334600 - SUBDRAINAGE.DOC
DOC document 43 KB Posted
- Attached to
- Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) Federal contract opportunity
- Solicitation number
- W91364-12-R-0005
About this file
SECTION 334600
View the file
Other files for this federal contract opportunity
Show all 50
Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNIT TRAINING EQUIPMENT SITE ADD/ALT
Copyright 2009 by The American Institute of Architects (AIA)
Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA
SECTION 334600 - SUBDRAINAGE
Revise this Section by deleting and inserting text to meet Project-specific requirements.
Verify that Section titles referenced in this Section are correct for this Project's Specifications; Section titles may have changed.
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Perforated-wall pipe and fittings.
2. Geotextile filter fabrics.
1.2 ACTION SUBMITTALS
A. Product Data: For geotextile filter fabrics.
PART 2 - PRODUCTS
2.1 PERFORATED-WALL PIPES AND FITTINGS
Pipe materials in this article have perforated walls and typically are joined with loose joints.
Pipe and fittings in paragraph below are available in NPS 3 to NPS 6 (DN 80 to DN 150). Joints are coupling type.
A. Perforated PE Pipe and Fittings: ASTM F 405 or AASHTO M 252, Type CP; corrugated, for coupled joints.
2.2 SOIL MATERIALS
A. Soil materials are specified in Division 31 Section "Earth Moving."
2.3 WATERPROOFING FELTS
A. Material: Comply with ASTM D 226, Type I, asphalt-saturated organic felt.
2.4 GEOTEXTILE FILTER FABRICS
A. Description: Fabric of PP or polyester fibers or combination of both, with flow rate range from 110 to 330 gpm/sq. ft. (4480 to 13 440 L/min. per sq. m) when tested according to ASTM D 4491.
B. Structure Type: Nonwoven, needle-punched continuous filament.
Class 2 in first subparagraph below is the default class recommended by AASHTO.
1. Survivability: AASHTO M 288 Class 2.
2. Styles: Flat and sock.
PART 3 - EXECUTION
3.1 EARTHWORK
A. Excavating, trenching, and backfilling are specified in Division 31 Section "Earth Moving."
3.2 FOUNDATION DRAINAGE INSTALLATION
A. Place impervious fill material on subgrade adjacent to bottom of footing after concrete footing forms have been removed. Place and compact impervious fill to dimensions indicated, but not less than 6 inches (150 mm) deep and 12 inches (300 mm) wide.
B. Lay flat-style geotextile filter fabric in trench and overlap trench sides.
C. Place supporting layer of drainage course over compacted subgrade and geotextile filter fabric, to compacted depth of not less than 4 inches (100 mm).
D. Encase pipe with sock-style geotextile filter fabric before installing pipe. Connect sock sections with tape.
E. Install drainage piping as indicated in Part 3 "Piping Installation" Article for foundation subdrainage.
F. Add drainage course to width of at least 6 inches (150 mm) on side away from wall and to top of pipe to perform tests.
G. After satisfactory testing, cover drainage piping to width of at least 6 inches (150 mm) on side away from footing and above top of pipe to within 12 inches (300 mm) of finish grade.
H. Install drainage course and wrap top of drainage course with flat-style geotextile filter fabric.
I. Place layer of flat-style geotextile filter fabric over top of drainage course, overlapping edges at least 4 inches (100 mm).
J. Place backfill material over compacted drainage course. Place material in loose-depth layers not exceeding 6 inches (150 mm). Thoroughly compact each layer. Final backfill to finish elevations and slope away from building.
3.3 UNDERSLAB DRAINAGE INSTALLATION
A. Excavate for underslab drainage system after subgrade material has been compacted but before drainage course has been placed. Include horizontal distance of at least 6 inches (150 mm) between drainage pipe and trench walls. Grade bottom of trench excavations to required slope, and compact to firm, solid bed for drainage system.
B. Lay flat-style geotextile filter fabric in trench and overlap trench sides.
C. Place supporting layer of drainage course over compacted subgrade and geotextile filter fabric, to compacted depth of not less than 4 inches (100 mm).
D. Encase pipe with sock-style geotextile filter fabric before installing pipe. Connect sock sections with tape.
E. Install drainage piping as indicated in Part 3 "Piping Installation" Article for underslab subdrainage.
F. Add drainage course to width of at least 6 inches (150 mm) on side away from wall and to top of pipe to perform tests.
G. After satisfactory testing, cover drainage piping with drainage course to elevation of bottom of slab, and compact and wrap top of drainage course with flat-style geotextile filter fabric.
3.4 PIPING INSTALLATION
A. Install piping beginning at low points of system, true to grades and alignment indicated, with unbroken continuity of invert. Bed piping with full bearing in filtering material. Install gaskets, seals, sleeves, and couplings according to manufacturer's written instructions and other requirements indicated.
