ACA shelter amendment 04
View the file
Other files for this federal contract opportunity
Show all 41
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F9F3CE8165AW01 WYTD079031
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this Amendment 04 is to answ er the final Q&A for ACA shelter project solicitation. updated TOC, one Spec and 2 draw ing sets.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Nov-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9136419B8001
X 9B. DATED (SEE ITEM 11)
23-Oct-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Nov-2018
CODE
180 FW CONTRACTING OFFICE
2660 S EBER ROAD
SWANTON OH 43558-8752
W91364 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9136419B8001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
Q&A SET 4
AMENDMENT/ADDENDUM 04
W91364-19-B-8001 FOR ACA Shelter
AT 180TH FIGHTER WING
REMINDER: the Bid opening date has BEEN extended in Block 13 of the SF1442.
The new Bid Opening date is now 10 December 2018 at 200PM EST.
Q135: Drawing ES104 keynote 1 and keynote 4 indicate that we are to extend conduits into Building 600.
Are there currently conduits stubbed out of Building 600 for tie in? If not, please provide more information as to how are to connect to Building 600.
A135: A&E Response: There are two existing 4” conduits that extend from existing building 600 comm room to HH16 and that stub out on the north side of the fence line for the new comm conduits to the shelter. New conduit to be installed shall connect in this location. The circuit homerun to be installed for the convenience receptacle on the utility rack will need to be coordinated with the Base prior to installation.
Q136: Drawing EP101 and EP102, General Note 4 on both pages should read the same and they do not.
EP101 Note 4 reads that all of the receptacles should be GFCI and WEATHERPROOF.
EP102 Note 4 reads that all of the receptacles should be EXPLOSION PROOF.
Which note is correct?
A136: A&E Response: See response on amendment 03, Question 117. All receptacles in these areas shall be weatherproof and GFCI
Q137: Drawing EP101 and EP102, electrical panels LP2 and LP3 and not listed as weather proof or explosion proof. Should they be?
A137: A&E Response: Panelboards LP2 and LP3 shall be installed in NEMA 3R enclosures.
Q138: Please provide specification for 12.47kV Sectionalizing Cabinet that is referenced on drawing ES106 Key Note #1.
A138: A&E Response: Sectionalizing cabinet is referenced in specification 33 71 02, section 2.5.7 ‘Junction Cabinets’
Q139: Please define what the circular items are on drawing CS102 represents.
A139: A&E Response: Electrical Lighting. Coordinate with the Electrical Drawings.
Q140: Section 076114 Paragraph 3.3.1 references providing roofing panels in longest practical lengths from ridge to eave...with no transverse joints except at the junction of ventilators, curbs, skylights, chimneys, and similar openings. Elsewhere in the specification, there is reference to panel end laps.
Given the low slope application and long roof to eave runs, a continuous length panel 160’-0” long is highly recommended and is standard with high performance standing seam roof systems. Otherwise, there will be approximately 568+ panel end laps having 5,000+ exposed fasteners penetrating the roof panels. The roof plan does not indicate end laps. End laps are unsightly, prone to leak, and if not installed properly may be excluded from a manufacturer’s warranty. BEMO USA recommends revising the specification to require full length panels from ridge to eave as is standard in the industry for the intended building type and performance requirement.
A140: A&E Response:
a. Requirements for the standing seam metal roof are addressed in specification section 13 34 19 METAL BUILDING SYSTEMS. Specification section 07 61 14.00 20 STEEL STANDING SEAM ROOFING shall be deleted in its entirety.
b. As long as the roof system meets the performance requirements listed in section 13 34 19 METAL BUILDING SYSTEMS, the seam locations may be determined by the metal building supplier.
Q141: Per Demolition and Civil drawings, is the existing concrete that is to be demolished and removed reinforced? If so, what method is it reinforced with (Wire Mesh, Reinforcing steel etc)?
A141: BASE Response: The concrete to be demolished is reinforced as follows. The joints are doweled with 1-1/2” dowels spaced at 15” on center or are tied with #5 bars, 30” long spaced at 30” on center.
Irregularly shaped sections are reinforced with WWF 6x6 – W4xW4.
Q142: Is there an ODOT equivalent gradation to the crushed aggregate base course shown in the specifications.
A142: A&E Response: The aggregate base course gradations were put together and compared to local ODOT gradations during design.
