W912QR24R0034_KC-46A_Specs-0005.pdf
PDF 2 MB Posted
- Solicitation number
- W912QR24R0034
About this file
This file is a technical specification section for Total Building Commissioning (Section 01 46 00.00 06) for a KC-46A Two-Bay Hangar project at March Air Base, California. The specification provides comprehensive requirements for commissioning building systems, including heating, ventilation, air conditioning, building automation, lighting, power distribution, plumbing, and energy metering systems. The commissioning process mandates an independent Commissioning Specialist who must be a first-tier subcontractor, financially independent from other contractors, and responsible for coordinating all aspects of the commissioning process.
Key requirements include detailed submittal procedures, qualification standards for Commissioning Specialists, and a rigorous testing and documentation protocol. The specification outlines specific responsibilities for the Lead Commissioning Specialist, including preparing a Construction Phase Commissioning Plan, conducting design reviews, overseeing inspection and testing, developing checklists, performing functional performance tests, and producing comprehensive commissioning reports. The process involves multiple stakeholders, including the Contractor's Quality Control Representative, mechanical and electrical subcontractors, and government representatives, with the goal of ensuring that all building systems are installed, tested, and operate according to design specifications and performance requirements.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P2#505421:2-Bay Hangar/P2#509757:Mooring Points&Restriping March Air Base, CA
SECTION 01 46 00.00 06
TOTAL BUILDING COMMISSIONING
04/20
Amendment 0005
PART 1 GENERAL
Commission the building systems listed herein. Employ the services of independent Commissioning Specialists. The Commissioning Specialists must be 1st tier subcontractors of the General or Prime Contractor; must be financially and corporately independent of all other subcontractors; and must not have any other role in constructing the systems to be commissioned. The Commissioning Specialists must coordinate all aspects of the commissioning process. Conform to the commissioning procedures outlined in this specification.
1.1 SYSTEMS TO BE COMMISSIONED
Commission the following systems:
Heating, Ventilating, Air Conditioning, and Refrigeration Systems
(HVAC)
Building Automation System
Utility Monitoring and Control System
Lighting Systems
Power Distribution Systems
Plumbing Systems
Energy and Water Utility Metering Systems and Sub-Meters
Building Envelope: Include moisture, thermal integrity, and air tightness for the entire building envelope including systems such as walls, fenestration, roofing, roof openings, floors, below grade perimeter walls, crawlspaces, attics, slabs-on-grade, floor assemblies
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING
ENGINEERS (ASHRAE)
ASHRAE 202 (2018) Commissioning Process for Buildings and Systems
ASSOCIATED AIR BALANCE COUNCIL (AABC)
ACG Commissioning Guideline (2005) Commissioning Guideline
SECTION 01 46 00.00 06 Page 1 Amendment 0005 - Certified Final
W912QR24R0034_KC-46A_Specs-0005
ASTM INTERNATIONAL (ASTM)
ASTM E2947-16 (2016) Standard Guide for Building Enclosure Commissioning
NATIONAL ENVIRONMENTAL BALANCING BUREAU (NEBB)
NEBB Commissioning Standard (2018) Whole Building Technical Commissioning of New Construction
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
ANSI/SMACNA 014-2013 (2013) HVAC Systems Commissioning Manual, 2nd Edition
US Army Corps of Engineers (USACE)
ER 25-345-1 Regulation No. 25-345-1Military Publications SYSTEMS MANUAL
Amendment 0005**************************************************************
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29.00 06 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Commissioning Specialists G
Submit the Commissioning Specialists' certification of qualifications no later than 30 calendar days after Notice to Proceed. Submit one hard copy and an electronic copy.
Project Schedule; G
Project construction schedule which includes commissioning milestone activities. Submit within 14 calendar days following the Construction Commissioning Coordination Meeting. Submit one hard copy and an electronic copy.
SD-06 Test Reports
Construction Phase Commissioning Plan; G.
Submit no later than 30 calendar days after the Construction Commissioning Coordination Meeting. Submit one hard copy and an electronic copy.
Building Envelope Inspection Checklists; G
SECTION 01 46 00.00 06 Page 2
Submit the completed and initialed Building Envelope Inspection Checklists no later than 7 calendar days after completion of inspection of all checklists items. Submit one hard copy and an electronic copy.
Pre-Functional Checklists; G
Submit no later than 7 calendar days after completion of all checklist items for each system. Submit one hard copy and an electronic copy.
PVT Procedures; G
Submit no later than 14 calendar days prior to Performance Verification Tests. Submit one hard copy and an electronic copy.
PVT Report; G
Submit no later than 30 calendar days prior to Functional Performance Tests. Submit three hard copies and an electronic copy.
Issues Log
Submit one hard copy and an electronic copy on the same day each month.
Trend Log Report
Submit one hard copy and an electronic copy no later than 14 calendar days prior to Functional Performance Tests.
Post-Construction Trend Log Report
Submit one hard copy and one electronic copy of the Post-Construction Trend Log Reports, once for peak cooling season and once for peak heating season, no later than 14 calendar days following receipt of the trend log data by the Lead Commissioning Specialist.
Commissioning Report; G
Submit no later than 14 calendar days following commissioning team acceptance of all Performance Tests. Submit three hard copies and an electronic copy.
