A-13 MATOC EXHIBIT E and E-1 Apr 10.doc
DOC document 37 KB Posted
- Attached to
- Alaska National Guard Multiple Award Task Order Contract Federal contract opportunity
- Solicitation number
- W91ZRU10R0004
About this file
word document for easier manipulation of forms
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AK-NG MATOC
RFP W91ZRU-10-R-0004
EXHIBIT E PROTOTYPICAL PROJECT
NOTICE OF PROPOSED PROJECT, PROPOSAL FORM
Date: 24 May 2010 PROJECT TITLE AND NO.: Building Reroof, Project # 0001 PROJECT DESCRIPTION: Reroof existing building. This project is only for the purpose of evaluating price. This project will NOT be awarded.
MAGNITUDE OF PROJECT: $500,000 - $1,000,000
PERFORMANCE PERIOD: 120 Days after receipt of Notice to Proceed
SITE VISIT: No site visit will be performed. All drawings will be provided at the proposal conference. (See Section 00100, paragraph 1.5.1.)
QUESTIONS AND ANSWERS: A list of questions and answers can be found at Attachment 1. No other questions will be taken.
PERFORMANCE & PAYMENT BONDS: In accordance with FAR 28.102-1 and Contract Clause 52.228-15, Contractors are reminded that any amount awarded over $30,000 shall require Payment Bonds, and awards exceeding $100,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 days after award.
LIQUIDATED DAMAGES: (X) YES or ( ) NO- reference Contract Clause 52.211-12.
CONSTRUCTION: (X ) YES or ( ) NO- reference Contract Clause 52.246-21, Warranty of Construction, is applicable to this task order.
WAGE DETERMINATION: Currently, General Decision AK20100001, Modification No. 4 dated 05/07/2010 is applicable to this task order. However, the current prevailing Wage Determination will be incorporated at time of award.
PROJECT SAFETY: In accordance with FAR 52.236-13, Accident Prevention, construction contractors are required to use the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. To view this manual click here http://www.usace.army.mil/inet/usace-docs/eng-manuals/em385-1-1/toc.htm PROPOSAL DUE DATE: All offers are due with proposal for MATOC basic contract. Failure to provide a price will make offer noncompliant, eliminated from the competition and offeror ineligible for a basic contract award. Basis for award is in the RFP.
Item
Number
Description
Lump Sum Amount
Reroof existing building
SIGNATURE:
COMPANY NAME
Name and title of person authorized to sign Offer Date
EXHIBIT E – 1 - CALCULATION OF PERFORMED WORK
IAW FAR 52.219-14, Limitations on Subcontracting
Identify what parts of the project will be "self-performed" by in-house forces and the related cost for each part, as defined below. Provide and illustrate the calculation for "percent of self-performed work", in accordance with the definitions below.
Definitions regarding self-performance of work by the Prime Contractor, in accordance with Contract Clause: "Limitations on Subcontracting" (FAR 52.219-14):
The work in this contract is “general construction” for purposes of Contract Clause "Limitations on Subcontracting."
"Self-performed work" generally includes costs for: mobilization and utilization of owned or rented plant and equipment to be operated by the contractor's own employees and labor associated with the aforementioned equipment; contractor's own labor to fabricate or to install materials into the finished construction; performance by the contractor's own employees of design work, land surveys and other engineering or technical specialist services required by the contract; supplies to directly support the aforementioned work to be accomplished by the contractor's own employees; and the contractor's own job overhead costs. Contractor markups for profit, general and administrative overhead, bonds, or other indirect costs on "self-performed" or subcontracted work are not "self-performed work" and are to be excluded from "total cost of the contract" for calculation purposes. Rental of plant or equipment for operation by subcontractors is not "self-performed work" but shall be included in the "total cost of the contract" for calculation purposes. Cost of materials to be incorporated into the work and supplies to support other than construction by the contractor's own employees are excluded from the above definition. Do not include these costs in the calculation.
"Total cost of the contract" means the total direct (variable, fixed, one-time and semi-variable) costs to the contractor, including jobsite overhead costs but excluding the cost of any materials to be incorporated into the work, to construct the project. It generally includes the cost of all self-performed work, as defined above, and all supplies and subcontract costs. The cost of subcontractor furnished materials will be excluded only to the extent that they can be segregated and identified in the subcontractors' proposals.
"Percent of self-performed work" is calculated by dividing the above defined cost of "self-performed work" by the "total cost of the contract" and multiplying the result by 100%.”
FORMAT FOR CALCULATION OF SELF-PERFORMED WORK
(For SET ASIDE Contract, only)
SUBMITTED IN RESPONSE TO W91ZRU-10-R-0004
Use a format similar to the following to identify and calculate cost of the work to be self-performed. Refer to the definitions above pertaining to "Self-performance of work", "Cost of the Contract" and "Percent of Self-Performed Work".
A. Clearly describe the work to be self-performed:
B. Show Calculation of Self-Performed Work:
B.1 Total Proposed Price: $_______________
B.2 Subtract all G&A, home office overhead, prime ($______________) contractor's markups for profit, bond, state use tax, etc. on self- performed and subcontracted work
B.4 Subtract identifiable cost of materials to be incorporated ($______________) into the work
B.5 Remainder is "Total Cost of the Contract" = $______________
B.6 "Work to be self-performed": = $______________ (only cost for mobilization and utilization of owned or rented plant and equipment to be operated by the contractor's own employees, labor for equipment operated by contractor's own employees; contractor's own labor to fabricate or to install materials into the finished construction; (NON Design/Build Only: performance by the contractor's own employees of design work, land surveys and other engineering or technical specialist services required by the contract); supplies to directly support the aforementioned work to be accomplished by the contractor's own employees; and the contractor's own job overhead costs. NO MATERIALS!
B.7 % Self-performed Work = Line B.6/ Line B.5 X 100% = ______________%
File details come from the government source that posted it. Updated .