Q143: For off-site removal of broken concrete and excavated spoils, drawings state the material must be disposed of at a government approved waste disposal site. Is this correct? And if so, can a listing of approved disposal facilities be provided?
A143: Base Response: NO, any appropriate disposal site is ok.
Q144: Drawing CU-100 shows the connection of the proposed Fireline at N: 702317.36 / E: 1613944.82.
The Fireline connection appears to cross over and run very close parallel to the existing security fence, with the actual Point of Connection appearing to underlap with the fence. Will the base remove or relocate this fence if required for the Hydrant scope of work? If the GC is to remove and relocate this fence is a there an allowance you would like us to carry.
A144: Base Response: The waterline connection will be made on the west side of the fence. The connection point can be adjusted as needed to avoid crossing below the fence if required (i.e. 2 -45s & thrust blocks). The contractor shall take all necessary precautions to maintain the integrity of the boundary fence and high security fence during construction. Fencing disturbed or damaged during construction shall be restored by the contractor to its pre-construction condition at no additional cost to the government.
Q145: What is the depth if the existing concrete to be demolished and removed? Is there asphalt underneath the Concrete? If so what is the depth of the asphalt?
A145: A&E Response: The existing concrete is 11 inches thick. There is no asphalt underneath, only a rock layer.
Q146: Please confirm that in accordance with the “Captivation Requirements” as noted on multiple drawings that this requirement applies to any and all trades which would have fasteners or other mechanical connections on the project?
A146: A&E Response: Correct- these requirements apply to all trades.
Q147: Sheets ES106 and ES104 indicate PVC conduit underground for 15KV primary feeds, however, specification section 26 20 00, paragraph 3.1.5.7 indicates rigid metal conduit only for circuits greater than 600V. Please clarify.
A147: A&E Response: All ducts that shall be concrete encased shall utilize PVC conduit, per specification 33 71 02.
Q148: Sheet EP102, General Note #4, indicates all 20A 120V receptacles are to be explosion proof.
EP101, General Note #4 indicates 20A 120V receptacles are to be weatherproof and GFCI. Please clarify.
A148: A&E Response: See response on amendment 03, Question 117. All receptacles in these areas shall be weatherproof and GFCI
Q149: Regarding captivation requirements, please clarify the intent of the requirement to apply to pre-manufactured goods (Light fixtures, HVAC units, etc) brought to the site, unboxed, and installed as is.
A149: A&E Response: The captivation requirement applies to the installation of these premanufactured goods. The use of GE silicone RTV 108 shall be used, as indicated in captivation notes on all applicable sheets, as an extra step in captivation for mounting and securing said goods due to the vibrating forces that will occur in this facility.
Q150: Is there a location onsite either at the 180th or at Toledo Express in which the materials from the taxiway demolition or spoils can be disposed of?
A150: BASE Response: NO location at the 180th. Materials that are not to be reused will be removed off site and disposed of properly by the contractor.
Q151: Sheet EP601 shows 2- 4" conduits going to the fire pump controller sheet EP 101 shows 3 conduits coming up at the fire pump controller.
A151: A&E Response: The configuration on sheet EP601 is correct. Conduits shown on sheet EP101 shall be modified in amendment 04.
Q152: Feeder for panel PL1 should have 4 #6.
A152: A&E Response: Correct. Feeders shall be 4-#6 AWG, 1-#10 AWG GND in 1” conduit.
Q153: Breaker in MSB for PP1 shows 100 amps but panel schedule shows 225 amps.
A153: A&E Response: PP1 shall be rated at 225A. One-line breaker size shall be modified in amendment 04.
Q154: We are unable to find the appendix for the existing IDS and CCTV drawings.
A154: A&E Response: See amendment 03 drawing T-002.
Q155: Sheet ES104 shows 3" conduit for easy button, what type of conductors are needed in the conduit?
A155: A&E Response: The ‘easy button’ controller provides remote control for the opening of the shelter doors. There will be 50 low voltage conductors that will run in 3” conduit from Building 600 to the controllers in the shelter.
Q156: What size conduits are needed to tie in sector 6,7 and 8 on sheet ES 104?
A156: A&E Response: IDS pathways are believed to be direct buried cables but will need to be verified by manufacturer prior to installation.