Post-Construction Commissioning Report; G
Submit no later than 14 calendar days following completion of all post-construction trend log reviews and building site visit.
Submit three hard copies and an electronic copy.
SD-07 Certificates
Certificate of Readiness; G
Submit no later than 14 calendar days prior to Functional Performance Tests. Submit one hard copy and an electronic copy.
SECTION 01 46 00.00 06 Page 3
SD-10 Operation and Maintenance Data
Systems Training; G, DO
Submit two copies of the Systems Training recording no later than 14 calendar days following completing of the Systems Training.
Training Plan; G, RO
Submit one hard copy and an electronic copy no later than 30 calendar days prior to the associated training.
Training Attendance Rosters; G, RO
Submit one hard copy and an electronic copy no later than 7 calendar days following the completion of the training for each system to be commissioned.
Systems Manual; G, DO
Submit Systems Manual no later than 30 calendar days following completion of Functional Performance Tests. Submit three hard copies and an electronic copy.
Post-Construction Systems Manual; G, DO
Submit Systems Manual no later than 14 calendar days following completion of all post-construction trend log reviews and building site visits. Submit three hard copies and an electronic copy.
SD-11 Closeout Submittals
Final Commissioning Report; S
Copy of the Post-Construction Commissioning Report for the Sustainability eNotebook. Submit an electronic copy concurrent with the Post-Construction Commissioning Report.
Final Construction Phase Commissioning Plan; S
Copy of the Construction Phase Commissioning Plan for the Sustainability eNotebook. Submit an electronic copy concurrent with the Construction Phase Commissioning Plan.
***************************************************************Amendment 0005
1.4 COMMISSIONING SPECIALISTS
1.4.1 Lead Commissioning Specialist (CxC)
The Lead Commissioning Specialist must lead and oversee all commissioning work specified herein and be the primary point of contact for the Government regarding commissioning work. The Lead Commissioning Specialist (CxC) must have a minimum of five years of commissioning experience, including two projects of similar size and complexity. The Lead Commissioning Specialist must also be one of the following:
a. AABC Commissioning Group (ACG) Certified Commissioning Authority
b. Building Commissioning Association (BCA) Certified Commissioning
SECTION 01 46 00.00 06 Page 4
Professional
c. International Certification Board/Testing, Adjusting, and Balancing Bureau (ICB/TABB) Certified Commissioning Supervisor
d. National Environmental Balancing Bureau (NEBB) Qualified Systems Commissioning Administrator
e. University of Wisconsin-Madison Qualified Commissioning Provider
f. Association of Energy Engineers (AEE) Certified Building Commissioning Specialist
1.4.2 Electrical Commissioning Specialist (CxE)
The technical work associated with the power distribution and generation systems must be performed by a Electrical Commissioning Specialist that is an engineering technician with five years of experience inspecting, testing, and calibrating electrical distribution and generation equipment, systems, and devices.
1.4.3 Building Envelope Commissioning Specialist (CxB)
The technical work associated with the Building Envelope systems must be performed by a Building Envelope Commissioning Specialist (CxB) meeting one of the following qualifications:
a. Five years of experience coordinating and instructing personnel involved in installation, joining, and sealing of air barrier materials and components and certification as an Air Barrier Installer from the Air Barrier Association of America (ABAA) or other 3rd party air barrier association.
b. A registered architect with at least five years of building envelope design or construction experience.
Commissioning Specialists with alternative qualifications may be approved at the sole discretion of the Government. The CxB may act as the Air Barrier Inspector required by Specification section 07 27 10.00 10 BUILDING AIR BARRIER SYSTEM provided that all of the qualification requirements of that specification section are met. The CxB may act as the thermographer required by Specification section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS provided that all qualification requirements of that specification section are met. The firm providing the CxB may act as the Pressure Test Agency required by Specification section 07 05 23 provided that all qualification requirements of that specification section are met.
1.4.4 Commissioning Specialists Certification
The Commissioning Specialists' qualifications must include the names of the specialists and firms; certifications, licenses, or registrations;
years of experience and a listing of representative projects of similar size and complexity. Describe any lapses in certification or disciplinary action taken by the certifying body against the proposed specialists or firms in detail. Any specialist/technician or firm that has been the subject of disciplinary action by the certifying body within the five years preceding the contract award is not eligible to perform any duties related to commissioning.
SECTION 01 46 00.00 06 Page 5
The Commissioning Specialists' certifications must be maintained for the entire duration of the duties specified herein. If, for any reason, a Commissioning Specialist loses a certification during this period, immediately notify the Contracting Officer's Representative and submit another Commissioning Specialist. All work specified in this specification section to be performed by the Commissioning Specialist is invalid if the Commissioning Specialist loses their certification prior to contract completion and must be performed by an approved successor.
1.4.5 Communication With The Government
The Lead Commissioning Specialist must submit all plans, schedules, reports, and documentation directly to the Contracting Officer's Representative concurrent with submission to the CQC System Manager. The Commissioning Specialists and Contracting Officer's Representative must have direct communication with each other regarding all elements of the commissioning process; however, the Government has no direct contract authority with the Commissioning Specialists.
