W912P5-14-R-0003TSpecs.pdf

PDF 2 MB Posted

Attached to
Center Hill - Auxiliary Dam Reinforcing Berm and Left Rim Stabilization
Solicitation number
W912P5-14-R-0003
Issued by

About this file

Technical Specifications

View the file

Other files

File Type Posted
W912P5-14-R-0003-0008.pdf PDF
W912P514R0003PlansAm8.pdf PDF
W912P5-14-R-0003TspecsAm8Pgs.pdf PDF
W912P5-14-R-0003-0007.pdf PDF
W912P5-14-R-0003TspecsAm7Pgs.pdf PDF
W912P514R0003PlansAm6.pdf PDF
W912P5-14-R-0003TspecsAm6Pgs.pdf PDF
W912P5-14-R-0003-0006.pdf PDF
W912P5-14-R-0003TSpecsAm5Pgs.pdf PDF
As-BuiltDrawings-ForInfoOnly.pdf PDF
W912P5-14-R-0003-0005.pdf PDF
W912P5-14-R-0003-0004.pdf PDF
W912P514R0003PlansAm3.pdf PDF
W912P5-14-R-0003-0003.pdf PDF
W912P514R0003TSpecsAm3Pgs.pdf PDF
W912P514R0003PlansDGN08.zip ZIP file
W912P5-14-R-0003Plans.pdf PDF
W912P5-14-R-0003TSpecsAppB4of5.pdf PDF
W912P5-14-R-0003TSpecsAppB5of5.pdf PDF
W912P5-14-R-0003TSpecsAppB3of5.pdf PDF
W912P514R0003TspecsAm2Pgs.pdf PDF
W912P5-14-R-0003TSpecsAm1Pgs.pdf PDF
W912P5-14-R-0003TSpecsAppendixA.pdf PDF
W912P514R0003PlansDGN02.zip ZIP file
W912P514R0003PlansDGN04.zip ZIP file
W912P514R0003PlansDGN03.zip ZIP file
W912P514R0003PlansDGN05.zip ZIP file
W912P514R0003PlansDGN07.zip ZIP file
W912P514R0003PlansDGN10.zip ZIP file
Q4-RCC-G-08.1.pdf PDF
W912P5-14-R-0003TSpecsAppB2of5.pdf PDF
W912P5-14-R-0003-0002.pdf PDF
W912P5-14-R-0003.pdf PDF
W912P5-14-R-0003TSpecsAppB1of5.pdf PDF
W912P514R0003PlansDGN01.zip ZIP file
W912P514R0003PlansDGN09.zip ZIP file
W912P514R0003PlansDGN06.zip ZIP file
W912P5-14-R-0003-0001.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. W912P5-14-R-0003

US Army Corps Of Engineers Nashville District

AUXILIARY DAM REINFORCING BERM

AND LEFT RIM STABILIZATION

Center Hill Reservoir Project Cumberland River Watershed Caney Fork River DeKalb County, Tennessee

CERTIFIED FINAL DOCUMENTS - RTA

TECHNICAL SPECIFICATIONS

September 2015

THIS PAGE INTENTIONALLY LEFT BLANK

FOR DUPLEX PRINTING

Auxiliary Dam Reinforcing Berm Center Hill Reservoir and Left Rim Stabilization DeKalb County, Tennessee

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 22 00 MEASUREMENT AND PAYMENT

01 31 00 DATA MANAGEMENT

01 32 01 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01 QUALITY CONTROL

01 45 02 QUALITY CONTROL SYSTEM (QCS)

01 50 02 TEMPORARY CONSTRUCTION FACILITIES

01 55 26 MAINTENANCE AND CONTROL OF TRAFFIC

01 57 20 ENVIRONMENTAL PROTECTION

01 57 23 STORM WATER

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 32 00 SUBSURFACE DRILLING, SAMPLING, AND TESTING

DIVISION 03 - CONCRETE

03 15 00 CONCRETE ACCESSORIES

03 20 00 CONCRETE REINFORCING

03 37 13 SHOTCRETE

03 37 23 CONCRETE

DIVISION 05 - METALS

05 50 15 CIVIL WORKS FABRICATIONS

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

DIVISION 26 - ELECTRICAL

26 05 19 INSULATED WIRE AND CABLE

26 11 16 MVS MEDIUM VOLTAGE LOAD INTERRUPTER FUSIBLE SWITCH

26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS

26 20 00 INTERIOR ELECTRICAL DISTRIBUTION SYSTEM

26 32 33.10 UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 - COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 21 10 FIBER OPTIC DATA TRANSMISSION SYSTEM