Of first three subparagraphs below, retain only those applicable to Project. Revise first subparagraph below as required for different minimum cover.
1. Foundation Subdrainage: Install piping level and with a minimum cover of 36 inches (915 mm) unless otherwise indicated.
2. Underslab Subdrainage: Install piping level.
3. Retaining-Wall Subdrainage: When water discharges at end of wall into stormwater piping system, install piping level and with a minimum cover of 36 inches (915 mm) unless otherwise indicated.
Revise first subparagraph below as required for different minimum slope and cover.
4. Lay perforated pipe with perforations down.
Revise subparagraph below to suit Project or delete.
5. Excavate recesses in trench bottom for bell ends of pipe. Lay pipe with bells facing upslope and with spigot end entered fully into adjacent bell.
B. Use increasers, reducers, and couplings made for different sizes or materials of pipes and fittings being connected. Reduction of pipe size in direction of flow is prohibited.
C. Install thermoplastic piping according to ASTM D 2321.
3.5 PIPE JOINT CONSTRUCTION
A. Join perforated PE pipe and fittings with couplings according to ASTM D 3212 with loose banded, coupled, or push-on joints.
B. Special Pipe Couplings: Join piping made of different materials and dimensions with special couplings made for this application. Use couplings that are compatible with and fit materials and dimensions of both pipes.
3.6 BACKWATER VALVE INSTALLATION
A. Comply with requirements for backwater valves specified in Division 33 Section "Storm Utility Drainage Piping."
B. Install horizontal backwater valves in header piping downstream from perforated subdrainage piping.
Backwater valves must be accessable for maintenance. Detail backwater valves and manholes or pits if backwater valve's check valve cannot be reached from the surface.
C. Install horizontal backwater valves in piping in manholes or pits where indicated.
3.7 CLEANOUT INSTALLATION
A. Comply with requirements for cleanouts specified in Division 33 Section "Storm Utility Drainage Piping."
B. Cleanouts for Foundation and Retaining-Wall Subdrainage:
1. Install cleanouts from piping to grade. Locate cleanouts at beginning of piping run and at changes in direction. Install fittings so cleanouts open in direction of flow in piping.
2. In vehicular-traffic areas, use NPS 4 (DN 100) cast-iron soil pipe and fittings for piping branch fittings and riser extensions to cleanout. Set cleanout frames and covers in a cast-in-place concrete anchor, 18 by 18 by 12 inches (450 by 450 by 300 mm) deep. Set top of cleanout flush with grade.
3. In nonvehicular-traffic areas, use NPS 4 (DN 100) PVC pipe and fittings for piping branch fittings and riser extensions to cleanout. Set cleanout frames and covers in a cast-in-place concrete anchor, 12 by 12 by 4 inches (300 by 300 by 100 mm) deep. Set top of cleanout 1 inch (25 mm) above grade.
4. Comply with requirements for concrete specified in Division 03 Section "Cast-in-Place Concrete."
C. Cleanouts for Underslab Subdrainage:
1. Install cleanouts and riser extensions from piping to top of slab. Locate cleanouts at beginning of piping run and at changes in direction. Install fittings so cleanouts open in direction of flow in piping.
2. Use NPS 4 (DN 100) cast-iron soil pipe and fittings for piping branch fittings and riser extensions to cleanout flush with top of slab.
3.8 CONNECTIONS
Coordinate piping installations and specialty arrangements with schematics on Drawings and with requirements specified in piping systems. If Drawings are explicit enough, these requirements may be reduced or omitted.
A. Comply with requirements for piping specified in Division 33 Section "Storm Utility Drainage Piping." Drawings indicate general arrangement of piping, fittings, and specialties.
Retain option in first paragraph below if connection will be to building's storm drainage system.
B. Connect low elevations of subdrainage system to building's solid-wall-piping storm drainage system.
Retain paragraph below if gravity discharge is not possible.
3.9 FIELD QUALITY CONTROL
Retain first paragraph below to describe tests and inspections to be performed. Insert specific test requirements to comply with authorities having jurisdiction.
A. Tests and Inspections:
1. After installing drainage course to top of piping, test drain piping with water to ensure free flow before backfilling.
2. Remove obstructions, replace damaged components, and repeat test until results are satisfactory.
See Division 01 Section "Quality Requirements" for retesting and reinspecting requirements and Division 01 Section "Execution" for requirements for correcting the Work.
B. Drain piping will be considered defective if it does not pass tests and inspections.
C. Prepare test and inspection reports.
3.10 CLEANING
A. Clear interior of installed piping and structures of dirt and other superfluous material as work progresses. Maintain swab or drag in piping and pull past each joint as it is completed. Place plugs in ends of uncompleted pipe at end of each day or when work stops.
END OF SECTION 334600
| Project No: 390265 SUBDRAINAGE |
| 334600 - 4 |
File details come from the government source that posted it. Updated .