1.5 COMMISSIONING STANDARD
Comply with the requirements of the commissioning standard under which the Commissioning Specialists qualifications are approved. When the firm and specialists are certified by BCA, AEE, or the University of Wisconsin-Madison, comply with the requirements of one of the acceptable standards unless otherwise stated herein. The acceptable standards are ACG Commissioning Guideline , NEBB Commissioning Standard , ANSI/SMACNA 014-2013 , or ASHRAE 202. Comply with applicable NETA testing standards for electrical systems. Comply with ASTM E2947-16 for commissioning of building envelope systems.
a. Implement all recommendations and suggested practices contained in the Commissioning Standard and electrical test standards.
b. Use the Commissioning Standard for all aspects of Commissioning, including calibration of instruments.
c. Where the instrument manufacturer calibration recommendations are more stringent than those listed in the Commissioning Standard, adhere to the manufacturer calibration recommendations.
d. All quality assurance provisions of the Commissioning Standard such as performance guarantees are part of this contract .
e. The Commissioning Specialists must develop commissioning procedures for any systems or system components not covered in the Commissioning Standard.
f. Use any new requirements, recommendations, and procedures published or adopted prior to contract solicitation by the body responsible for the Commissioning Standard.
1.6 SUSTAINABILITY THIRD PARTY CERTIFICATION (TPC)
The Lead Commissioning Specialist must execute and document the commissioning activities required of the Commissioning Authority for the purposes of complying with Third Party Certification (TPC) requirements for the project in accordance with Section 01 33 29.00 06 SUSTAINABILITY
SECTION 01 46 00.00 06 Page 6
REPORTING. Provide all commissioning documentation required to meet the TPC requirements.
The Final Construction Phase Commissioning Plan and the Final Commissioning Report are copies of the Construction Phase Commissioning Plan and the Post-Construction Commissioning Report for inclusion in the Sustainability eNotebook.
1.7 ISSUES LOG
The Lead Commissioning Specialist must develop and maintain an Issues Log for tracking and resolution of all deficiencies discovered through submittal review, inspection, and testing. Include the date of final resolution of issues as confirmed by the Commissioning Specialists.
Submit the Issues Log on a monthly basis at a minimum. At any point during construction, any commissioning team member finding deficiencies may communicate those deficiencies in writing to the Lead Commissioning Specialist for including into the Issues Log.
Track construction deficiencies identified in the Issues Log using RMS as specified in Specification Section 01 45 00.15 RESIDENT MANAGEMENT SYSTEM
CONTRACTOR MODE(RMS CM).
1.8 CERTIFICATE OF READINESS
Prior to scheduling Functional Performance Tests for each system, issue a Certificate of Readiness certifying that the building system is ready for Functional Performance Testing. The Certificate of Readiness must include, for each system to be commissioned, all equipment and system start-up reports; Performance Verification Test Reports; completed Building Envelope Inspection Checklists; completed Pre-Functional Checklists; Testing, Adjusting, and Balancing (TAB) Report; Trend Log Review Report; and the Building Air Barrier Air Leakage Test Reports and Diagnostic Test Reports. The Contractor; the Lead Commissioning Specialist; the Contractor's Quality Control Representative; and the Mechanical, Electrical, Controls, and TAB subcontractor representatives must sign and date the Certificate of Readiness. Do not schedule and perform Functional Performance Tests prior to Government approval of the Certificate of Readiness.
1.9 PROJECT SCHEDULE
Include the following tasks in the Project Schedule provided in accordance with section 01 32 01.00 06 PROJECT SCHEDULE. Ensure sufficient time is scheduled to accommodate the requirements of this specification section.
The order of items listed are not intended to imply a specified sequence:
a. Pre-Construction Conference (Specification Section 07 27 10.00 10)
b. Electrical system energization.
c. Electrical system acceptance tests and inspections (Specification Section 26 08 00)
d. Mock-Up Tests (Specification Section 07 27 10.00 10
e. Building Enclosure Construction
f. Building Envelope Inspection Checklist Submittal
SECTION 01 46 00.00 06 Page 7
g. Air Barrier Leakage Test
h. Drainage and Vent, Building Sewers, Water Supply Systems and Backflow Prevention Assembly Tests
i. Potable Water System Flushing
j. Operational Tests of the plumbing systems (Specification 22 00 00)
k. Disinfection of the plumbing systems (Specification 22 00 00)
l. Duct Air Leakage Tests
m. Manufacturer Equipment Start-Up for each system to be commissioned.
n. Testing, Adjusting, and Balancing (TAB)
o. TAB Verification
p. Performance Verification Tests
q. HVAC Trend Log Report
r. Pre-Functional Checklist Submittal
s. Functional Performance Testing
t. Post-Test Deficiency Correction
u. Re-Testing
v. Training for each system to be commissioned
w. Systems Manual, Maintenance Plan, and Service Life Plan Submission
x. Submission and approval of the Commissioning Report
y. Seasonal Tests
z. Post-Construction Trend Log Reports
aa. Post-Construction Building Site Visit
1.10 FUNCTIONAL PERFORMANCE TEST PREREQUISITES
Complete the following prior to starting Functional Performance Tests of the mechanical systems:
a. The building envelope is enclosed according to contract documents with final construction completed, the Air Barrier Pressure Tests have been completed and the Air Leakage Test Reports and Diagnostic Test Reports have been submitted and approved in accordance with Section 07 05 23
PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS.
b. All equipment and systems have been completed, cleaned, flushed, disinfected, calibrated, tested, and operate in accordance with the contract documents and construction plans and specifications.
