This file is a Project Table of Contents for specification sections 08 11 13 (Steel Doors and Frames), 09 06 00 (Schedules for Finishes), 09 90 00 (Paints and Coatings), 13 34 19 (Metal Building Systems), and 22 00 00 (Plumbing, General Purpose) for a construction project at March Air Reserve Base, California. The specifications cover detailed requirements for materials, fabrication, installation, and finishes for various building components including steel doors, frames, wall panels, painting, plumbing systems, and metal building systems.
The specification sections provide comprehensive technical guidelines for contractors, including material specifications, installation methods, quality assurance requirements, and performance standards. Key elements include requirements for steel doors with various duty levels, color schedules for exterior and interior finishes, paint application procedures, metal building system fabrication and erection, and plumbing fixture installations. The documents specify precise technical standards for materials such as door construction, paint types, metal panel coatings, and plumbing equipment, ensuring high-quality construction that meets military facility standards.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P2# 504634 Addition/Alteration of B1244 March Air Base, CA
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION AND DECONSTRUCTION
02 81 00 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 82 00 ASBESTOS REMEDIATION
02 83 00 LEAD REMEDIATION
02 84 16 HANDLING OF LIGHTING BALLASTS AND
LAMPS CONTAINING PCBs AND MERCURY
02 84 33 05/20 REMOVAL AND DISPOSAL OF
POLYCHLORINATED BIPHENYLS (PCBs)
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 4: 08/22 CAST-IN-PLACE CONCRETE
03 33 00 11/09 CAST-IN-PLACE ARCHITECTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 05 23.16 08/18 STRUCTURAL WELDING
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 05/17, CHG 1: 08/18 MISCELLANEOUS METAL FABRICATIONS SS
COUNTERTOPS
05 51 00 08/23 METAL STAIRS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 52 00 02/18, CHG 1: 02/20 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM
FOR AIR TIGHTNESS
07 11 13 08/11, CHG 1: 05/17 BITUMINOUS DAMPPROOFING
07 21 13 02/16, CHG 2: 08/20 BOARD AND BLOCK INSULATION
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 19.01 05/17, CHG 2: 08/20 SELF-ADHERING AIR BARRIERS
PROJECT TABLE OF CONTENTS
AMENDMENT 0004
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 10 00 PRICE BREAKOUT SCHEDULE
(See P2#505421 KC-46A Two-Bay Maintenance Hangar for Div 00 Specs)00.00 06 04/21 SPECIAL PROVISIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
(See P2#505421 KC-46A Two-Bay Maintenance Hangar for Div 01 Specs)
PROJECT TABLE OF CONTENTS
AMENDMENT 0004Amendment 0004 - Certified Final
Volume I
W912QR24R0034_B1244_Specs-0004
07 27 26 05/17, CHG 2: 08/20 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 27 36 05/17, CHG 2: 08/20 SPRAY FOAM AIR BARRIERS
07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS
07 42 63 05/11, CHG 4: 08/20 FABRICATED WALL PANEL ASSEMBLIES
07 54 19 02/13, CHG 3: 02/21 POLYVINYL-CHLORIDE ROOFING
07 60 00 05/17, CHG 2: 11/18 FLASHING AND SHEET METAL
07 61 14.00 20 08/16, CHG 1: 08/18 STEEL STANDING SEAM ROOFING
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16, CHG 3: 11/18 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 06 00 08/22 SCHEDULES FOR FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 68 00 11/17, CHG 2: 08/20 CARPETING
09 90 00 02/21 PAINTS AND COATINGS
09 97 13.27 DELETED
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 08/20 TOILET COMPARTMENTS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 56 13 04/06 STEEL SHELVING
10 81 13 03/10 BIRD CONTROL DEVICES (BID OPTION)
DIVISION 12 - FURNISHINGS
12 24 13 08/20 ROLLER WINDOW SHADES
12 50 00.13 10 08/17, CHG 1: 11/18 FURNITURE AND FURNITURE INSTALLATION
12 59 00 08/17, CHG 1: 08/18 SYSTEMS FURNITURE
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 19 08/20, CHG 1: 02/21 METAL BUILDING SYSTEMS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 30 00 04/08, CHG 1: 08/13 FIRE PUMPS
PROJECT TABLE OF CONTENTS
AMENDMENT 0004
13 34 19 08/20, CHG 1: 02/21 METAL BUILDING SYSTEMS
05/19 08/20
PROJECT TABLE OF CONTENTS
AMENDMENT 0004Amendment 0004 - Certified Final
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING, SUPPORTS, ANCHORAGE,
AND VIBRATION ISOLATION FOR MECHANICAL
SYSTEMS
23 05 93.00 06 08/16 TESTING, ADJUSTING, AND BALANCING
(TAB) OF HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
23 35 16.17 10 05/20 MECHANICAL ENGINE EXHAUST SYSTEMS
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.01 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - HVAC AND AMI
25 05 11.02 05/21 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - FIRE PROTECTION
DIVISION 26 - ELECTRICAL
26 05 26.00 40 08/19 GROUNDING AND BONDING FOR ELECTRICAL
SYSTEMS
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 05 73 08/23 POWER SYSTEM STUDIES
26 20 00 08/19, CHG 3: 11/21 INTERIOR DISTRIBUTION SYSTEM
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
26 56 00 08/21 EXTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00.00 06 07/18 EARTHWORK
31 05 22.00 06 07/16 GEOTEXTILES USED AS FILTERS
PROJECT TABLE OF CONTENTS
AMENDMENT 0004
PROJECT TABLE OF CONTENTS
AMENDMENT 0004Amendment 0004 - Certified Final
Volume II
31 32 23.00 06 07/16 LOW MOBILITY GROUTING AND GROUT PILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 23 05/22 GRADED CRUSHED AGGREGATE BASE COURSE
32 11 33.13 05/20 PORTLAND CEMENT-STABILIZED BASE COURSES
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 13 73.00 06 07/16 COMPRESSION JOINT SEALS FOR CONCRETE
PAVEMENTS
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13 11/21 CHAIN LINK FENCES AND GATES
32 92 19 08/17, CHG 1: 08/21 SEEDING
DIVISION 33 - UTILITIES
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 11/21 STORMWATER UTILITIES
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS
AMENDMENT 0004
PROJECT TABLE OF CONTENTS
AMENDMENT 0004Amendment 0004 - Certified Final
SECTION 08 11 13
STEEL DOORS AND FRAMES
08/20
Amendment 0004
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WELDING SOCIETY (AWS)
AWS D1.1/D1.1M (2020; Errata 1 2021) Structural Welding Code - Steel
ASTM INTERNATIONAL (ASTM)
ASTM A653/A653M (2023) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM A879/A879M (2012; R 2017) Standard Specification for Steel Sheet, zinc Coated by the Electrolytic Process for Applications Requiring Designation of the Coating Mass on Each Surface
ASTM A924/A924M (2022a) Standard Specification for General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process
ASTM C578 (2022) Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation
ASTM C591 (2021) Standard Specification for Unfaced Preformed Rigid Cellular Polyisocyanurate Thermal Insulation
ASTM C612 (2014; R 2019) Standard Specification for Mineral Fiber Block and Board Thermal Insulation
ASTM D2863 (2019) Standard Test Method for Measuring the Minimum Oxygen Concentration to Support Candle-Like Combustion of Plastics (Oxygen Index)
BUILDERS HARDWARE MANUFACTURERS ASSOCIATION (BHMA)
ANSI/BHMA A156.115 (2016) Hardware Preparation in Steel Doors and Steel Frames
SECTION 08 11 13 Page 1 Amendment 0004 - Certified Final
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 80 (2022) Standard for Fire Doors and Other Opening Protectives
NFPA 105 (2022) Standard for Smoke Door Assemblies and Other Opening Protectives
NFPA 252 (2022) Standard Methods of Fire Tests of Door Assemblies
STEEL DOOR INSTITUTE (SDI/DOOR)
SDI/DOOR 111 (2009) Recommended Details for Standard Steel Doors, Frames, and Accessories and Related Components
SDI/DOOR 113 (2013; R2018) Standard Practice for Determining the Steady-State Thermal Transmittance of Steel Door and Frame Assemblies
SDI/DOOR A250.4 (2018) Test Procedure and Acceptance Criteria for Physical Endurance for Steel Doors, Frames and Frame Anchors
SDI/DOOR A250.6 (2015) Recommended Practice for Hardware Reinforcing on Standard Steel Doors and Frames
SDI/DOOR A250.8 (2017) Specifications for Standard Steel Doors and Frames
SDI/DOOR A250.11 (2012) Recommended Erection Instructions for Steel Frames
UNDERWRITERS LABORATORIES (UL)
UL 10C (2016; Reprint May 2021) UL Standard for Safety Positive Pressure Fire Tests of Door Assemblies
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-02 Shop Drawings
Doors; G
Frames; G
Accessories
SECTION 08 11 13 Page 2
Schedule of Doors; G
Schedule of Frames; G
SD-03 Product Data
Doors; G
Recycled Content for Steel Door Product; S
Frames; G
Recycled Content for Steel Frame Product; S
Accessories
1.3 DELIVERY, STORAGE, AND HANDLING
Deliver doors, frames, and accessories undamaged and with protective wrappings or packaging. Provide temporary steel spreaders securely fastened to the bottom of each welded frame. Store doors and frames on platforms under cover in clean, dry, ventilated, and accessible locations, with 1/4 inch airspace between doors. Remove damp or wet packaging immediately and wipe affected surfaces dry. Replace damaged materials with new.
PART 2 PRODUCTS
Amendment 0004***************************************************************
2.1 STANDARD STEEL DOORS
SDI/DOOR A250.8 , except as specified otherwise. Prepare doors to receive door hardware as specified in Section 08 71 00 DOOR HARDWARE. Undercut where indicated. Provide exterior doors with top edge closed flush and sealed to prevent water intrusion. Provide doors at 1-3/4 inch thick, unless otherwise indicated. Provide door material that uses a minimum of 25 percent recycled content. Provide data indicating percentage of recycled content for steel door product.
***************************************************************Amendment 0004
2.1.1 Classification - Level, Performance, Model
2.1.1.1 Extra Heavy Duty Doors
SDI/DOOR A250.8 , Level 3, physical performance Level A, Model 2 with core construction as required by the manufacturer for interior doors and for indicated exterior doors, of size(s) and design(s) indicated. Where vertical stiffener cores are required, the space between the stiffeners must be filled with board insulation. Provide Level 3 where indicated.
2.1.1.2 Maximum Duty Doors
SDI/DOOR A250.8 , Level 4, physical performance Level A, Model 2 with core construction as required by the manufacturer for interior door and for indicated exterior doors, of size(s) and design(s) indicated. Where vertical stiffener cores are required, the space between the stiffeners must be filled with board insulation. Provide Level 4 where indicated.
2.2 INSULATED STEEL DOOR SYSTEMS
Provide insulated steel doors and frames in accordance with SDI/DOOR 113
SECTION 08 11 13 Page 3 at entrances to dwelling units and where indicated. Meet energy requirements including Solar Heat Gain Coefficient (SHGC) and U-factor.
Provide insulated steel doors with a core of polyurethane foam; face sheets, edges, and frames of galvanized steel not lighter than 23 gage, 16 gage, and 16 gage respectively; magnetic weatherstripping;
nonremovable-pin hinges; thermal-break aluminum threshold; and vinyl door bottom. Provide to doors and frames a phosphate treatment, rust-inhibitive primer, and baked acrylic enamel finish. Test doors in accordance with SDI/DOOR A250.4 and meet the requirements for Level C.
Prepare doors to receive specified hardware. Provide doors 1-3/4 inch thick.
2.3 ACCESSORIES
2.3.1 Astragals
For pairs of exterior steel doors which will not have aluminum astragals or removable mullions, as specified in Section 08 71 00 DOOR HARDWARE provide overlapping steel astragals with the doors.
2.3.2 Moldings
Provide moldings around glass of interior and exterior doors and louvers of interior doors. Provide nonremovable moldings on outside of exterior doors and on corridor side of interior doors. Other moldings may be stationary or removable. Secure inside moldings to stationary moldings, or provide snap-on moldings.
