Q A Round 6.pdf

PDF 96 KB Posted

Attached to
Repair Squadron Operations, Bldg. 369
Solicitation number
W912PQ-11-B-0002
Issued by

About this file

Q A Round 6

View the file

Other files

File Type Posted
W912PQ-11-C-0020.pdf PDF
Q A Bid Opening.pdf PDF
Bid Opening - 02 June 2011.pdf PDF
Q A Round 5.pdf PDF
Amendment 2.pdf PDF
Q A Round 4.pdf PDF
W912PQ-11-B-0002-0001.pdf PDF
Q A Round 3.docx DOCX document
Addendum_001_20110517.pdf PDF
AD101.pdf PDF
AD102.pdf PDF
AD201.pdf PDF
A-201.pdf PDF
Q A Round 2.docx DOCX document
Q A Round 1.docx DOCX document
106 Pre Bid Conference 11 May 2011.pptx PPTX presentation
attendance sheet.pdf PDF
LEED Checklist.pdf PDF
Final Specifications.pdf PDF
Telecommunications.zip ZIP file
Mechanical.zip ZIP file
Structural.zip ZIP file
W912PQ-11-B-0002 Repair Squadron Operations Bldg 369.pdf PDF
General.zip ZIP file
Electrical.zip ZIP file
Fire_Protection.zip ZIP file
Existing_Dwgs_Reference_Only.zip ZIP file
Landscaping.zip ZIP file
Civil.zip ZIP file
Architectural.zip ZIP file
Plumbing.zip ZIP file
Wage Determinations - April 22 2011 - Mod 14.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31 May 2011

Invitation for Bid (IFB) W912PQ-11-B-0002 - Squadron Operations

Building #369

Pre-Bid Questions & Answers (6):

64. Can you tell us how old the existing electrical transformer is? The age of the transformer will help determine whether or not it may carry PCB’s.

Answer: The existing transformer is a brand new one installed in 2010. It will have to be replaced under the new project.

65. In lieu of deflection runner and clips may we substitute a slotted deflection top track similar to Marino-Ware slotted slip track?

Answer: HEAD OF WALL DEFLECTION, We see no issue with substituting this slotted deflection channel as long as it is properly fire-stopped (slots allow air movement) and/or sound-proofed as required at certain partition types.

66. Detail 4-A503 indicates to ”provide and install ceiling bracing per manufacture for seismic category B” Detail 8-A503 indicates attachment clips and stabilizer bars at perimeter.

Armstrong and the IBC says related to Category B, “ceiling installation should conform to basic minimums established in ASTM C636

Answer: ACOUSTIC CEILING INSTALLATION, ASTM C636 should be followed for seismic zone 'B' and thus no extra bracing is required.