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

PROJECT TABLE OF CONTENTS Page 1 W912P5-14-R-0003

28 16 01 SMALL INTRUSION DETECTION SYSTEM

28 23 23 CLOSED CIRCUIT TELEVISION SYSTEMS

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 05 19 NONWOVEN GEOTEXTILE

31 10 00 CLEARING FOR CIVIL WORKS

31 23 05 EXCAVATION

31 23 06 BLASTING

31 23 07 ROCK SLOPE SCALING

31 32 23 DRILLING AND GROUTING

31 60 00 FOUNDATION PREPARATION

31 68 13 REINFORCEMENT FOR SLOPE PROTECTION

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 16 HAUL AND ACCESS ROADS

32 31 13 CHAIN LINK FENCES AND GATES

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 70 02 EXTERIOR AND UNDERGROUND ELECTRICAL DISTRIBUTION SYSTEM

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

35 31 19 STONE PROTECTION

APPENDIX A - FORMS AND ATTACHMENTS (Separate Volume)

PROJECT TABLE OF CONTENTS Page 2

-- End of Project Table of Contents --

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 SCOPE

1.2 REFERENCES

1.2.1 Standard Specifications (TDOT Std Specs)

1.2.1.1 Standard Specifications

1.2.1.2 Non-Applicable Provisions of the Standard Specifications

1.3 MEASUREMENT AND PAYMENT

1.4 INITIAL SURVEY REQUIREMENTS

1.5 COORDINATION WITH OTHER CONTRACTORS

1.6 COORDINATION CONFERENCES

1.7 STAGING AND AREA USE PLAN

1.8 PROJECT SIGNS

1.9 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER AND POOL FLUCTUATIONS

1.9.1 General

1.9.2 Reservoir Fluctuations

1.9.3 Contract Clauses

1.10 CONSTRUCTION HAZARD COMMUNICATIONS

1.10.1 General

1.10.2 Work Area Hazard Evaluation

1.10.3 Electrical Hazards

1.11 SUBMITTALS

1.12 PARTNERING

1.13 PROJECT SITE SECURITY REQUIREMENTS

1.13.1 Employee Identification and Control Procedure

1.13.2 Pre-Screening Contractor's On-Site Employees

1.13.3 Non-Disclosure of Government Information

1.13.4 Conduct of Contractor Employees

1.13.5 Government Furnished Materials and Equipment

1.13.6 Damage or Loss of Contractor's Supplies and Property

1.14 EVALUATION OF CONTRACTOR PERFORMANCE

1.15 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 FIELD SURVEYS

3.1.1 Survey Requirements

3.1.2 Disposal/Borrow Area Survey

3.1.3 As-Found Survey

3.1.4 Final Survey

3.2 AVAILABILITY AND USE OF UTILITY SERVICES

3.2.1 Contractor Responsibilities

3.2.2 Alterations to Utilities

3.2.3 Interruptions of Utilities

SECTION 01 00 00 Page 1

-- End of Section Table of Contents --

SECTION 01 00 00 Page 2

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 SCOPE

This section comprises an explanation of the general contract requirements associated with construction of the Center Hill Roller Compacted Concrete Reinforcing Berm and Left Rim Stabilization in accordance with the contract plans and specifications. This section is not intended to be all encompassing in the descriptions. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and contract drawings. The Contractor shall propose each type of work under the applicable line item. Compensation for any item of work described in the contract documents, but not listed in the price breakout schedule shall be included in the price for the item of work to which it is made subsidiary.