2.4 INSULATION CORES
Provide insulating cores at all exterior doors, and provide an apparent U-factor of .48 in accordance with SDI/DOOR 113 and conforming to:
a. Rigid Cellular Polyisocyanurate Foam: ASTM C591, Type I or II, foamed-in-place or in board form, with oxygen index of not less than 22 percent when tested in accordance with ASTM D2863; or
b. Rigid Polystyrene Foam Board: ASTM C578, Type I or II; or
c. Mineral board: ASTM C612, Type I.
2.5 STANDARD STEEL FRAMES
SDI/DOOR A250.8 , Level 4, except as otherwise specified. Form frames to sizes and shapes indicated, with welded corners or knock-down field-assembled corners. Provide steel frames for doors, transoms, cased openings, unless otherwise indicated. Provide frame product that uses a minimum of 25 percent recycled content. Provide data indicating percentage of recycled content for steel frame product.
2.5.1 Welded Frames
Continuously weld frame faces at corner joints. Mechanically interlock or continuously weld stops and rabbets. Grind welds smooth.
Weld frames in accordance with the recommended practice of the Structural Welding Code Sections 1 through 6, AWS D1.1/D1.1M and in accordance with the practice specified by the producer of the metal being welded.
SECTION 08 11 13 Page 4
2.5.2 Mullions and Transom Bars
Provide mullions and transom bars of closed or tubular construction with heads and jambs butt-welded together. Bottom of door mullions must have adjustable floor anchors and spreader connections.
2.5.3 Stops and Beads
Provide form and loose stops and beads from 20 gage steel. Provide for glazed and other openings in standard steel frames. Secure beads to frames with oval-head, countersunk Phillips self-tapping sheet metal screws or concealed clips and fasteners. Space fasteners approximately 12 to 16 inch on center. Miter molded shapes at corners. Butt or miter square or rectangular beads at corners.
2.5.4 Terminated Stops
Where indicated, terminate interior door frame stops 6 inch above floor.
2.5.5 Cased Openings
Fabricate frames for cased openings of same material, gage, and assembly as specified for metal door frames, except omit door stops and preparation for hardware.
2.5.6 Anchors
Provide anchors to secure the frame to adjoining construction. Provide steel anchors, zinc-coated not lighter than 18 gage.
2.5.6.1 Wall Anchors
Provide at least three anchors for each jamb. For frames which are more than 7.5 feet in height, provide one additional anchor for each jamb for each additional 2.5 feet or fraction thereof.
a. Masonry: Provide anchors of corrugated or perforated steel straps or 3/16 inch diameter steel wire, adjustable or T-shaped;
b. Stud partitions: Weld or otherwise securely fasten anchors to backs of frames. Design anchors to be fastened to closed steel studs with sheet metal screws, and to open steel studs by wiring or welding;
c. Completed openings: Secure frames to previously placed concrete or masonry with expansion bolts in accordance with SDI/DOOR 111 ; and
2.5.6.2 Floor Anchors
Provide floor anchors drilled for 3/8 inch anchor bolts at bottom of each jamb member. Where floor fill occurs, terminate bottom of frames at the indicated finished floor levels and support by adjustable extension clips resting on and anchored to the structural slabs.
2.6 FIRE AND SMOKE DOORS AND FRAMES
Provide fire and smoke doors and frames in accordance with NFPA 80 and NFPA 105 and this specification. Include insulated core materials in fire doors where indicated in the door schedule.
SECTION 08 11 13 Page 5
2.6.1 Labels
Provide fire doors and frames bearing the label of Underwriters Laboratories (UL), Factory Mutual Engineering and Research (FM), or Warnock Hersey International (WHI) attesting to the rating required.
Testing must be in accordance with NFPA 252 or UL 10C . Provide labels that are metal with raised letters, bearing the name or file number of the door and frame manufacturer. Labels must be permanently affixed at the factory to frames and to the hinge edge of the door. Do not paint door and labels.
2.6.2 Oversized Doors
For fire doors and frames which exceed the size for which testing and labeling are available, furnish certificates stating that the doors and frames are identical in design, materials, and construction to a door which has been tested and meets the requirements for the class indicated.
2.6.3 Astragal on Fire and Smoke Doors
On pairs of labeled fire doors, conform to NFPA 80 and UL requirements.
On smoke control doors, conform to NFPA 105 .
2.7 EXTERIOR FRAMES
Provide thermal insulation in all exterior frames. Provide frames of a minimum Level 4, with frames of a minimum thickness of 0.067 inch, 14 gage.
2.8 HARDWARE PREPARATION
Drill and tap doors and frames to receive finish hardware. Prepare doors and frames for hardware in accordance with the applicable requirements of SDI/DOOR A250.8 and SDI/DOOR A250.6 . For additional requirements refer to ANSI/BHMA A156.115 . Drill and tap for surface-applied hardware at the project site. Build additional reinforcing for surface-applied hardware into the door at the factory. Punch door frames, with the exception of frames that will have weatherstripping gasketing, to receive a minimum of two rubber or vinyl door silencers on lock side of single doors and one silencer for each leaf at heads of double doors. Set lock strikes out to provide clearance for silencers.
2.9 FINISHES
2.9.1 Hot-Dip Zinc-Coated and Factory-Primed Finish
Fabricate scheduled doors and frames from hot dipped zinc coated steel, alloyed type, that complies with ASTM A924/A924M and ASTM A653/A653M . The coating weight must meet or exceed the minimum requirements for coatings having 0.4 ounces per square foot, total both sides, i.e., A40. Repair damaged zinc-coated surfaces by the application of zinc dust paint.
Thoroughly clean and chemically treat to insure maximum paint adhesion.
Factory prime as specified in SDI/DOOR A250.8 . Provide for exterior doors and interior doors.
2.9.2 Electrolytic Zinc-Coated Anchors and Accessories
Provide electrolytically deposited zinc-coated steel in accordance with ASTM A879/A879M , Commercial Quality, Coating Class A. Phosphate treat and factory prime zinc-coated surfaces as specified in SDI/DOOR A250.8 .
SECTION 08 11 13 Page 6
2.10 FABRICATION AND WORKMANSHIP
Provide finished doors and frames that are strong and rigid, neat in appearance, and free from defects, waves, scratches, cuts, dents, ridges, holes, warp, and buckle. Provide molded members that are clean cut, straight, and true, with joints coped or mitered, well formed, and in true alignment. Dress exposed welded and soldered joints smooth. Design door frame sections for use with the wall construction indicated. Corner joints must be well formed and in true alignment. Conceal fastenings where practicable. On wraparound frames for masonry partitions, provide a throat opening 1/8 inch larger than the actual masonry thickness. Design other frames in exposed masonry walls or partitions to allow sufficient space between the inside back of trim and masonry to receive caulking compound.
