Addendum_001_20110517.pdf

PDF 13 KB Posted

Attached to
Repair Squadron Operations, Bldg. 369
Solicitation number
W912PQ-11-B-0002
Issued by

About this file

Addendum to Drawings Specifications 1

View the file

Other files

File Type Posted
W912PQ-11-C-0020.pdf PDF
Q A Bid Opening.pdf PDF
Bid Opening - 02 June 2011.pdf PDF
Q A Round 6.pdf PDF
Q A Round 5.pdf PDF
Amendment 2.pdf PDF
Q A Round 4.pdf PDF
W912PQ-11-B-0002-0001.pdf PDF
Q A Round 3.docx DOCX document
AD101.pdf PDF
AD102.pdf PDF
AD201.pdf PDF
A-201.pdf PDF
Q A Round 2.docx DOCX document
Q A Round 1.docx DOCX document
106 Pre Bid Conference 11 May 2011.pptx PPTX presentation
attendance sheet.pdf PDF
LEED Checklist.pdf PDF
Final Specifications.pdf PDF
Telecommunications.zip ZIP file
Mechanical.zip ZIP file
Structural.zip ZIP file
W912PQ-11-B-0002 Repair Squadron Operations Bldg 369.pdf PDF
General.zip ZIP file
Electrical.zip ZIP file
Fire_Protection.zip ZIP file
Existing_Dwgs_Reference_Only.zip ZIP file
Landscaping.zip ZIP file
Civil.zip ZIP file
Architectural.zip ZIP file
Plumbing.zip ZIP file
Wage Determinations - April 22 2011 - Mod 14.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Squadron Operations Building 369 New York Air National Guard Project Number WKVB000617

TBC Project No. 6150930307 AMENDMENT 001

AMENDMENT 001

May 17, 2011

This Amendment forms a part of the Contract Documents and modifies the original Bidding Documents and previous Amendments as noted below. Acknowledge receipt of this Amendment in the space provided in the Bid Form. Failure to do so may subject Bidder to disqualification.

This Amendment consists of 5 page(s) including all attachments noted herein.

MODIFICATIONS TO PREVIOUS ADDENDA:

Not applicable.

MODIFICATIONS TO SPECIFICATIONS:

Not applicable.

MODIFICATIONS TO DRAWINGS:

1. Revise drawing AD101 as follows:

a. Revise Keynotes 4 & 5 to omit reference to submitting salvaged items to Contracting Officer.

b. Revise Keynote 24 to indicate tower and all associated hardware and cabling are to be re-moved and disposed by the General Contractor.

c. Revise Keynotes 27 through 33, indicate as “NOT USED”; removed items from floor plan.

d. Revise Keynote 36 to omit reference to salvaging benches.

e. Revise Keynote 43, indicate as “NOT USED”; removed items from floor plan.

f. Revise Note in its entirety to read: “FOR ALL ITEMS NOTED TO BE SALVAGED, CONTRACTOR IS RESPONSIBLE FOR:

• PROTECTING SALVAGED ITEMS IN PLACE DURING CONSTRUCTION, OR

• TEMPORARILY RELOCATING SALVAGED ITEMS AND PROTECTING THEM INSIDE

THE FACILITY UNTIL REINSTALLED, OR

• STORING SALVAGED ITEMS IN A TRAILER ON BASE NEXT TO THE FACILITY

DURING RENOVATION, OR

• STORING SALVAGED ITEMS OFF BASE AT A FACILITY PROVIDED BY THE

GENERAL CONTRACTOR.

THE GENERAL CONTRACTOR WILL BE RESPONSIBLE FOR THE CONDITION OF ALL

PROTECTED/STORED EQUIPMENT. DAMAGED EQUIPMENT WILL BE REPLACED WITH

NEW BY THE GENERAL CONTRACTOR.”

g. Added new Note to read “UNLESS ITEMS ARE TO BE SALVAGED, ALL REMOVED ITEMS

ARE TO BE DISPOSED BY THE GENERAL CONTRACTOR.”

2. Revise drawing AD102 as follows:

a. Revise Keynote 8 to indicate tower and all associated hardware and cabling are to be removed and disposed by the General Contractor.

3. Revise drawing AD201 as follows:

a. Revise Keynote 9 to indicate tower and all associated hardware and cabling are to be removed and disposed by the General Contractor.

4. Revise drawing A-201 as follows:

a. Revise Keynote 14 to indicate as “NOT USED”; removed tower from elevations.

ATTACHMENTS:

1. Drawings AD101, AD102, AD201, A-201

END OF AMENDMENT 001