SECTION 01 46 00.00 06 Page 8
c. Testing, Adjusting, and Balancing has been completed and the Testing, Adjusting, and Balancing Report has been submitted and approved in accordance with Section 23 05 93.00 06 TESTING, ADJUSTING, AND
BALANCING FOR HVAC.
d. Performance Verification Tests of the controls systems have been completed and the Performance Verification Tests Report has been submitted and approved in accordance with Specification Section
23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC.
e. The Pre-Functional Checklists have been submitted and approved.
f. The Certificate of Readiness for the mechanical systems has been submitted and approved.
Complete the following prior to starting Functional Performance Tests of the electrical systems:
a. All electrical, power generation, and lighting equipment and systems have been completed, calibrated, tested, and operate in accordance with contract documents and construction plans and specifications.
b. The Certificate of Readiness for electrical systems has been submitted and approved.
PART 2 PRODUCTS(NOT APPLICABLE)
PART 3 EXECUTION
Amendment 0005***************************************************************
3.1 DELETED
***************************************************************Amendment 0005
3.2 CONSTRUCTION PHASE
3.2.1 Construction Commissioning Coordination Meeting
The Lead Commissioning Specialist must lead a Construction Commissioning Coordination Meeting no later than 14 calendar days after approval of the Commissioning Specialists 30 calendar days following construction notice to proceed to discuss the commissioning process including contract requirements, lines of communication, roles and responsibilities, schedules, documentation requirements, inspection and test procedures, and logistics as specified in this specification section. The Contractor's Superintendent or Project Manager, the Contractor's Quality Control Representative, and the Government must attend this meeting. Invite the User and a Directorate of Public Works Representativea Reserve Readiness Division RepresentativeBase Civil Engineer Representative to attend this meeting.
3.2.2 Commissioning Progress Meetings
The Lead Commissioning Specialist must lead Commissioning Progress Meetings to discuss the progress of commissioning process activities, upcoming commissioning activities, and any issues and deficiencies. The Contractor's Superintendent or Project Manager, the Contractor's Quality Control Representative, and the Government must attend this meeting. A representative from each of the sub-contractors involved in the systems to be commissioned must attend this meeting. Invite the User to attend these meetings.
SECTION 01 46 00.00 06 Page 9
The Mechanical, Electrical, and Architectural designers of record must participate in the Commissioning Progress Meetings, at the request of the Lead Commissioning Specialist, to address any design issues or issues regarding technical adequacy.
Commissioning Progress Meetings must occur monthly, or as needed, following the Construction Commissioning Coordination Meeting. When installation of interior mechanical or electrical systems begins, the Commissioning Progress Meetings must occur every 2 weeks, or as needed.
3.2.3 Construction Phase Commissioning Plan
The Lead Commissioning Specialist must prepare the Construction Phase Commissioning Plan identifying the commissioning and testing standards to be used and outlining the overall commissioning process, the commissioning schedule, the commissioning team members and responsibilities, lines of communication, and the documentation requirements for the construction phase of the project. Include the template building envelope inspection checklists, pre-functional checklists, and Functional Performance Test checklists.
Download example checklists at the following location:
http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs/forms-graphics-tables The checklists submitted with the Construction Phase Commissioning Plan are required to have the same level of detail as the example checklists, but are not required to match the format of the examples.
The construction phase commissioning plan must include the monitoring and control points, sample frequency, and duration of trends for the trend log reviews.
3.2.3.1 Template Building Envelope Inspection Checklists
The Building Envelope Commissioning Specialist must develop the Template Building Envelope Inspection Checklists. Include all items that verify the building materials and construction maintain the required thermal and moisture integrity and air tightness of the building envelope system.
Incorporate requirements, including additional activities, of ASTM E2947-16 into the template building envelope checklists and the Construction Phase Commissioning Plan.
3.2.3.2 Pre-Functional Checklists
The Commissioning Specialists must develop the Pre-Functional Checklists.
Pre-Functional Checklists include items for physical inspection or testing that demonstrate that installation and start-up of all equipment and systems is complete. Refer to paragraph "Pre-Functional Checks" for more information.
3.2.3.3 Functional Performance Test Checklists
The Commissioning Specialists must develop the Functional Performance Test Checklists including procedures that explain, step-by-step, the actions and expected results that will demonstrate that the system performs in accordance with the contract. Refer to paragraph "Functional Performance Tests" for more information.
Include the following sections and details appropriate to the systems
SECTION 01 46 00.00 06 Page 10 being tested:
a. Notable system features including information about controls to facilitate understanding of system operation.
b. Conclusions and recommendations. Conclusions must clearly indicate if system does or does not perform in accordance with contract requirements. Recommendation must clearly indicate that the system should or should not be accepted by the Government.
c. Test conditions including date, beginning and ending time, and beginning and ending outdoor air conditions.
d. Attendees.
e. Identification of the equipment involved in the test.
f. Control system feature identification.
g. Point-to-point observations including demonstrating system sensors and flow meters have been calibrated and are correctly displayed on the Operator work station.
h. Actuator operation observations demonstrating actuator responses to commands from the control system.
i. As-found condition of the system operation.
j. List of test items with step numbers along with the corresponding feature or control operation, intended test procedure, expected system response, and pass/fail indication.
k. Space for comments for each test item.