2.11 PROVISIONS FOR GLAZING
Materials are specified in Section 08 81 00, GLAZING.
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Frames
Set frames in accordance with SDI/DOOR A250.11 . Plumb, align, and brace securely until permanent anchors are set. Anchor bottoms of frames with expansion bolts or powder-actuated fasteners. Build in or secure wall anchors to adjoining construction. Backfill frames with mortar. Coat inside of frames with corrosion-inhibiting bituminous material. For frames in exterior walls, ensure that stops are filled with rigid insulation before grout is placed.
3.1.2 Doors
Hang doors in accordance with clearances specified in SDI/DOOR A250.8 .
After erection and glazing, clean and adjust hardware.
3.1.3 Fire and Smoke Doors and Frames
Install fire doors and frames, including hardware, in accordance with NFPA 80 . Install fire rated smoke doors and frames in accordance with NFPA 80 and NFPA 105 .
3.2 PROTECTION
Protect doors and frames from damage. Repair damaged doors and frames prior to completion and acceptance of the project or replace with new, as directed. Wire brush rusted frames until rust is removed. Clean thoroughly. Apply an all-over coat of rust-inhibitive paint of the same type used for shop coat.
3.3 CLEANING
Upon completion, clean exposed surfaces of doors and frames thoroughly.
Remove mastic smears and other unsightly marks.
-- End of Section --
SECTION 08 11 13 Page 7
SECTION 08 11 13 Page 8
SECTION 09 06 00
SCHEDULES FOR FINISHES
08/22
Amendment 0004
PART 1 GENERAL
1.1 SUMMARY
This section covers only the color of exterior and interior materials and products that are exposed to view in the finished construction. The word "color", as used herein, includes surface color and pattern. Requirements for quality, product specifications, and method of installation are covered in other appropriate sections of the specifications. Specific locations where the various materials are required are shown on the drawings if not identified in this specification. Items not designated for color in this section may be specified in other sections. When color is not designated for items, propose a color for approval.
1.2 SUBMITTALS
SD-04 Samples
Contractor Color Boards; G
1.3 COLOR REFERENCE SYSTEMS
Colors for project finishes are identified in the Color Schedule and based on the Red, Green, Blue (RGB) Color Model, RAL Design Color Guide, AMS-STD-595 (Federal Standard 595C) color reference system.
PART 2 PRODUCTS
2.1 CONTRACTOR COLOR BOARDS
Contractor to submit actual color boards to include all finish color samples specified on the project, prior to the submittal and approval of individual finish submittals. The DOR must review and approve the color boards to verify overall building finish coordination and aesthetic.
Color boards must be prepared by professional interior designers or architects with significant interior design experience. Qualification of designers is based on education, experience and examination. Interior designers or architects must have completed a program accredited by the Council for Interior Design Accreditation (CIDA) or equal accreditation program of academic training in interior design. In addition, the interior designer or architect must also have attained National Council for Interior Design Qualification (NCIDQ) certification or state licensure, certification or registration and must not be affiliated with a furniture dealership, vendor or manufacturer.
2.2 COLOR SCHEDULE
The color information provided in the following paragraphs lists the colors, patterns and textures for exterior and interior finishes, including both factory applied and field applied colors. In the case of difference between the drawings and specifications, colors identified in this specification govern.
SECTION 09 06 00 Page 1 ent 0004 - CertifieCertified Final StatusCertified Final StatusCertified Final StatusAmendment 0004 - Certified Final
2.3 EXTERIOR FINISHES
Reference drawings for color information.
2.3.1 Exterior Walls
Exterior wall colors apply to exterior wall surfaces including recesses at entrances and projecting vestibules. When applicable, paint conduit to closely match the adjacent surface color. Provide wall colors to match the colors listed below.
2.3.1.1 Metal Wall Panels, Hardware, and Associated Trim
MP-1 Insulated metal panel - color matching Base sample Antique Linen (RGB
- 224-207-176)
MP-1 Metal Panel - color matching Base sample Antique Linen (RGB - 224-207-176)
2.3.1.2 Glass and Glazing
IGU-1 - Solar Control Low-Iron Low-E Clear Insulating Glass
2.3.2 Exterior Trim
Provide exterior trim to match the colors listed below.
2.3.2.1 Steel Doors and Door Frames
Color Matching Base Sample - Tobacco Brown (RGB - 102-84-57)
2.3.2.2 Aluminum Doors and Door Frames
Bronze, Anodized.
2.3.2.3 Aluminum Windows (mullion, muntin, sash, trim, and sill)
Bronze, Anodized.
2.3.2.4 Overhead Coiling Doors
Color matching Base sample Tobacco Brown (RGB - 102-84-57)
2.3.2.5 Overhead Coiling Service Doors
Color matching Base sample Tobacco Brown (RGB - 102-84-57)
2.3.2.6 Fascia
Color matching Base sample Terracotta (RGB - 161-92-77)
2.3.2.7 Soffits
MSP-1 (Roof soffit) Color matching Base sample Terracotta (RGB - 161-92-77)
MSP-2 (Tug bay and Main entry) Color matching Base sample Antique Linen
(RGB - TBD)
SECTION 09 06 00 Page 2 ent 0004 - Certified Certified Final StatusAmendment 0004 - Certified Final
IMP-1 (Hangar doors) Color matching Base sample Antique Linen (RGB - 224-207-176
2.3.2.8 Gutters
Color matching Base sample Terracotta (RGB - 161-92-77)
2.3.2.9 Downspouts and Conductor Heads
Color matching Base sample Antique Linen (RGB - 224-207-176)
2.3.2.10 Louvers
Match adjacent material in color. Color matching Base sample Antique Linen (RGB - 224-207-176)
2.3.2.11 Flashings
Match adjacent material in color.
2.3.2.12 Handrails and Guardrails
As indicated on drawings.
2.3.2.13 Caulking and Sealants
Match adjacent material in color.
