271100 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS.DOC

DOC document 37 KB Posted

Attached to
Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC)
Solicitation number
W91364-12-R-0005
Issued by

About this file

271100

View the file

Other files

File Type Posted
amendment three OHIO MATOC 2012.pdf PDF
amendment two OHIO MATOC 2012.pdf PDF
334600 - SUBDRAINAGE.DOC DOC document
330500 - COMMON WORK RESULTS FOR UTILITIES.DOC DOC document
site visit information.pdf PDF
proposal questions and answers MATOC.pdf PDF
amendment one OHIO MATOC 2012.pdf PDF
311000 - SITE CLEARING.DOC DOC document
Ohio MATOC Division 1-2012.pdf PDF
334100 - STORM UTILITY DRAINAGE PIPING.DOC DOC document
329200 - TURF AND GRASSES.DOC DOC document
312000 - EARTH MOVING.DOC DOC document
283111 - DIGITAL ADDRESSABLE FIRE-ALARM SYSTEM.DOC DOC document
315000 - EXCAVATION SUPPORT AND PROTECTION.DOC DOC document
12-R-0005-0001.pdf PDF
323113 - CHAIN LINK FENCES AND GATES.DOC DOC document
321373 - CONCRETE PAVING JOINT SEALANTS.DOC DOC document
412213 BRIDGE CRANES.doc DOC document
321313 - CONCRETE PAVING.DOC DOC document
Table of Contents.doc DOC document
12-R-0005.doc DOC document
MATOC-EXHIBIT-E-14FEB12.docx DOCX document
T002.pdf PDF
S-102.PDF PDF
S-101.PDF PDF
235216 SF - CONDENSING BOILERS.DOC DOC document
271500 - COMMUNICATIONS HORIZONTAL CABLING.DOC DOC document
Spill Procedure.doc DOC document
260533 - RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS.DOC DOC document
014000 - QUALITY REQUIREMENTS.DOC DOC document
088000 - GLAZING.DOC DOC document
C-101.PDF PDF
235100 SF - BREECHINGS CHIMNEYS AND STACKS.DOC DOC document
221116 SF - DOMESTIC WATER PIPING.DOC DOC document
UTES Material Submittal.xls XLS spreadsheet
221513 SF - GENERAL-SERVICE COMPRESSED-AIR PIPING.DOC DOC document
221113 - FACILITY WATER DISTRIBUTION PIPING.DOC DOC document
017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL.DOC DOC document
033000 - CAST IN PLACE CONCRETE.doc DOC document
071800 - TRAFFIC COATINGS.DOC DOC document
A302.pdf PDF
233113 FL - METAL DUCTS.DOC DOC document
017700 - CLOSEOUT PROCEDURES.DOC DOC document
A600.pdf PDF
223400 SF - FUEL-FIRED DOMESTIC-WATER HEATERS.DOC DOC document
230529 SF - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT.DOC DOC document
220719 SF - PLUMBING PIPING INSULATION.DOC DOC document
E-102.pdf PDF
A201.pdf PDF
A303.pdf PDF
Show 40 more

Latest 50 of 168 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT TRAINING EQUIPMENT SITE ADD/ALT

SECTION 271100 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Telecommunications mounting elements.

2. Telecommunications equipment racks and cabinets.

3. Grounding.

B. All drawings and specifications apply to work in this section. Furnish all items, articles, materials, equipment, operations or methods that are mentioned, listed or scheduled on drawings or are in this specification including all labor, equipment materials and miscellaneous incidentals necessary and/or required for the completion of this project. The work covered under this section of the specification is in no way complete within itself but is supplementary to the entire specification and drawings.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: For communications equipment room fittings. Include plans, elevations, sections, details, and attachments to other work.

1. Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection.

2. Grounding: Indicate location of grounding bus bar and its mounting detail showing standoff insulators and wall mounting brackets.

1.3 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer, qualified layout technician, installation supervisor, and field inspector.

B. Seismic Qualification Certificates: For equipment frames from manufacturer.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: Cabling Installer must have personnel certified by BICSI on staff.

1. Layout Responsibility: Preparation of Shop Drawings shall be under the direct supervision of RCDD.

2. Installation Supervision: Installation shall be under the direct supervision of Level 2 Installer, who shall be present at all times when Work of this Section is performed at Project site.

3. Field Inspector: Currently registered by BICSI as RCDD to perform the on-site inspection.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Seismic Performance: Equipment frames shall withstand the effects of earthquake motions determined according to ASCE/SEI 7

1. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified and the unit will be fully operational after the seismic event."

2.2 GROUNDING

A. Comply with requirements in Section 260526 "Grounding and Bonding for Electrical Systems" for grounding conductors and connectors.

B. Telecommunications Main Bus Bar:

1. Connectors: Mechanical type, cast silicon bronze, solderless compression type wire terminals, and long-barrel, two-bolt connection to ground bus bar.

2. Ground Bus Bar: Copper, minimum 1/4 inch thick by 4 inches wide with 9/32-inch holes spaced 1-1/8 inches apart.

3. Stand-Off Insulators: Comply with UL 891 for use in switchboards, 600 V. Lexan or PVC, impulse tested at 5000 V.

C. Comply with J-STD-607-A.

2.3 LABELING

A. Comply with TIA/EIA-606-A and UL 969 for a system of labeling materials, including label stocks, laminating adhesives, and inks used by label printers.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Comply with NECA 1.

B. Comply with BICSI TDMM for layout and installation of communications equipment rooms.

C. Bundle, lace, and train conductors and cables to terminal points without exceeding manufacturer's limitations on bending radii. Install lacing bars and distribution spools.

D. Coordinate layout and installation of communications equipment with Owner's telecommunications and LAN equipment and service suppliers. Coordinate service entrance arrangement with local exchange carrier.

1. Record agreements reached in meetings and distribute them to other participants.

2. Adjust arrangements and locations of distribution frames, cross-connects, and patch panels in equipment rooms to accommodate and optimize arrangement and space requirements of telephone switch and LAN equipment.

E. Coordinate location of power raceways and receptacles with locations of communications equipment requiring electrical power to operate.

3.2 FIRESTOPPING

A. Comply with requirements in Section 078413 "Penetration Firestopping."

B. Comply with TIA-569-B, Annex A, "Firestopping."

C. Comply with BICSI TDMM, "Firestopping Systems" Article.

3.3 GROUNDING

A. Install grounding according to BICSI TDMM, "Grounding, Bonding, and Electrical Protection" Chapter.

B. Comply with J-STD-607-A.

C. Locate grounding bus bar to minimize the length of bonding conductors. Fasten to wall allowing at least 2-inch clearance behind the grounding bus bar. Connect grounding bus bar with a minimum No. 4 AWG grounding electrode conductor from grounding bus bar to suitable electrical building ground.

D. Bond metallic equipment to the grounding bus bar, using not smaller than No. 6 AWG equipment grounding conductor.

3.4 IDENTIFICATION

A. Identify system components, wiring, and cabling complying with TIA/EIA-606-A. Comply with requirements in Division 26 Section "Identification for Electrical Systems."

B. Comply with requirements in Division 09 Section "Interior Painting" for painting backboards. For fire-resistant plywood, do not paint over manufacturer's label.

END OF SECTION 271100

Project No: 390265 COMMUNICATIONS EQUIPMENT ROOM FITTINGS
271100 - 3