3.2.4 Design Review
The Commissioning Specialists must review the construction contract plans and specifications, the Owner's Project Requirements, and the Basis of Design. The Owner's Project Requirements and Basis of Design documents are not contract documents and are provided for commissioning review purposes only. The Commissioning Specialists must identify any discovered discrepancies between the Basis of Design and the Owner's Project Requirements, any deficiencies of the design to comply with the Owner's Project Requirements or Basis of Design and any deficiencies that would prevent the building systems and features from operating or performing effectively or from being adequately maintainable.
The Commissioning Specialists must provide a Design Review Report individually listing each deficiency and the corresponding proposed corrective action necessary for proper system operation or performance.
The Lead Commissioning Specialist must lead a meeting with the Contracting Officer's Representative and Contractor's Quality Control Representative to discuss any items contained in the report no later than 14 calendar days after submission of the report. Invite the designers of record for the commissioned systems to attend.
SECTION 01 46 00.00 06 Page 11
3.2.5 Construction Submittals
Provide all submittals associated with the systems to be commissioned, including shop drawings; equipment submittals; test plans, procedures, and reports; and resubmittals to the Commissioning Specialists. The Commissioning Specialists must review the submittals to the extent necessary verify that the equipment and system installation will comply with the contract requirements and the requirements of the Basis of Design and the Owner's Project Requirements Document.
3.2.6 Inspection and Testing
Demonstrate that all system components have been installed, that each control device and item of equipment operates, and that the systems operate and perform in accordance with contract documents and the Owner's Project Requirements. Requirements in related Sections are independent from the requirements of this Section and do not satisfy any of the requirements specified in this specification section. Provide all materials, services, and labor required to perform and submit the Pre-Functional Checks , Building Envelope Inspection, HVAC system trend logs, and Functional Performance Tests.
3.2.6.1 Commissioning Team
Provide a commissioning representative for each sub-contractor associated with the systems to be commissioned. Each commissioning representative is responsible for coordination of their respective sub-contractor's execution of the commissioning activities and participation in the inspection and testing required by this specification section. The designers listed below must be the designer of record for the respective system. Substitutes must be approved by the Contracting Officer's Representative.
Designate team members to participate in the building envelope inspections, Pre-Functional checks, and the Functional Performance Testing specified herein.
3.2.6.1.1 Building Envelope Inspections Team
The following team members participate as needed in building envelope inspections:
Designation Function
CxB Building Envelope Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
BEC Contractor's Building Envelope Commissioning Representative
AD Architectural Designer
SECTION 01 46 00.00 06 Page 12
3.2.6.1.2 Mechanical Systems Team
The following team members participate as needed in Pre-Functional Checks and Functional Performance Testing of mechanical systems:
Designation Function
CxC Lead Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
MC Contractor's Mechanical Commissioning Representative
CC Contractor's Controls Commissioning Representative
TABC Contractor's TAB Commissioning Representative
PC Contractor's Plumbing Commissioning Representative
MD Mechanical Designer (Functional Performance Tests Only)
PD Plumbing Designer (Functional Performance Tests Only)
ID Irrigation Designer (Functional Performance Tests Only)
3.2.6.1.3 Electrical Systems Team
The following team members participate as needed in Pre-Functional Checks and Functional Performance Testing of electrical systems:
Designation Function
CxE Electrical Commissioning Specialist
QAR Contracting Officer's Quality Assurance Representative
CQC Contractor's Quality Control Personnel
EC Contractor's Electrical Commissioning Representative
ED Electrical Designer (Functional Performance Tests Only)
3.2.6.1.4 Other Pre-Functional and Functional Performance Participants
The following may participate as team members during Pre-Functional Checks and Functional Performance Testing:
SECTION 01 46 00.00 06 Page 13
Designation Function
DPW Directorate of Public Works Representative
BCE Base Civil Engineer Office Representative
RD Reserve Readiness Division Representative
PWD Public Works Division Representative
User Using Agent's Representative
3.2.6.2 Building Envelope Inspection and Pressure Tests
Document building envelope inspection by the commissioning team using the approved Template Building Envelope Inspection Checklists. Indicate commissioning team member inspection and acceptance of each Building Envelope Inspection Checklist item by initials at the time they are inspected and found to be in conformance with contract requirements.
Inspect checklist items before they become hidden as construction progresses. Submit the completed and initialed Building Envelope Inspection Checklists no later than 7 calendar days after completion of inspection of all checklist items.
The Building Envelope Technical Commissioning Specialist must make at least two site visits to the site to observe construction of the building envelope in-progress. On each visit, the Building Envelope Commissioning Specialist must review the Contractor's in-progress checklists to ensure that the commissioning team is inspecting the building envelope as required. Perform additional activities as required by ASTM E2947-16 and the approved Construction Phase Commissioning Plan.
The Building Envelope Technical Commissioning Specialist must witness the building envelope pressure tests and diagnostic tests specified in Specification Section 07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS. The Building Envelope Technical Commissioning Specialist must review the resulting reports and provide recommendations for correction of any deficiencies or further testing.
