SECTION 321373

View the file

Other files for this federal contract opportunity

Other files attached to Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC), newest first.
File Type Posted
amendment three OHIO MATOC 2012.pdf PDF
amendment two OHIO MATOC 2012.pdf PDF
323113 - CHAIN LINK FENCES AND GATES.DOC DOC document
412213 BRIDGE CRANES.doc DOC document
321313 - CONCRETE PAVING.DOC DOC document
330500 - COMMON WORK RESULTS FOR UTILITIES.DOC DOC document
311000 - SITE CLEARING.DOC DOC document
amendment one OHIO MATOC 2012.pdf PDF
262416 - PANELBOARDS.DOC DOC document
262913 - ENCLOSED CONTROLLERS.DOC DOC document
220500_FL - COMMON WORK RESULTS FOR PLUMBING.DOC DOC document
018100 - GENERAL COMMISSIONING REQUIREMENTS.DOC DOC document
E-108.pdf PDF
099113 - EXTERIOR PAINTING.DOC DOC document
081113 - HOLLOW METAL DOORS AND FRAMES.DOC DOC document
260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.DOC DOC document
230513 SF - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT.DOC DOC document
260923 - LIGHTING CONTROL DEVICES.DOC DOC document
017823 - OPERATION AND MAINTENANCE DATA.DOC DOC document
230593 SF - TESTING ADJUSTING AND BALANCING FOR HVAC.DOC DOC document
079200 - JOINT SEALANTS.DOC DOC document
E-104.pdf PDF
018150 - COMMISSIONING OF HVAC.DOC DOC document
S-100.PDF PDF
M-100.PDF PDF
A301.pdf PDF
221113 - FACILITY WATER DISTRIBUTION PIPING.DOC DOC document
A600.pdf PDF
017700 - CLOSEOUT PROCEDURES.DOC DOC document
233113 FL - METAL DUCTS.DOC DOC document
A302.pdf PDF
223400 SF - FUEL-FIRED DOMESTIC-WATER HEATERS.DOC DOC document
230529 SF - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT.DOC DOC document
220719 SF - PLUMBING PIPING INSULATION.DOC DOC document
A101.pdf PDF
262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS.DOC DOC document
265600 - EXTERIOR LIGHTING.DOC DOC document
E-101.pdf PDF
M-101.PDF PDF
014200 - REFERENCES.DOC DOC document
0142-428 Geotechnical Report.pdf PDF
260500 - COMMON WORK RESULTS FOR ELECTRICAL.DOC DOC document
E-103.pdf PDF
Camp Ravenna Waste Management Guidelines 21jan2011.doc DOC document
C-040.PDF PDF
017300 - EXECUTION.DOC DOC document
E-100.pdf PDF
233423 FL - HVAC POWER VENTILATORS.DOC DOC document
A102.pdf PDF
221316 SF - SANITARY WASTE AND VENT PIPING.DOC DOC document
Show all 50

Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT TRAINING EQUIPMENT SITE ADD/ALT

Copyright 2009 by The American Institute of Architects (AIA)

Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA

SECTION 321373 - CONCRETE PAVING JOINT SEALANTS

Revise this Section by deleting and inserting text to meet Project-specific requirements.

This Section uses the term "Architect." Change this term to match that used to identify the design professional as defined in the General and Supplementary Conditions.

Verify that Section titles referenced in this Section are correct for this Project's Specifications; Section titles may have changed.

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Cold-applied joint sealants.

2. Cold-applied, jet-fuel-resistant joint sealants.

3. Hot-applied joint sealants.

4. Hot-applied, jet-fuel-resistant joint sealants.

1.2 PRECONSTRUCTION TESTING

Preconstruction compatibility and adhesion testing in this article is performed off-site by joint-sealant manufacturer. Test requires many Samples, and some tests require four weeks to complete. If retaining, also retain "Preconstruction compatibility and adhesion test reports" Paragraph in "Informational Submittals" Article.