2.3.2.14 Control Joints
Match adjacent material in color.
2.3.2.15 Expansion Joint and/or Covers
Match adjacent material in color.
2.3.2.16 Bollards
Safety Yellow
2.3.2.17 Canopies
Color matching Base sample Tobacco Brown (RGB - 102-84-57)
2.3.2.18 Translucent Panels
Frame color - TBD
Panel color - Crystal / Crystal
Shoji grid pattern
2.3.3 Exterior Roof
Apply roof color to exterior roof surfaces including sheet metal flashings and copings, mechanical units, mechanical penthouses, roof trim, pipes, conduits, electrical appurtenances, and similar items. Provide roof color to match the colors listed below.
SECTION 09 06 00 Page 3 ent 0004 - Certified FCertified Final StatusAmendment 0004 - Certified Final
PVC roof and accessories, white color.
2.3.3.1 Metal
Color matching Base sample Terracotta (RGB - 161-92-77)
2.4 INTERIOR FINISHES
2.4.1 Interior Floor Finishes
Provide flooring materials to match the colors listed below.
2.4.1.1 Carpet Tile
CPT-1 - Tarkett, Pattern: Thread Craft #11569, Color: Night Vale #60801, 18 inch by 36 inch tile, Installation: Ashlar.
2.4.1.2 Luxury Vinyl Tile
RF-1 - Mannington, Pattern: Bend ALB401, Color: Pop, 6 inch by 36 inch tile, Unbeveled edges, Installation: Ashlar.
2.4.1.3 Porcelain Tile
TLP-1 - Concept Surfaces, Style: Luna, Color: DG, Finish:
Matte, 12 inch by 24 inch, Installation: Straight.
2.4.1.4 Grout
GR-1 - Mapei, Color: 09 Gray.
2.4.1.5 Aluminum Transition
Clear, Anodized.
Amendment 0004 ***********************************************************
2.4.1.6 Concrete (Sealed and Hardened)
CS-1 - Concrete, Sealed : Euclid Chemical, Euco Diamond Hard, Color: Clear .
*********************************************************** Amendment 0004
2.4.1.7 Industrial Floor Coating
RES-1 - Stonhard, Style: Stonshield QBT, Color: Flagstone
2.4.2 Interior Base Finishes
Provide base materials to match the colors listed below.
2.4.2.1 Resilient Base and Moldings
RB-1 - Tarkett, 4 inch Cove base, Color: TA4 Gateway.
2.4.2.2 Integral Cove Base
RESB-1 - Stonhard, 4 inch Cove base, Style: Stonshield QBT, Color: Flagstone.
SECTION 09 06 00 Page 4 ent 0004 - Certified FCertified Final StatusAmendment 0004 - Certified Final
2.4.3 Interior Wall Finishes
Apply interior wall color to the entire wall surface, including reveals, vertical furred spaces and columns, grilles, diffusers, electrical and access panels, and piping and conduit adjacent to wall surfaces unless otherwise specified. Paint items not specified in other paragraphs to match adjacent wall surface. Provide wall materials to match the colors listed below.
2.4.3.1 Paint
PA-1 - Sherwin Williams, Color: SW7035 Aesthetic White.
PA-3 - Sherwin Williams, Color: SW7604 Smoky Blue.
PA-4 - Sherwin Williams, Color: SW7017 Dorian Gray.
2.4.3.2 Ceramic Tile
TLC-1 - Daltile, Pattern: Color Wheel Linear, Color: White 0100 6 inch by 18 inch Tile, Installation: Vertical Straight.
2.4.3.3 Grout
GR-2 - Mapei, Color: 27 Silver.
2.4.3.4 Resinous Wall Coating
RES-3 - Stonhard, Style: Stonglaze, Color: Ash Gray.
2.4.3.5 Metal Liner Panels
MLP-1 - Manufacturer's Standard White.
2.4.4 Interior Ceiling Finishes
Apply ceiling colors to ceiling surfaces including soffits, furred down areas, grilles, diffusers, registers, and access panels. In addition, apply ceiling color to joists, underside of roof deck, and conduit and piping where joists and deck are exposed and required to be painted.
Provide ceiling materials to match the colors listed below.
2.4.4.1 Acoustical Tile and Grid
ACT-1 - Armstrong Ceilings, 3354 Optima Square Tegular, 24 inch by 24 inch, Color: White, Grid: 15/16 inch.
2.4.4.2 Paint (Ceilings)
PA-2 - Sherwin Williams, Color: SW7007 Ceiling Bright White.
2.4.4.3 Paint (Soffits)
PA-2 - Sherwin Williams, Color: SW7007 Ceiling Bright White.
2.4.4.4 Metal Deck
PA-2 - Sherwin Williams, Color: SW7007 Ceiling Bright White.
SECTION 09 06 00 Page 5 ent 0004 - Certified Certified Final StatusAmendment 0004 - Certified Final
2.4.4.5 Structural Framing
PA-2 - Sherwin Williams, Color: SW7007 Ceiling Bright White.
2.4.5 Interior Trim
Provide interior trim to match the colors listed below.
2.4.5.1 Steel Doors
PA-5 - Sherwin Williams, Color: SW7069 Iron Ore.
2.4.5.2 Steel Door Frames
PA-5 - Sherwin Williams, Color: SW7069 Iron Ore.
2.4.5.3 Steel Windows (mullion, muntin, sash, trim, and stool)
PA-5 - Sherwin Williams, Color: SW7069 Iron Ore.
2.4.5.4 Fire Extinguisher Cabinets
Brushed Stainless Steel.
2.4.5.5 Handrails
PA-5 - Sherwin Williams, Color: SW7069 Iron Ore.
2.4.5.6 Guardrails
PA-5 - Sherwin Williams, Color: SW7069 Iron Ore.
2.4.5.7 Ladders
PA-5 - Sherwin Williams, Color: SW7069 Iron Ore.
2.4.5.8 Bollards
Interior - Safety Yellow.
2.4.6 Interior Window Treatment
Provide window treatments to match the colors listed below.
2.4.6.1 Window Shades
RS-1 - Mechoshade, Ecoveil 1550 Series, 3 percent Open, Color:
1566 Eggshell.
2.4.7 Interior Miscellaneous
Provide miscellaneous items to match the colors listed below.