3.2.6.3 Pre-Functional Checks
Pre-Functional Checklists from the approved Construction Phase Commissioning Plan must be completed by the commissioning team. Complete one Pre-Functional Checklist for each individual item of equipment or system for each system required to be commissioned including, but not limited to, ductwork, piping, equipment, fixtures (lighting and plumbing), panels, and controls. Indicate commissioning team member inspection and acceptance of each Pre-Functional Checklist item by initials. Acceptance of each Pre-Functional Checklist item by each team member indicates that item has been installed correctly and conforms to the construction contract and accepted design requirements in their area of responsibility.
Commissioning Specialist acceptance of each Pre-Functional Checklist item indicates that each item has been installed correctly and in accordance with contract documents and the Owner's Project Requirements. Submit the completed and initialed Pre-Functional Checklists upon completion.
Include manufacturer start-up checklists associated with the equipment
SECTION 01 46 00.00 06 Page 14 with the submission of the Pre-Functional Checklists.
3.2.6.4 Testing, Adjusting, and Balancing (TAB) Verification
The Lead Commissioning Specialist must witness the TAB Verification performed in accordance with LRL section 23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING OF HVAC. Identify any deficiencies in the Issues Log.
The Lead Commissioning Specialist must witness the TAB Verification performed in accordance with LRL section 23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING OF HVACTAB Field Acceptance Testing performed in accordance with UFGS section 23 05 93.00 06 TESTING, ADJUSTING, AND BALANCING (TAB) OF HVAC. Identify any deficiencies in the Issues Log.
Following the testing, adjusting, and balancing of the systems and submission of a TAB Report and prior to scheduling Functional Performance Tests, perform a TAB verification with the Contracting Officer's Quality Assurance Representative present. The Lead Commissioning Specialist must witness the TAB verification.
Recheck a minimum of 10 percent of all readings listed in the TAB report during TAB verification. The Contracting Officer's Quality Assurance Representative will select the readings to be rechecked. If over 20 percent of the measurements rechecked fall outside of the specified tolerance from design requirements specified, recheck an additional 10 percent sample with selection of readings by the Contracting Officer's Quality Assurance Representative. If over 20 percent of the total rechecked readings fall outside of the required tolerance, the TAB Report will be considered invalid and all contract required testing, adjusting, and balancing work must be repeated.
Repair all insulation following completion of TAB Verification.
3.2.6.5 Building Control System Performance Verification Tests
The controls contractor must perform a Performance Verification Test (PVT) of the building control systems demonstrating that the control systems are in compliance with the requirements of the construction contract and accepted design. Show, step-by-step, the actions and results demonstrating that the systems perform in accordance with the sequences of operation. A one-point accuracy check will be performed for each sensor.
Prepare and submit PVT Procedures that list the step-by-step procedures to be performed during the tests and the expected results from each step that demonstrate contract and accepted design compliance. Start the Performance Verification Tests only after approval of the PVT Procedures.
Provide a PVT Report documenting all tests performed during the PVT and the results. Document all failures and associated repairs in the PVT Report.
The Lead Commissioning Specialist must review the PVT Procedures or Test Plan and the PVT Report required by Specification Section 23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC. Include a certification by the Lead Commissioning Specialist with each of these submittals that the submittals do not indicate any deficiencies in the HVAC systems or HVAC control systems .
SECTION 01 46 00.00 06 Page 15
3.2.6.6 HVAC System Trend Logs
Following approval of the Performance Verification Test (PVT) Report and prior to Functional Performance Testing, the Lead Commissioning Specialist must review trend logs from the heating, ventilation, air-conditioning, and refrigeration control systems to ensure that the systems have stable operation and operate as required by construction contract , the accepted design, and the Owner's Project Requirements. Review trends for all items of equipment including sensor inputs; valve and damper positions (command or feedback); equipment status, modes, and commands; and variable frequency drive commands. Control and monitoring points, sample frequency, and duration of trends must be in accordance with the approved Construction Phase Commissioning Plan. Provide a Trend Log Report that identifies any deficiencies noted in operation and includes a graphical representation of the trends.
3.2.6.7 Tests
3.2.6.7.1 Functional Performance Tests
Schedule personnel to attend the Functional Performance Tests for each system only after the Certificate of Readiness has been approved by the Government for the system and all deficiencies identified through any prior review, inspection, or test activity have been corrected. The Lead Commissioning Specialist must lead and document all Functional Performance Tests for the systems to be commissioned with the Contractor and appropriate sub-contractors performing the Functional Performance Tests.
The Electrical Commissioning Specialist must lead and document Functional Performance Tests for power distribution and generation systems. The representatives listed in the paragraph "Commissioning Team" must attend the Functional Performance Tests.
Abort Functional Performance Tests when any system deficiency prevents the successful completion of the test.
3.2.6.7.1.1 Checklists
Use the Functional Performance Test Checklists from the approved Construction Phase Commissioning Plan to guide the Functional Performance Tests. Functional Performance Tests must be performed for each item of equipment and each system required to be commissioned and verify all sensor calibrations, control responses, safeties, interlocks, operating modes, sequences of operation, capacities, lighting levels, and all other system performance requirements comply with the construction contract and accepted design requirements regardless of the specific items listed within the Functional Performance Test Checklists provided. Testing must progress from equipment or components to subsystems to systems to interlocks and connections between systems. The order of components and systems to be tested must be determined by the Lead Commissioning Specialist, and by the Electrical Commissioning Specialist for power distribution and generation systems.