All work shall be completed as specified, detailed and/or in strict accordance with all terms, conditions, general, specific and technical provisions, contained herein or incorporated by reference. Incorporation by reference shall include any and all mandatory provisions required by the Federal Acquisition Regulation (FAR) whether it is referenced or not referenced, current at time of award.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 310-1-6a (2006) Sign Standards Manual, VOL 1

EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1926.59 Hazard Communication

TENNESSEE DEPARTMENT OF TRANSPORTATION (TDOT)

TDOT Std Specs (2006) Standard Specifications for Road and Bridge Construction, including subsequent Supplementals to date

SECTION 01 00 00 Page 3

1.2.1 Standard Specifications (TDOT Std Specs)

1.2.1.1 Standard Specifications

Where specified, all materials, equipment and workmanship shall be in accordance with the applicable portions of TDOT Std Specs. The words listed below are to be substituted in TDOT Std Specs as indicated:

State to Government Department to Corps of Engineers Bureau to Corps of Engineers Commissioner to Contracting Officer Engineer to Contracting Officer

1.2.1.2 Non-Applicable Provisions of the Standard Specifications

Measurement and payment provisions contained in the Standard Specifications shall be considered non-applicable to this contract with the exception of specific references to specific provisions. Likewise, no contract administration provisions contained in the Standard Specifications apply to this contract. In general, only the technical provisions associated with a Standard Specification reference will apply. The contract clauses, contract administration provisions, and measurement and payment provisions contained in these specifications and contract documents shall govern over any such provisions in the Standard Specifications.

1.3 MEASUREMENT AND PAYMENT

Measurement and payment shall be made as specified in Section 01 22 00

MEASUREMENT AND PAYMENT.

1.4 INITIAL SURVEY REQUIREMENTS

As an initial order of work, the Contractor shall have a Licensed Surveyor establish the baseline(s) for any of the work required in the specifications. Baseline re-establishment will be required prior to starting any site work and stations shall be identified with location and elevation every 100 feet, marked with permanent signage approved by the Contracting Officer. The signs shall have six inch tall lettering. The stationing shall be maintained for the extent of the contract. Surveying shall be incidental to Section 01 22 00 MEASUREMENT AND PAYMENT, paragraph 1.1.2, Miscellaneous Site Work. Original survey notes shall become the property of the Government and delivered to the COR no more than fifteen working days after completion of the survey(s). The Contractor is responsible for coordinating his initial site survey with the Contracting Officer. The Government has survey data available for monumentation. The Contractor may establish his own reference points.

1.5 COORDINATION WITH OTHER CONTRACTORS

Coordination with other Contractors in the area will be required. Another multi-year contract was awarded in 2014 for hydropower machinery rehabilitation and will be executed concurrently with this contract.

Coordination with the hydropower rehab contractor will be required throughout this contract.

1.6 COORDINATION CONFERENCES

Routine coordination conferences will be scheduled by the Contracting

SECTION 01 00 00 Page 4

Officer throughout the life of this contract. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to this construction. The Corps of Engineers and the Contractor will be represented at each of these meetings. Similar information concerning replacement personnel shall be forwarded to the Contracting Officer, should any replacement be required at any time during the life of this contract. Coordination conferences will be scheduled to occur as mutually agreed by the Contractor and by the Contracting Officer, but at a minimum, shall be held monthly.

1.7 STAGING AND AREA USE PLAN

The Contractor shall submit an Area Use Plan to the Contracting Officer, for approval, within thirty (30) days after receipt of the contract Notice to Proceed. The Area Use Plan shall show the following:

a. Location of Contractor offices trailers and sheds

b. Location of all Contractor storage areas

c. Location of Contractor staging and disposal areas

d. Temporary utility tie-ins

e. Location of haul roads

f. Required telephone service and locations

g. Batch plant and concrete materials storage

1.8 PROJECT SIGNS

a. General. The Contractor shall furnish and erect, within 30 days after issue of the Notice to Proceed, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN at the locations directed at the jobsite.