2.4.7.1 Toilet Partitions and Urinal Screens
TP-1 - ASI Global Partitions, Color-Thru Solid Phenolic, Color:
Fog 3450C.
SECTION 09 06 00 Page 6 ment 0004 - Certified Certified Final StatusAmendment 0004 - Certified Final
2.4.7.2 Plastic Laminate
PLAM-1 - Formica, Color: 3245-58 Smoke, Finish: Matte.
2.4.7.3 Solid Surfacing Material
SSF-1 - Formica, Everform, Color: 733 Mirage.
2.4.7.4 Window Sills (Solid Surface)
SSF-1 - Formica, Everform, Color: 733 Mirage.
2.4.7.5 Corner Guards
CG-1 - Construction Specialties, Color: 933 Mission White.
CG-2 - Construction Specialties, CO-8, Color: #4 Satin Finish.
2.4.7.6 Signage Message Color
To Match: Sherwin Williams, Color: SW 7069 Iron Ore.
2.4.7.7 Signage Background Color To Match
To Match: Sherwin Williams, Color: SW 7035 Aesthetic White.
2.4.7.8 Wall Switch Handles and Standard Receptacle Bodies
Manufacturer's Standard Grey.
2.4.7.9 Electrical Device Cover Plates
Brushed Stainless Steel.
2.4.7.10 Electrical Panels
Manufacturer's Standard Grey.
2.4.7.11 Shower Curtain
Manufacturer's Standard White Vinyl.
2.4.7.12 Shower Wall
SSF-2 - Manufacturer's Standard White.
2.5 PLACEMENT SCHEDULE
Placement of color to be in accordance with the drawings.
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 09 06 00 Page 7 ment 0004 - Certified Certified Final StatusAmendment 0004 - Certified Final
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 09 06 00 Page 8
SECTION 09 90 00
PAINTS AND COATINGS
02/21
Amendment 0004
PART 1 GENERAL
1.1 RELATED REQUIREMENTS
1.1.1 Painting Included
Where a space or surface is indicated to be painted, include the following unless indicated otherwise.
a. Surfaces behind portable objects and surface mounted articles readily detachable by removal of fasteners, such as screws and bolts.
b. New factory finished surfaces that require identification or color coding and factory finished surfaces that are damaged during performance of the work.
c. Existing coated surfaces that are damaged during performance of the work.
1.1.1.1 Exterior Painting
Includes new surfaces of the building and appurtenances. Also included are existing coated surfaces made bare by cleaning operations.
1.1.1.2 Interior Painting
Includes new surfaces of the building and appurtenances as indicated and existing coated surfaces made bare by cleaning operations. Where a space or surface is indicated to be painted, include the following items, unless indicated otherwise.
a. Exposed columns, girders, beams, joists, and metal deck; and
b. Other contiguous surfaces.
1.1.2 Painting Excluded
Do not paint the following unless indicated otherwise.
a. Surfaces concealed and made inaccessible by panelboards, fixed ductwork, machinery, and equipment fixed in place.
b. Surfaces in concealed spaces. Concealed spaces are defined as enclosed spaces above suspended ceilings, furred spaces, attic spaces, crawl spaces, elevator shafts and chases.
c. Steel to be embedded in concrete.
d. Copper, stainless steel, aluminum, anodized aluminum, brass, and lead except existing coated surfaces.
e. Hardware, fittings, and other factory finished items.
SECTION 09 90 00 Page 1
f. Do not paint surfaces in the following areas: As indicated on drawings.
1.1.3 Mechanical and Electrical Painting
Includes field coating of interior and exterior new surfaces.
a. Where a space or surface is indicated to be painted, include the following items unless indicated otherwise.
(1) Exposed piping, conduit, and ductwork;
(2) Supports, hangers, air grilles, and registers;
(3) Miscellaneous metalwork and insulation coverings.
b. Do not paint the following, unless indicated otherwise:
(1) New zinc-coated, aluminum, and copper surfaces under insulation
(2) New aluminum jacket on piping
(3) New interior ferrous piping under insulation.
1.1.3.1 Fire Extinguishing Sprinkler Systems
Clean, pretreat, prime, and paint new fire extinguishing sprinkler systems including valves, piping, conduit, hangers, supports, miscellaneous metalwork, and accessories. Apply coatings to clean, dry surfaces, using clean brushes.
1.1.4 Miscellaneous Painting
1.1.4.1 Lettering Building
Paint as identified on the drawings water-type decalcomania, finished with a protective coating of spar varnish.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONFERENCE OF GOVERNMENTAL INDUSTRIAL HYGIENISTS (ACGIH)
ACGIH 0100 (2017; Suppl 2020) Documentation of the Threshold Limit Values and Biological Exposure Indices
ASTM INTERNATIONAL (ASTM)
ASTM D523 (2014; R 2018) Standard Test Method for Specular Gloss
ASTM D4263 (1983; R 2018) Standard Test Method for Indicating Moisture in Concrete by the Plastic Sheet Method
SECTION 09 90 00 Page 2
ASTM D4444 (2013; R 2018) Standard Test Method for Laboratory Standardization and Calibration of Hand-Held Moisture Meters
ASTM D6386 (2016a) Standard Practice for Preparation of Zinc (Hot-Dip Galvanized) Coated Iron and Steel Product and Hardware Surfaces for Painting
ASTM F1869 (2022) Standard Test Method for Measuring Moisture Vapor Emission Rate of Concrete Subfloor Using Anhydrous Calcium Chloride
CENTERS FOR DISEASE CONTROL AND PREVENTION (CDC)
Intelligence Bulletin 65 (2013) Occupational Exposure to Carbon Nanotubes and Nanofibers
MASTER PAINTERS INSTITUTE (MPI)
MPI 3 (2016) Primer, Alkali Resistant, Water Based
MPI 4 (2016) Interior/Exterior Latex Block Filler
MPI 9 (2016) Alkyd, Exterior Gloss (MPI Gloss Level 6)
MPI 38 (2016) Elastomeric Coating, Exterior, Water Based, Non-Flat