3.2.6.7.1.2 Acceptance
Indicate acceptance of each item of equipment and systems tested by signature of each commissioning team member for each Functional Performance Test. The Contractor's Quality Control Representative and the Lead Commissioning Specialist must indicate acceptance after the equipment and systems are free of deficiencies. The Electrical Commissioning
SECTION 01 46 00.00 06 Page 16
Specialist must indicate acceptance after the power distribution and generation equipment and systems are free of deficiencies.
3.2.6.7.2 Sample Strategy
Perform Functional Performance Tests using the following sample strategy.
Prepare and complete a Functional Performance Test Checklist for each item of equipment or system to be tested. For sample sizes less than 100 percent for all similar equipment, the Government will select the specific equipment or system to be tested during testing. Equipment Identifiers are as indicated on the design drawings:
Equipment Identifier Sample Size (Percent)
AHU 100
VAV 25
Exhaust Fan 100
Fan Coil Unit 100
DWH 100
Humidifier 100
Lighting Controls 100
Perform Functional Performance Tests for all equipment and systems.
Prepare and complete a Functional Performance Test Checklist for each item of equipment or system.
3.2.6.7.3 Seasonal Tests
Regardless of the season, perform initial Functional Performance Tests of equipment and systems at the time of system completion. Develop and implement means of artificial loading to demonstrate, to a reasonable level of confidence, the ability of the HVAC systems to handle peak seasonal loads.
In addition to the initial Functional Performance Tests, perform Functional Performance Tests of the HVAC systems during peak heating and cooling seasons during outdoor air condition design extremes. Schedule the seasonal Functional Performance Tests in coordination with the Government.
Systems may be partially accepted by the Government prior to seasonal testing if they comply with all construction contract and accepted design requirements that can be tested during the initial Functional Performance Tests. All Functional Performance Test procedures must be completed prior to full systems acceptance.
3.2.6.7.4 Aborted Tests and Re-Testing
Abort Functional Performance Tests or Seasonal Tests if any deficiency prevents successful completion of the test. Reimburse the Government for all costs associated with effort lost caused by re-testing due to test failures and aborted tests. These costs must include salary, travel
SECTION 01 46 00.00 06 Page 17 costs, and per diem for Government commissioning team members. Re-test only after all deficiencies identified during the original tests have been corrected.
3.2.6.7.4.1 100 percent Sample
Systems or items of equipment for which 100 percent sample are tested fail if one or more of the test procedures results in a discovery of a deficiency and the deficiency can not be resolved within 5 minutes during the test. Upon test failure, abort the test of the system or item of equipment. Schedule a re-test, in coordination with the Government, only after all deficiencies for all failed equipment and systems have been corrected.
Re-test to the extent necessary to confirm that the deficiencies have been corrected. At the sole discretion of the Government, all test procedures for the failed item of equipment or system must be repeated to confirm that no deficiencies remain within that equipment or system.
3.2.6.7.4.2 Less than 100 percent Sample
For systems or equipment tests with a sample size less than 100 percent, if one or more of the test procedures for an item of equipment or system results in discovery of a deficiency, regardless of whether the deficiency is corrected during the sample tests, the item of equipment or system fails the test. Correction of the deficiencies during Functional Performance Testing may be performed only at the sole discretion of the Government.
If the system failure rate is 5 percent or less, meaning that 5 percent or less of the equipment or systems had at least one deficiency, re-test only the items which experienced the initial failures.
If the system failure rate is higher than 5 percent, meaning that more than 5 percent of the equipment or systems tested had at least one deficiency, re-test the items which experience the initial failures. In addition, test another sample of the same size as the initial sample for the first time. If the second sample set has any failures, re-test those failed items and all remaining equipment and systems to complete 100 percent testing of that system type.
3.3 SYSTEMS TRAINING
The training specified by the specification sections associated with commissioned systems must be provided by certified technicians or trainers. Include both demonstration of proper equipment and system operation both at the equipment and classroom training. For the classroom training, include proper operating and maintenance procedures, preventative maintenance requirements and procedures, trouble-shooting procedures, and calibration frequency and procedures. Include identification of the equipment and system warranties and procedures for correction under the warranties. Include a review of the draft systems manual, maintenance plan, and service life plans.
Visibly and audibly record the systems training. All instruction on the recording must be clear and intelligible.
SECTION 01 46 00.00 06 Page 18
3.4 TRAINING PLAN
Develop a training plan which identifies all training required by specification sections associated with commissioned systems. Include a matrix listing each training requirement, content of the training, the trainer name, trainer contact information, and schedule and location of training.
Document training attendance using Training Attendance Rosters and provide completed attendance rosters to the Lead Commissioning Specialist and the Government.
3.5 SYSTEMS MANUAL
Prepare and submit a Systems Manual including a signed certification or letter from the Lead Commissioning Specialist and Electrical Commissioning Specialist stating that the Systems Manual is complete, clear, and accurate. The Systems Manual, for all commissioned systems, must conform to Appendix A SYSTEMS MANUAL ORGANIZATION AND CONTENT to ER 25-345-1 , available at the USACE Publications website at the following location:
https://www.publications.usace.army.mil/USACE-Publications/Engineer-Regulations/ Update and resubmit the Systems Manual based on any corrective action taken during the warranty period.