The signs shall be lettered on one side only and shall conform to the requirements of EP 310-1-6a (Section 16), EP 310-1-6b, and to the details and colors shown on the sketches included in Appendix A - FORMS AND ATTACHMENTS. The name of the project shall be as follows:

AUXILIARY DAM REINFORCING BERM

AND LEFT RIM STABILIZATION

b. Materials. The sign shall be constructed with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material. Screws shall be commercial quality and of sizes shown.

c. Painting. The signs and posts shall be given one prime coat and two finish coats of exterior oil paint before lettering. Letters and trim shall be applied to one side only using one coat of enamel of color, style, and size shown.

d. Erection and Maintenance. The signs shall be erected at the designated locations. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs out the life of the contract. The signs shall be maintained in good condition until completion of the contract, shall remain the property of the Contractor, and shall be removed from the site upon final acceptance of the contract work.

SECTION 01 00 00 Page 5

1.9 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER AND POOL FLUCTUATIONS

1.9.1 General

Weather conditions/anticipated adverse weather days are as indicated in Section 00800 SPECIAL CONTRACT REQUIREMENTS. This addresses the contract procedure for the determination of time extensions for unusually severe weather. The Contractor shall understand that there is a potential for unusually severe weather or high reservoir and/or stream levels which may impact construction. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:

a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

b. The unusually severe weather or high pool or stream levels must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

1.9.2 Reservoir Fluctuations

Currently, Center Hill Reservoir is being operated to maintain, as closely as possible, a pool level defined by the Partial Fill 623.5 to 630 (PF

623.5 to 630) Guide Curve shown in the Climate and Hydrology-Hydraulics document, included in Appendix A - FORMS AND ATTACHMENTS of the specifications. However, the Contractor shall not assume that a reservoir elevation of 623.5 to 630 will be maintained during any portion of the project duration. The Contractor is advised reservoir elevations may be lowered below elevation 623.5 if additional concerns regarding project safety arise or may rise above elevation 630 when inflow into the reservoir exceeds project discharge capacity. Changes in the operating criteria will be determined solely by the US Army Corps of Engineers. The Contractor shall refer to Appendix A - FORMS AND ATTACHMENTS for for a discussion of climate in the vicinity of Center Hill dam. Also included in Appendix A are graphs depicting "Percent Time Exceedance" for the pool based on midnight headwater elevations observed during the years prior to implementation of the PF 623.5 to 630 guide curve (historic - 1952-2009).

Similar plots are provided for simulations of reservoir operation using the PF 623.5 to 630 guide curve and assuming varying operational capability to make discharges.

The Contractor should be aware that a flood event at or above 75% of a Probable Maximum Flood will cause the Center Hill reservoir pool to rise above elevation 691.5, the invert of the pilot channel in the fuse plug on top of the saddle dam. Should this occur, the fuse plug is expected to operate as designed, eroding in 30 minutes and passing up to 400,000 cfs of water over the top of the saddle dam and into the auxiliary dam reinforcing berm construction site. This event is estimated to have a 0.05% chance of occurring in any given year corresponding to an average recurrence interval of once every 2,000 years. The Contractor is required to submit an Emergency Evacuation Plan as part of the Governmental Safety Requirements outlined in Specifications Section 01 35 26 and to implement this plan as needed to prevent personal injury or loss of life and to minimize damage to equipment.

In order for the Contracting Officer to award a time extension for

SECTION 01 00 00 Page 6 reservoir fluctuations, each of the following conditions must be satisfied:

a. The pool level at the project site during the contract period must be found to be unusually higher than anticipated; that is, higher than the pool anticipated at the project location used in preparation of project work schedule.

b. An unusually high pool level must actually cause delay to the completion of the project. The delay must be beyond the control and without fault or negligence of the Contractor.

c. Actual high pool level delay days must prevent work on critical construction activities for 50 percent or more of the Contractor's scheduled work day.

d. The number of actual high pool level delay days that meet the criteria in subparagraph c. above will be allowed on a "day-for-day" basis.