MPI 39 (2018) Primer, Latex, for Interior Wood
MPI 50 (2015) Primer Sealer, Latex, Interior
MPI 51 (2016) Alkyd, Interior, (MPI Gloss Level 3)2
MPI 72 (2016) Polyurethane, Two-Component, Pigmented, Gloss (MPI Gloss Level 6-7)
MPI 76 (2016) Primer, Alkyd, Quick Dry, for Metal
MPI 77 (2015) Epoxy, Gloss
MPI 79 (2016) Primer, Alkyd, Anti-Corrosive for Metal
MPI 95 (2015) Primer, Quick Dry, for Aluminum
MPI 101 (2016) Primer, Epoxy, Anti-Corrosive, for Metal
MPI 107 (2016) Primer, Rust-Inhibitive, Water Based
MPI 108 (2015) Epoxy, High Build, Low Gloss
MPI 113 (2018) Elastomeric, Pigmented, Exterior, SECTION 09 90 00 Page 3
Water Based, Flat
MPI 116 (2012) Block Filler, Epoxy
MPI 134 (2015) Primer, Galvanized, Water Based
MPI 138 (2016) Latex, Interior, High Performance Architectural, (MPI Gloss Level 2)
MPI 139 (2016) Latex, Interior, High Performance Architectural, (MPI Gloss Level 3)
MPI 140 (2016) Latex, Interior, High Performance Architectural, (MPI Gloss Level 4)
MPI 141 (2016) Latex, Interior, High Performance Architectural, Semi-Gloss (MPI Gloss Level 5)
MPI 144 (2016) Latex, Interior, Institutional Low Odor/VOC, (MPI Gloss Level 2)
MPI 145 (2016) Latex, Interior, Institutional Low Odor/VOC, ( MPI Gloss Level 3)
MPI 146 (2016) Latex, Interior, Institutional Low Odor/VOC, (MPI Gloss Level 4)
MPI 147 (May 2016) Latex, Interior, Institutional Low Odor/VOC, Semi-Gloss (MPI Gloss Level 5)
MPI 153 (2016) Light Industrial Coating, Interior, Water Based, Semi-Gloss (MPI Gloss Level 5)
MPI 154 (2016) Light Industrial Coating, Interior, Water Based, Gloss (MPI Gloss Level 6)
MPI 161 (2016) Light Industrial Coating, Exterior, Water Based ( MPI Gloss Level 3)
MPI 163 (2016) Light Industrial Coating, Exterior, Water Based, Semi-Gloss (MPI Gloss Level 5)
MPI 164 (2016) Light Industrial Coating, Exterior, Water Based, Gloss (MPI Gloss Level 6)
MPI ASM (2019) Architectural Painting Specification Manual
MPI GPS-1-14 (2014) Green Performance Standard GPS-1-14
MPI GPS-2-14 (2014) Green Performance Standard GPS-2-14
MPI MRM (2015) Maintenance Repainting Manual
SOCIETY FOR PROTECTIVE COATINGS (SSPC)
SSPC 7/NACE No.4 (2007) Brush-Off Blast Cleaning
SECTION 09 90 00 Page 4
SSPC Glossary (2011) SSPC Protective Coatings Glossary
SSPC PA 1 (2016) Shop, Field, and Maintenance Coating of Metals
Amendment 0004************************************************************
SSPC QP 1 (2019) Standard Procedure for Evaluating the Qualifications of Industrial/Marine Painting Contractors (Field Application to Complex Industrial Steel Structures and Other Metal Components)
SSPC QP 3 (2010) Standard Procedure for Evaluating Qualifications of Shop Painting Applicators
************************************************************Amendment 0004
SSPC SP 1 (2015) Solvent Cleaning
SSPC SP 2 (2018) Hand Tool Cleaning
SSPC SP 3 (2018) Power Tool Cleaning
SSPC SP 6/NACE No.3 (2007) Commercial Blast Cleaning
SSPC SP 10/NACE No. 2 (2015) Near-White Blast Cleaning
SSPC VIS 1 (2002; E 2004) Guide and Reference Photographs for Steel Surfaces Prepared by Dry Abrasive Blast Cleaning
SSPC VIS 3 (2004) Guide and Reference Photographs for Steel Surfaces Prepared by Hand and Power Tool Cleaning
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual
U.S. DEPARTMENT OF DEFENSE (DOD)
MIL-STD-101 (2014; Rev C) Color Code for Pipelines and for Compressed Gas Cylinders
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FED-STD-313 (2018) Material Safety Data, Transportation Data and Disposal Data for Hazardous Materials Furnished to Government Activities
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910.1000 Air Contaminants
SECTION 09 90 00 Page 5
1.3 DEFINITIONS
1.3.1 Qualification Testing
Qualification testing is the performance of all test requirements listed in the product specification. This testing is accomplished by MPI to qualify each product for the MPI Approved Product List, and may also be accomplished by Contractor's third-party testing lab if an alternative to Batch Quality Conformance Testing by MPI is desired.
1.3.2 Batch Quality Conformance Testing
Batch quality conformance testing determines that the product provided is the same as the product qualified to the appropriate product specification. This testing must be accomplished by an MPI testing lab.
1.3.3 Coating
SSPC Glossary ; (1) A liquid, liquefiable, or mastic composition that is converted to a solid protective, decorative, or functional adherent film after application as a thin layer; (2) Generic term for paint, lacquer, enamel.
1.3.4 DFT or dft
Dry film thickness, the film thickness of the fully cured, dry paint or coating.
1.3.5 DSD
Degree of Surface Degradation, the MPI system of defining degree of surface degradation. Five levels are generically defined under the Assessment sections in the MPI MRM, MPI Maintenance Repainting Manual.
1.3.6 EXT
MPI short term designation for an exterior coating system.
1.3.7 INT
MPI short term designation for an interior coating system.
1.3.8 Loose Paint
Paint or coating that can be removed with a dull putty knife.
1.3.9 mil / mils
The English measurement for 0.001 in or one one-thousandth of an inch.
1.3.10 MPI Gloss Levels
MPI system of defining gloss. Seven gloss levels (G1 to G7) are generically defined under the Evaluation sections of the MPI Manuals.
Traditionally, Flat refers to G1/G2, Eggshell refers to G3, Semigloss refers to G5, and Gloss refers to G6.
