017700 - CLOSEOUT PROCEDURES.DOC

DOC document 44 KB Posted

Attached to
Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) Federal contract opportunity
Solicitation number
W91364-12-R-0005
Issued by
Department of the Army Ohio Army National Guard

About this file

CLOSEOUT PROCEDURES

View the file

Other files for this federal contract opportunity

Other files attached to Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC), newest first.
File Type Posted
323113 - CHAIN LINK FENCES AND GATES.DOC DOC document
321373 - CONCRETE PAVING JOINT SEALANTS.DOC DOC document
412213 BRIDGE CRANES.doc DOC document
321313 - CONCRETE PAVING.DOC DOC document
proposal questions and answers MATOC.pdf PDF
site visit information.pdf PDF
329200 - TURF AND GRASSES.DOC DOC document
334100 - STORM UTILITY DRAINAGE PIPING.DOC DOC document
262416 - PANELBOARDS.DOC DOC document
262913 - ENCLOSED CONTROLLERS.DOC DOC document
220500_FL - COMMON WORK RESULTS FOR PLUMBING.DOC DOC document
018100 - GENERAL COMMISSIONING REQUIREMENTS.DOC DOC document
E-108.pdf PDF
099113 - EXTERIOR PAINTING.DOC DOC document
081113 - HOLLOW METAL DOORS AND FRAMES.DOC DOC document
260526 - GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS.DOC DOC document
230513 SF - COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT.DOC DOC document
260923 - LIGHTING CONTROL DEVICES.DOC DOC document
017823 - OPERATION AND MAINTENANCE DATA.DOC DOC document
230593 SF - TESTING ADJUSTING AND BALANCING FOR HVAC.DOC DOC document
079200 - JOINT SEALANTS.DOC DOC document
E-104.pdf PDF
018150 - COMMISSIONING OF HVAC.DOC DOC document
S-100.PDF PDF
M-100.PDF PDF
A301.pdf PDF
221113 - FACILITY WATER DISTRIBUTION PIPING.DOC DOC document
A600.pdf PDF
233113 FL - METAL DUCTS.DOC DOC document
A302.pdf PDF
223400 SF - FUEL-FIRED DOMESTIC-WATER HEATERS.DOC DOC document
A201.pdf PDF
P-102.PDF PDF
E-102.pdf PDF
013200 - CONSTRUCTION PROGRESS DOCUMENTATION.DOC DOC document
S-104.PDF PDF
A303.pdf PDF
015000 - TEMPORARY FACILITIES AND CONTROLS.DOC DOC document
221119 SF - DOMESTIC WATER PIPING SPECIALTIES.DOC DOC document
E-109.pdf PDF
E-107.pdf PDF
cr_recyclables_tracking_report_form_9feb2011.xlsx XLSX spreadsheet
265100 - INTERIOR LIGHTING.DOC DOC document
237339 SF - INDOOR DIRECT-FIRED HEATING AND VENTILATING UNITS.DOC DOC document
012500 - SUBSTITUTION PROCEDURES.DOC DOC document
104416 - FIRE EXTINGUISHERS.DOC DOC document
016000 - PRODUCT REQUIREMENTS.DOC DOC document
101400 - SIGNAGE.DOC DOC document
013100 - PROJECT MANAGEMENT AND COORDINATION.DOC DOC document
133419 - METAL BUILDING SYSTEMS.DOC DOC document
Show all 50

Construction Indefinite Delivery-Indefinite Quantity (IDIQ) Multiple Award Task Order Contracts (MATOC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT TRAINING EQUIPMENT SITE ADD/ALT

Copyright 2010 by The American Institute of Architects (AIA)

Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA

SECTION 017700 - CLOSEOUT PROCEDURES

Revise this Section by deleting and inserting text to meet Project-specific requirements.

This Section uses the term "Architect." Change this term to match that used to identify the design professional as defined in the General and Supplementary Conditions.

Verify that Section titles referenced in this Section are correct for this Project's Specifications; Section titles may have changed.

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

Retain or delete this article in all Sections of Project Manual.

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

Coordinate list below with "Related Requirements" subparagraphs.

1. Substantial Completion procedures.

2. Warranties.

3. Final cleaning.

B. Related Requirements:

Retain subparagraphs below to cross-reference requirements Contractor might expect to find in this Section but are specified in other Sections.

1. Division 1 Section "Payment Procedures" for requirements for Applications for Payment for Substantial and Final Completion.

2. Division 1 Section "Execution Requirements" for progress cleaning of Project site.

3. Division 1 Section "Project Record Documents" for submitting Record Drawings, Record Specifications, and Record Product Data.

4. Division 1 Section "Operation and Maintenance Data" for operation and maintenance manual requirements.

5. Division 1 Section "Demonstration and Training" for requirements for instructing Owner's personnel.

6. Divisions 2 through 16 Sections for specific closeout and special cleaning requirements for the Work in those Sections.

1.3 FINAL COMPLETION PROCEDURES

A. Submittals Prior to Final Completion: Before requesting final inspection for determining final completion, complete the following:

Revise subparagraphs below to match the Supplementary Conditions.