3.6 CURRENT FACILITIES REQUIREMENTS AND O&M PLAN
Prepare and submit a Current Facilities Requirements and O&M Plan document that contains information necessary to operate the building efficiently.
Include the following:
a. Sequences of operation for all commissioned systems.
b. Building occupancy schedule.
c. Equipment run-time schedules.
d. Setpoints for all HVAC equipment.
e. Set lighting levels throughout the building.
f. Minimum outside air requirements.
g. Changes in schedules or setpoints for different seasons, days of the week, and times of the day.
h. Systems narrative describing the mechanical and electrical systems and equipment.
i. Preventative maintenance plan for building equipment described in the systems narrative.
j. Commissioning program including periodic commissioning requirements, ongoing commissioning tasks, and continuous tasks for critical facilities.
Information from other submitted documents may be referenced from the current facilities requirements and O&M plan in lieu of repeating information provided that the reference includes the location of the information in those other submitted documents such as page number or
SECTION 01 46 00.00 06 Page 19 chapter or part and section.
3.7 COMMISSIONING REPORT
Following the completion of Functional Performance Tests, with the exception of Seasonal Tests, the Lead Commissioning Specialist must prepare a Commissioning Report including an executive summary describing the overall commissioning process, describing the results of the commissioning process, listing any outstanding deficiencies and recommended resolutions, and describing any seasonal testing that must be scheduled for a later date. Indicate, in the executive summary, whether the systems meet the requirements of the construction contract and accepted design and the Owner's Project Requirements.
Detail any deficiencies discovered during the commissioning process and the corrective actions taken. Include the completed Building Envelope Inspection Checklists, Pre-Functional Checklists, Functional Performance Test Checklists, the Construction Phase Commissioning Plan, the Issues Log, Performance Verification Test Reports, Training Attendance Rosters, the Design Review Report, and the final TAB Report.
Following any Seasonal Tests or Post-Construction Activities, update the Commissioning Report to reflect any changes and resubmit.
3.8 POST-CONSTRUCTION SUPPORT
Submit a Post-Construction Commissioning Report and Post-Construction Systems Manual that supplement the original Commissioning Report and Systems Manual with documentation of the results of the post-construction site visit and HVAC trend log review. Include Post-Construction Trend Log Report in the Post-Construction Commissioning Report. Submit a Post-Construction Commissioning Report and Post-Construction Systems Manual with documentation of the results of the post-construction site visit.
3.8.1 Post-Construction HVAC Trend Logging
Provide Trend Logs from the heating, ventilation, air conditioning, and refrigeration control systems to the Lead Commissioning Specialist once during peak heating season and once during peak cooling season. Selected control and monitoring points, sample frequency, and duration of trends must be in accordance with the Construction Phase Commissioning Plan.
The Lead Commissioning Specialist must review trends for all items of equipment including all sensor inputs; valve and damper positions (commands or feedback); equipment status, modes, and commands; and variable frequency drive commands to ensure that the systems have stable operation and operate as required by the construction contract ,the accepted design, and the Owner's Project Requirements. The Lead Commissioning Specialist must provide a Post-Construction Trend Log Report that identifies any deficiencies noted in operation and includes a graphical representation of the trends. Provide one Trend Log Report for the peak cooling season and one Trend Log Report for the peak heating season.
3.8.2 Post-Construction Site Visit
The Lead Commissioning Specialist must visit the building site concurrent with the 9 month warranty inspection to inspect building system equipment
SECTION 01 46 00.00 06 Page 20 and review building operation with the building operating/maintenance staff. The Lead Commissioning Specialist must identify any deficiency of the building systems to operate in accordance with the contract and accepted design requirements and the Owner's Project Requirements. The Lead Commissioning Specialist must advise the Contracting Officer's Representative of any identified deficiencies and the proposed corrective action.
-- End of Section --
SECTION 01 46 00.00 06 Page 21
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 46 00.00 06 Page 22
SECTION 05 40 00
COLD-FORMED METAL FRAMING
05/15, CHG 1: 08/18
Amendment 0005
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE (ACI)
ACI 318 (2014; Errata 1-2 2014; Errata 3-5 2015;
Errata 6 2016; Errata 7-9 2017) Building Code Requirements for Structural Concrete (ACI 318-14) and Commentary (ACI 318R-14)
AMERICAN IRON AND STEEL INSTITUTE (AISI)
AISI S100 (2012) North American Specification for the Design of Cold-Formed Steel Structural Members
AISI S110 (2007; Suppl 1; Reaffirmed 2012) Standard for Seismic Design of Cold-Formed Steel Structural Systems - Special Bolted Moment Frames
AISI S200 (2007) North American Standard for Cold-Formed Steel Framing - General Provision
AISI S201 (2007) North American Standard for Cold-Formed Steel Framing - Product Data
AISI S202 (2011) Code of Standard Practice for Cold-formed Steel Structural Framing
AISI S211 (2007) North American Standard for Cold-Formed Steel Framing - Wall Stud Design
AISI S212 (2007) North American Standard for Cold-Formed Steel Framing - Header Design