Q A Round 2.docx

DOCX document 16 KB Posted

Attached to
Repair Squadron Operations, Bldg. 369
Solicitation number
W912PQ-11-B-0002
Issued by

About this file

Prebid Questions Answers 2 dated 17 May 11

View the file

Other files

File Type Posted
W912PQ-11-C-0020.pdf PDF
Q A Bid Opening.pdf PDF
Bid Opening - 02 June 2011.pdf PDF
Q A Round 6.pdf PDF
Q A Round 5.pdf PDF
Amendment 2.pdf PDF
Q A Round 4.pdf PDF
W912PQ-11-B-0002-0001.pdf PDF
Q A Round 3.docx DOCX document
Addendum_001_20110517.pdf PDF
AD101.pdf PDF
AD102.pdf PDF
AD201.pdf PDF
A-201.pdf PDF
Q A Round 1.docx DOCX document
106 Pre Bid Conference 11 May 2011.pptx PPTX presentation
attendance sheet.pdf PDF
LEED Checklist.pdf PDF
Final Specifications.pdf PDF
Telecommunications.zip ZIP file
Mechanical.zip ZIP file
Structural.zip ZIP file
W912PQ-11-B-0002 Repair Squadron Operations Bldg 369.pdf PDF
General.zip ZIP file
Electrical.zip ZIP file
Fire_Protection.zip ZIP file
Existing_Dwgs_Reference_Only.zip ZIP file
Landscaping.zip ZIP file
Civil.zip ZIP file
Architectural.zip ZIP file
Plumbing.zip ZIP file
Wage Determinations - April 22 2011 - Mod 14.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

17 May 2011

Invitation for Bid (IFB) W912PQ-11-B-0002 - Squadron Operations Building #369

Pre-Bid Questions & Answers (2):

14. Who is responsible for the fire service line and Back flow device?

a. Answer: The successful contractor

15. Is filing with the local fire marshal required? or is the National Guard reviewing and approving drawings and performing their own final inspections?

a. The local Fire Marshall, Base Fire Marshall, the Engineer of Record, and the National Guard will be reviewing and approving the fire sprinkler system shop drawings and calculations.

16. Is there any area that might require Galvanized pipe and or explosion proof components?

a. No, not for the fire sprinkler system. See the design documents for the specifications on other systems in the building.

17. A flow test would help to determine pipe sizing and the possibility of a fire pump. Is, or will there be a test performed by others before our bid is due?

a. Answer: Yes a flow test was performed, see drawing notes on FX101.

18. Are the fire sprinkler sub contractors required to obtain any bonds. If so, please advise which one and the amount. Bid Bond, Performance Bond.

a. Answer: The Guard is requiring from only the Prime Contractor the bid, performance, and payment bonds.

19. Please confirm the scope in this bid solicitation for work related to the radio tower structure. Please confirm any scope for communication wiring or any other wiring structures associated with it?

a. Answer: Antenna tower and all associated hardware & cabling are to be removed and disposed by the General Contractor. This scope of work will be spelled out on a revised drawing sheet AD101 to be issued this week which will be the controlling contract document for work on the tower.

20. Please confirm there is no scope for communication wiring and devices throughout the building? Only raceways to be provided in locations indicated on the electrical drawings?

a. Answer: The complete scope of Communications is described in the Telecommunications part of the drawings and specifications. See Drawings T-001 through T-601 of the Design Documents.

21. Please confirm the scope for this contract in rooms 171 & 162 ?

a. Answer: The detailed scope of work in rooms 162 & 171 is included in the Design Documents.