Q157: ES 104 show (2) 5" conduits for primary power from sectionalizer to EHH 10. Sheet ES 106 shows
(1) 4" conduit at the other end of the run. Sheet ES401 also shows (1) 4"
A157: A&E Response: Primary power between cabinet and EHH10 shall be in 5” conduit. One conduit shall be for primary conductor routing, and the other shall be spare. Conduit extending to transformer shall be (1) 5” conduit. As indicated, conduit sizes shall be corrected in amendment 04.
Q158: Will the (2) 5" conduits for future expansion and or the 4" comm conduit for future expansion require installation in a duct bank?
A158: A&E Response: Yes. See answer for concrete encasement with amendment 03.
Q159: Please advise the amperage and configuration on the Arktite receptacle shown on sheet ES401.
A159: A&E Response: Receptacle shall be rated for 200A, 600VAC, 4 wire/4 pole NEMA 3R. Information will be included on sheet EP601 in amendment 04.
Q160: TN 101 refers to sheet E-004 I do not have that sheet available.
A160: A&E Response: Reference E-004 should be T-002. Change will be included in amendment 04.
Q161: TN 401 and TN 501 show a 200 pair CAT 6 and a fiber service cable, where do these cables originate and how many fibers are required.
A161: A&E Response: A Hybrid 12-strand single mode / 24-strand 62.5 multimode fiber optic and 200 pair copper cabling will be extended to the comm room within the shelter from the communication room in building 600.
Q162: On ES 105 keyed note 3, are the FDB-4 conduits in addition to the (2) 5" and (1) 4" shown?
A162: A&E Response: No. Conduit pathways for FDB-4 relocation are included in the 5” and 4” electrical and comm conduit installation shown.
Q163: Amendment 3 clarified the pavement section for the concrete pavement. What is the pavement section for the asphalt pavement to be demoed?
A163: Base Response: The pavement section for the asphalt shoulder profile is: 2” of ODOT 448 surface course, 4” of ODOT 301 bituminous base, 6” of base course, 4” limestone screenings, and compacted subgrade.
Q164: There are references and details for Stoops but I don’t see any on the drawings. Please verify that there are no stoops required.
A164: A&E Response: The references and details for stoops will be removed since they are not a part of this design.
Q165: Reference to specification section 321314.13; sub section 1.3.6.1 (Test Section) and Q/A no. 92 with regards to pilot lane and fill in lane please clarify the following:
a- Is the pilot lane required?
b- If the pilot lane is required, please provide location (where are we constructing this lane) and exact dimensions. Specification 321314.13 subsection 1.3.6.1 calls for 400’ lane.
c- Do we need to remove the pilot lane after testing.
d- Is the fill in lane required?
e- If the fill in lane is required, per specification section 321314.13, subsection 1.3.6.2, states “consider the first 400 feet of initial production fill in lane as a fill – in lane test section” there is no 400’ of straight pavement section in this project, please clarify what section measurement is acceptable?
and confirm if the permeant pavement first pour could be considered fill-in lane test section?
A165: A&E Response:
a. Pilot lane is required.
b. Will be a part of the production of the paving operations and must meet project specification requirements.. Adjusted to 200-feet minimum length.
c. Pilot lane will be removed if it does not meet the specification requirements at the Contractor’s expense.
d. Yes
e. Revised to be 200-feet minimum length. Can be a part of the production of the paving operations and must meet project specification requirements.
Q166- Is there metal deck under the standing seam metal roof or there are only purlins. Amendments still call for roofing on metal deck.
A166: A&E Response: There is no metal deck under the standing seam metal roofing.
29 November 2018
DRAWINGS REMARKS
EP101 Modified conduits shown stubbed up under fire pump controller.
EP601 PL1 feeder size modified, PP1 breaker size on one-line shown as 225A, Primary conduit size to transformer modified, Arktite receptacle configuration identified.
ES106 Primary power feed: (2) 5” conduits.
ES401 Conduit size modified for feed to transformer from EHH10.
S-005 Deleted the exterior stoop detail
SPECIFICATIONS REMARKS
Project TOC Revised to show removal of Section 07 61 14.00 20
07 61 14.00 20 This specification section is removed in its entirety.
32 13 14.13 Spec sections 1.3.6, 1.3.6.1 and 1.3.6.2 have been revised.
(End of Summary of Changes)