1. Submit a final Application for Payment according to Division 1 Section "Payment Procedures."

2. Submit certified copy of Architect's Beneficial Occupancy inspection list of items to be completed or corrected (punch list), endorsed and dated by Architect. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

3. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

4. Submit pest-control final inspection report and warranty.

5. Instruct Owner's personnel in operation, adjustment, and maintenance of products, equipment, and systems and Submit demonstration and training videotapes.

Revise "Inspection" Paragraph below to comply with office policy and Project requirements.

B. Inspection: Submit a written request for final inspection to determine acceptance a minimum of 10 days prior to date the work will be completed and ready for final inspection and tests. On receipt of request, Architect will either proceed with inspection or notify Contractor of unfulfilled requirements. Architect will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

1.4 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

1. Organize list of spaces in sequential order.

2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems.

3. Include the following information at the top of each page:

a. Project name.

b. Date.

c. Name of Architect.

d. Name of Contractor.

e. Page number.

1.5 SUBMITTAL OF PROJECT WARRANTIES

A. Time of Submittal: Submit written warranties on request of Architect for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated, or when delay in submittal of warranties might limit Owner's rights under warranty.

On advice of Owner's legal counsel, revise "Partial Occupancy" Paragraph below to suit Project. Sometimes, extended warranties may be necessary.

B. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor.

C. Organize warranty documents into an orderly sequence based on the table of contents of Project Manual.

Revise first subparagraph below to suit Project.

1. Bind warranties and bonds in heavy-duty, three-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch (215-by-280-mm) paper.

2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

Retain "Warranty Electronic File" Subparagraph below and paper copy documents if required by Owner. Indexing requirement below can be performed automatically using PDF publishing software.

4. Warranty Electronic File: Scan warranties and bonds and assemble complete warranty and bond submittal package into a single indexed electronic PDF file with links enabling navigation to each item. Provide bookmarked table of contents at beginning of document.

Coordinate paragraph below if using Section 017823 "Operation and Maintenance Data."

D. Provide additional copies of each warranty to include in operation and maintenance manuals.

PART 2 - PRODUCTS

2.1 MATERIALS

"Cleaning Agents" Paragraph below contains basic requirements. Revise this article to suit Project or to accommodate unusual situations.

A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

Requirements in subparagraph below are from the USGBC's "LEED 2009 for Existing Buildings: Operation & Maintenance" (LEED-EB), Credit IEQ 3.3. Revise if Owner requirements differ.

PART 3 - EXECUTION

3.1 FINAL CLEANING

Delete this article if owners prefer to use their own personnel. Cleaning provisions in the General Conditions are limited to rubbish removal and similar activities.

A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

If final cleaning is delayed until final acceptance, revise subparagraph below.

1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project:

Subparagraphs below are a sample list of final cleaning requirements. Revise to suit Project.

a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

c. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.

d. Remove tools, construction equipment, machinery, and surplus material from Project site.

e. Remove snow and ice to provide safe access to building.

f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

g. Remove debris and surface dust from limited access spaces, including roofs, plenums, shafts, trenches, equipment vaults, manholes, attics, and similar spaces.

h. Sweep concrete floors broom clean in unoccupied spaces.

i. Vacuum carpet and similar soft surfaces, removing debris and excess nap; clean according to manufacturer's recommendations if visible soil or stains remain.

j. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other noticeable, vision-obscuring materials. Polish mirrors and glass, taking care not to scratch surfaces.

k. Remove labels that are not permanent.

Revise subparagraphs below to suit Project. Check for conflict or duplication with provisions in other Sections.

l. Wipe surfaces of mechanical and electrical equipment and similar equipment. Remove excess lubrication, paint and mortar droppings, and other foreign substances.

m. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water exposure.

n. Replace disposable air filters and clean permanent air filters. Clean exposed surfaces of diffusers, registers, and grills.

First subparagraph below describes a major work item that requires coordination with other closeout procedures.

o. Clean ducts, blowers, and coils if units were operated without filters during construction or that display contamination with particulate matter on inspection.

Retain first subparagraph below in environments with demanding HVAC system cleaning standards or for special contamination issues. Below adds significantly to cleaning cost.

1) Clean HVAC system in compliance with NADCA Standard 1992-01. Provide written report on completion of cleaning.

p. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency.

q. Leave Project clean and ready for occupancy.

"Pest Control" and "Construction Waste Disposal" paragraphs below represent end of the Work specified in Section 015000 "Temporary Facilities and Controls." Most projects require these actions at completion of construction. Insert a paragraph on termite inspection where required by authorities having jurisdiction or applicable for Project.

C. Pest Control: Comply with pest control requirements in Section 015000 "Temporary Facilities and Controls." Prepare written report.

D. Construction Waste Disposal: Comply with waste disposal requirements in Section 017419 "Construction Waste Management and Disposal."

Insert an article on continuing inspections or consultations by Contractor if required. Possibly insert a schedule of approximate times for inspections.

3.2 REPAIR OF THE WORK

A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.

B. Repair or remove and replace defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired. Restore damaged construction and permanent facilities used during construction to specified condition.

1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.

2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces. Replace finishes and surfaces that that already show evidence of repair or restoration.

a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.

3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.

4. Replace burned-out bulbs, bulbs noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

Insert additional requirements to suit Project.

END OF SECTION 017700

Project No: 309265 CLOSEOUT PROCEDURES
017700 - 5

File details come from the government source that posted it. Updated .