Gloss levels are defined by MPI as follows:
SECTION 09 90 00 Page 6
Gloss Level Description Units at 60 degree angle
Units at 80 degree angle
G1 Matte or Flat 0 to 5 10 max
G2 Velvet 0 to 10 10 to 35
G3 Eggshell 10 to 25 10 to 35
G4 Satin 20 to 35 35 min
G5 Semi-Gloss 35 to 70
G6 Gloss 70 to 85
G7 High Gloss
Gloss is tested in accordance with ASTM D523. Historically, the Government has used Flat (G1 / G2), Eggshell (G3), Semi-Gloss (G5), and Gloss (G6).
1.3.11 MPI System Number
The MPI coating system number in each MPI Division found in either the MPI Architectural Painting Specification Manual or the Maintenance Repainting Manual and defined as an exterior (EXT/REX) or interior system (INT/RIN).
1.3.12 Paint
SSPC Glossary ; (1) Any pigmented liquid, liquefiable, or mastic composition designed for application to a substrate in a thin layer that is converted to an opaque solid film after application. Used for protection, decoration, identification, or to serve some other functional purposes; (2) Application of a coating material.
1.3.13 REX
MPI short term designation for an exterior coating system used in repainting projects or over existing coating systems.
1.3.14 RIN
MPI short term designation for an interior coating system used in repainting projects or over existing coating systems.
1.4 SCHEDULING
Allow paint, polyurethane, varnish, and wood stain installations to cure prior to the installation of materials that adsorb VOCs, including carpets, textiles, unprimed gypsum wallboard, acoustical ceiling panels.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SECTION 09 90 00 Page 7
Samples of specified materials may be taken and tested for compliance with specification requirements.
SD-02 Shop Drawings
Piping Identification
SD-03 Product Data
Coating; G
Product Data Sheets
SD-04 Samples
Color; G
SD-07 Certificates
Qualification Testing laboratory for coatings; G
Indoor Air Quality for Paints and Primers
Indoor Air Quality for Consolidated Latex Paints
SD-08 Manufacturer's Instructions
Mixing
Manufacturer's Safety Data Sheets
SD-10 Operation and Maintenance Data
Coatings, Data Package 1; G
1.6 QUALITY ASSURANCE
1.6.1 Regulatory Requirements
1.6.1.1 Environmental Protection
In addition to requirements specified elsewhere for environmental protection, provide coating materials that conform to the restrictions of the local Air Pollution Control District and regional jurisdiction.
Notify Contracting Officer of any paint specified herein which fails to conform.
1.6.1.2 Lead Content
Do not use coatings having a lead content over 0.06 percent by weight of nonvolatile content.
1.6.1.3 Chromate Content
Do not use coatings containing zinc-chromate or strontium-chromate.
SECTION 09 90 00 Page 8
1.6.1.4 Asbestos Content
Provide asbestos-free materials.
1.6.1.5 Mercury Content
Provide materials free of mercury or mercury compounds.
1.6.1.6 Silica
Provide abrasive blast media containing no free crystalline silica.
1.6.1.7 Human Carcinogens
Provide materials that do not contain ACGIH 0100 confirmed human carcinogens (A1) or suspected human carcinogens (A2).
1.6.1.8 Carbon Based Fibers / Tubes
Materials must not contain carbon based fibers such as carbon nanotubes or carbon nanofibers. Intelligence Bulletin 65 ranks toxicity of carbon nanotubes on a par with asbestos.
Amendment 0004************************************************************
1.6.2 Deleted
1.6.3 SSPC QP 1 Certification
Contractors that perform surface preparation or coating application on steel substrates must be certified by the Society for Protective Coatings (formerly Steel Structures Painting Council) (SSPC) to the requirements of SSPC QP 1 prior to Contract award, and must remain certified while accomplishing any surface preparation or coating application. If a Contractor's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered. Notify the Contracting Officer of any change in Contractor certification status. Notify the Contracting Officer of all scheduled and unannounced on-site audits from SSPC and furnish a copy of all audit reports.
1.6.4 SSPC QP 3 Certification
Shop application shall have SSPC QP 3 or AISC SPE qualifications. The painting Contractors and painting subcontractors must remain so certified for the duration of the project. If a Contractor's certification expires, the firm will not be allowed to perform any work until the certification is reissued. Requests for extension of time for any delay to the completion of the project due to an inactive certification will not be considered. Notify the Contracting Officer of any change in Contractor certification status. Notify the Contracting Officer of all scheduled and unannounced on-site audits from SSPC and furnish a copy of all audit reports.
************************************************************Amendment 0004
1.6.5 Approved Products List
The current MPI, "Approved Product List" which lists paint by brand, label, product name and product code as of the date of Contract award, will be used to determine compliance with the submittal requirements of this specification. The Contractor may choose to use a subsequent MPI
SECTION 09 90 00 Page 9
"Approved Product List", however, only one list may be used for the entire Contract and each coating system is to be from a single manufacturer.
Provide all coats on a particular substrate from a single manufacturer.
No variation from the MPI Approved Products List is acceptable.
1.6.6 Paints and Coatings Indoor Air Quality Certifications
Provide paint and coating products certified to meet indoor air quality requirements by MPI GPS-1-14 , MPI GPS-2-14 or provide certification by other third-party programs. Provide current product certification documentation from certification body.
Provide certification of Indoor Air Quality for Paints and Primers.
Provide certification of Indoor Air Quality for Consolidated Latex Paints.
Submit required indoor air quality certifications in one submittal package.
1.6.7 Field Samples and Tests
The Contracting Officer may choose up to two coatings that have been delivered to the site to be tested at no cost to the Government. Take samples of each chosen product as specified in the paragraph SAMPLING PROCEDURE. Test each chosen product as specified in the paragraph TESTING PROCEDURE. Remove products from the job site which do not conform, and replace with new products that conform to the referenced specification.
Test replacement products that failed initial testing as specified in the paragraph TESTING PROCEDURE at no cost to the Government.
1.6.7.1 Sampling Procedure
Select paint at random from the products that have been delivered to the job site for sample testing. The Contractor must provide one quart samples of the selected paint materials. Take samples in the presence of the Contracting Officer, and label, and identify each sample. Provide labels in accordance with the paragraph PACKAGING, LABELING, AND STORAGE.
1.6.7.2 Testing Procedure
Provide Batch Quality Conformance Testing for specified products, as defined by and performed by MPI.