A. Preconstruction Compatibility and Adhesion Testing: Submit to joint-sealant manufacturers, eight, Samples of materials that will contact or affect joint sealants. Use ASTM C 1087 to determine whether priming and other specific joint-preparation techniques are required to obtain rapid, optimum adhesion of joint sealants to joint substrates.

1.3 ACTION SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

First paragraph below assumes manufacturer's standard-size Samples are acceptable. Revise to suit Project.

B. Samples: For each kind and color of joint sealant required.

C. Pavement-Joint-Sealant Schedule: Include the following information:

1. Joint-sealant application, joint location, and designation.

2. Joint-sealant manufacturer and product name.

3. Joint-sealant formulation.

4. Joint-sealant color.

1.4 INFORMATIONAL SUBMITTALS

A. Product certificates.

B. Product test reports.

Coordinate test reports in paragraph below with testing requirements in "Preconstruction Testing" Article.

C. Preconstruction compatibility and adhesion test reports.

1.5 QUALITY ASSURANCE

A. Testing Agency Qualifications: An independent testing agency qualified according to ASTM C 1021.

B. Preinstallation Conference: Conduct conference at Project site.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Compatibility: Provide joint sealants, backing materials, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by joint-sealant manufacturer based on testing and field experience.

Retain paragraph below if joint sealants specified are offered in a choice of colors and colors are not specified in Paving-Joint-Sealant Schedule in Part 3 or on Drawings. Typically, color choice is not available for pavement joint sealants.

B. Colors of Exposed Joint Sealants: As selected by Architect from manufacturer's full range.

2.2 COLD-APPLIED JOINT SEALANTS

A. One-component, Elastomeric, Gun-Grade Polyurethane Sealant for Concrete: High-performance, chemically curing elastomeric formulation complying with the following requirements for formulation and with ASTM C 920 for type, grade, class, and uses indicated:

1. Polyurethane Formulation: Type S; Grade NS; Class 25; Uses NT, M, A, G and I, as applicable to joint substrates indicated.

a. Products:

b. Sonolastic NP 1, BASF, Sonneborn.

2.3 JOINT-SEALANT BACKER MATERIALS

A. Expansion-Joint Filler Strips: Polyethylene closed-cell backing for Sonolastic Sealants.

B. Isolation- and Control -Joint Filler Strips: Closed –cell Backer-Rod and Soft Backer-Rod. ASTM C 1330, Type B and C.

Retain one of first two paragraphs below for use in joints such as contraction joints cut partially through paving material.

2.4 PRIMERS

Generally retain this article unless it is known that priming of substrates is not required with joint sealants specified. Purpose of primers is to improve adhesion of joint sealant to substrate.

A. Primers: Product recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

PART 3 - EXECUTION

3.1 INSTALLATION

A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated unless more stringent requirements apply.

B. Cleaning of Joints: Clean out joints immediately before installing joint sealants.

C. Joint-Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

D. Install joint-sealant backings of kind indicated to support joint sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

1. Do not leave gaps between ends of joint-sealant backings.

2. Do not stretch, twist, puncture, or tear joint-sealant backings.

3. Remove absorbent joint-sealant backings that have become wet before sealant application and replace them with dry materials.

E. Install joint sealants using proven techniques that comply with the following and at the same time backings are installed:

1. Place joint sealants so they directly contact and fully wet joint substrates.

2. Completely fill recesses in each joint configuration.

3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow optimum sealant movement capability.

F. Tooling of Nonsag Joint Sealants: Immediately after joint-sealant application and before skinning or curing begins, tool sealants according to the following requirements to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint:

1. Remove excess joint sealant from surfaces adjacent to joints.

2. Use tooling agents that are approved in writing by joint-sealant manufacturer and that do not discolor sealants or adjacent surfaces.

G. Provide joint configuration to comply with joint-sealant manufacturer's written instructions unless otherwise indicated.

H. Clean off excess joint sealant or sealant smears adjacent to joints as the Work progresses, by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

END OF SECTION 321373