas, Inc., "Contract Sunflex 1", Aluminum Blinds.

Architectural Products Div., Levelor Lorentzen, Inc., "Riviera 1" Blind.

FABRICATION AND OPERATION

Prior to fabrication, verify actual opening dimensions by accurate site measurements. Adjust dimensions for proper fit at openings.

Coordinate with other trades for securing tracks to substrates and other finished surfaces.

Fabricate window treatment components from non-corrosive, non-staining, non-fading materials that are completely compatible and do not require lubrication during normal expected life.

Fabricate blind units to fill openings from head to horizontal mullion and jamb to jamb.

Space slats to provide overlap for light exclusion when fully closed.

Equip horizontal blind units for the following operation:

Full-tilting operation with slats rotating approximately 180 degrees. Place tilt operating controls on left hand side of blind units unless otherwise directed.

Full-height raising, to minimum stacking dimension, with lifting cord locks for stopping blind at any point of ascending or descending travel. Place pull cords on right-hand side of blind units unless otherwise indicated.

PART 3 - EXECUTION

EXAMINATION

FLOOR MATS AND FRAMES 12690 - 4

Examine openings where horizontal louver blinds will be installed prior to beginning installation. Verify that critical dimensions are correct and surface conditions acceptable.

Complete all finishing operations, including painting, before beginning installation.

Do not proceed with installation until unsatisfactory conditions have been corrected.

INSTALLATION

General: Install window treatment units to comply with manufacturer's instructions. Position units level, plumb, secure, and at proper height and location relative to adjoining window units and other related work.

Securely anchor units with clips, brackets, and anchorages suited to type of substrate.

Provide clearance between sash and blinds to permit unencumbered operation of sash hardware.

CLEANING AND PROTECTION

After completing the installation, clean blind surfaces according to the manufacturer's instructions.

Protect installed units to ensure their being in operating condition, without damage, blemishes, or indication of use at substantial completion of project. Correct nonconforming damaged units. Replace units that cannot be field corrected.

END OF SECTION 12511

SECTION 12690 - FLOOR MATS AND FRAMES

PART 1 - GENERAL

RELATED DOCUMENTS

Drawings and general provisions of Contract, including General and Division 1 Specification Sections, apply to Work of this Section.

DESCRIPTION OF WORK

This Section includes:

Recessed Floor Mats:

Roll-Up, Linked-Tread-Type Floor Mats

Related Sections: The following sections contain requirements that relate to this section:

Division 3 sections for concrete work, including forming, placing, and finishing concrete floor

FLOOR MATS AND FRAMES 12690 - 5

slabs and grouting frames into recess.

SUBMITTALS

Product data for floor mat and frame specified, including manufacturer's specifications and installation instructions, details of construction relative to materials, dimensions of individual components, profiles, and finishes.

Samples for initial selection purposes in form of manufacturer's color charts consisting of actual sections of floor mat and frame materials, showing full range of colors, textures, finishes, and patterns available.

Samples for verification purposes in form of 12-inch-square assembled section of floor mat and frame members with selected tread surface showing each type of metal finish and color of exposed floor mat, frames, and accessories required. Where finishes involve normal color and texture variations, include sample sets showing full range of variations expected.

Maintenance data in form of manufacturer's printed instructions for cleaning and maintaining floor mats.

PROJECT CONDITIONS

Field Measurements: Check actual blocked-out openings in floors by accurate field measurements before fabrication of frames and mats. Coordinate fabrication schedule with construction progress to avoid delay of Work.

Where field measurements cannot be made without delaying the Work, guarantee opening dimensions and proceed with fabrication without field measurements. Coordinate floor construction to ensure that actual opening dimensions correspond to guaranteed dimensions.

QUALITY ASSURANCE

Single-Source Responsibility: Obtain floor mats and frames from one source from a single manufacturer.

SEQUENCING AND SCHEDULING

Provide oversized recesses in concrete work to receive frames. Defer frame installations until building enclosure is completed and related interior finish work is in progress.

PART 2 - PRODUCTS

ACCEPTABLE MANUFACTURERS

Manufacturers: Subject to compliance with requirements, provide products of the following:

Balco, Inc., Type FMA-R.

Construction Specialties, Inc., Model PM425RM "Pedimat".

FLOOR MATS AND FRAMES 12690 - 6

MATERIALS

General: Provide colors, patterns, and profiles of materials, including metals and metal finishes, as indicated on drawings or by this specification or as selected by Contracting Officer from manufacturer's full range of colors, patterns, and profiles.

Recessed Mat Frames: Provide manufacturer's standard design, of size and style to fit floor mat type for permanent recessed installation in floor, complete with corner pins or reinforcing and installation anchorages.

Provide frames of extruded aluminum, ASTM B 221, alloy 6063-T5. Coat surface of frame that will contact cementitious material with zinc chromate paint or manufacturer's standard protective coating.

Aluminum Finish: Dark bronze anodized finish or as selected by the Contracting Officer.

Provide frame members in single lengths.

Roll-Up-Type Vinyl Tread Floor Mats: Provide manufacturer's standard vinyl-acrylic hinged tread-slat mat system, with slotted or perforated hinges to form 2 inch-wide by 3/8-inch-thick slat modules, with top-surface tread inserts and vinyl edge accessories to accommodate frame application as indicated.

Provide type of tread inserts as specified below.

Tread Surface: Abrasive fill or insert of aluminum oxide or silicon carbide grit in epoxy matrix.

Color: As selected by Contracting Officer from manufacturer's full range of colors.

FABRICATION

Shop fabricate units of floor mat work to greatest extent possible in sizes as indicated. Where not otherwise indicated, provide single unit for each mat installation, but do not exceed manufacturer's maximum size recommendation for units intended for removal and cleaning. Where joints in mats are necessary, space symmetrically and away from normal traffic lanes. Miter corner joints in framing elements with hairline joints or provide prefabricated corner units without joints. Where possible, verify sizes by field measurement before shop fabrication.

PART 3 - EXECUTION

INSTALLATION

Install recessed frames and mats to comply with manufacturer's instructions, at locations indicated and with top of frames and mats in proper relationship to one another and to adjoining finished flooring. Set mat tops at height recommended by manufacturer for most effective cleaning action; coordinate top of mat surfaces with doors that swing across mats to provide under door clearance.

Where frame is embedded in grout, provide necessary shims, spacers, and anchorages for proper

FLOOR MATS AND FRAMES 12690 - 7

location and secure attachment.

PROTECTION

Upon completion of frame installations and concrete work, provide temporary filler of plywood or fiberboard in recesses, and cover frames with plywood protective flooring. Maintain protection until construction traffic has ended and project is near time of Substantial Completion.

Defer installation of floor mats until near time of Substantial Completion for project.

END OF SECTION 12690