1.9.3 Contract Clauses

The Contractor's responsibility for damage to any part of the permanent work shall be as set forth in Contract Clause 52.236-7: PERMITS AND RESPONSIBILITIES. However, if in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flooding, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor will make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or lump sum prices applicable to any part of such work, an equitable adjustment pursuant to Contract Clause 52.243-4: CHANGES, will be made as full compensation for the repairs of that part of the permanent work. Except as herein provided, damage to all work, temporary construction, utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer. The repair shall be completed at the Contractor's expense, regardless of the cause of such damage.

1.10 CONSTRUCTION HAZARD COMMUNICATIONS

1.10.1 General

The Contractor is required to comply with the requirements of the OSHA Hazard Communication Standard (29 CFR 1926.59). This standard is designed to inform workers of safe and appropriate methods of working with hazardous structures in the work area.

1.10.2 Work Area Hazard Evaluation

The Contractor must conduct safety and hazard training to familiarize workers with the potential health or physical hazards of working near the Power Plant Operations, in the galleries, along State Highway 96 and other Contractors and Recreation Users and Facilities. The hazard evaluation consists of an investigation of all the available scientific evidence about the substance. The Contractor is required to assure that all employees (manufacturers/distributors) have performed these evaluations and transmit the required information with any (blasting explosives and other chemical

SECTION 01 00 00 Page 7 hazards) hazardous conditions or a materials being used or stored on the project site. From the hazard evaluation, a substance may be classified as a health hazard, or a physical hazard. These classifications are then further broken down according to type. See the Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS for more specific information.

1.10.3 Electrical Hazards

The Contractor shall be aware of the jobsite to prevent harm to any employees from electrical hazards.

1.11 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Initial Survey of Saddle Dam and RCC Reinforcing Berm; G, DO Initial Survey on the Left Rim; G, DO Initial Disposal Area Survey; G, DO Survey submittal requirements are detailed under paragraph FIELD SURVEYS of this specification section.

Area Use Plan; G Area Use Plan requirements are detailed under paragraph STAGING AND AREA USE PLAN of this specification section.

Verified/Eligible On-Site Employees Employee Identification and Control Procedure; G Investigation Package Foreign Nationals Submittal requirements for site security are detailed in the Nashville District Public Website as described in paragraph

PROJECT SITE SECURITY REQUIREMENTS.

SD-02 Shop Drawings

Progress Survey of Saddle Dam and RCC Reinforcing Berm; G, DO Progress Surveys on the Left Rim; G

SD-11 Closeout Submittals

Final Survey of Saddle Dam and RCC Reinforcing Berm; G, DO Final Survey on the Left Rim; G, DO Final Disposal Area Survey; G

1.12 PARTNERING

In order to most effectively accomplish this contract, the Government urges the Contractor to join with the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship, both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project’s intended results are achieved, within budget and on schedule. This endeavor seeks an environment that nurtures team building, cooperation and trust between

SECTION 01 00 00 Page 8 the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.

The first step in initiating the concept would be a joint project management team "partnering" conference attended by multiple officers from each organization representing management and the key jobsite staff of each entity. The initial conference would be held within the first thirty (30) days following contract award. The Resident Engineer would chair the conference, establish its agenda and distribute minutes of the meeting. A professional facilitator acceptable to both parties would lead the participants of the session, through the steps of team building and the formation of a problem solving mechanism within the group. The conference duration would be no more than one day. Location of the conference would be offsite within a 60 mile radius of the jobsite at a facility which offers conference rooms and food service. All costs in connection with rented facilities and the facilitator would be shared equally by the Government and the Contractor. Each organization would pay other costs of its respective employees attending the conference.

Additional partnering sessions would be held no less than biannually.

Implementation of the partnering concept and philosophy would be an on-going process.

1.13 PROJECT SITE SECURITY REQUIREMENTS

The entire Center Hill Dam area is not open to the public. Depending upon the level of security threat, some Project areas may or may not be open to the Contractor and Contractor employees. The security of the Contractor's property and items furnished under this contract, until items are accepted by the Government, are the Contractor's responsibility whether stored inside or outside the site. Guidance and forms for project site security requirements are available on the Nashville District Public Website:

http://www.lrn.usace.army.mil/BusinessWithUs/ContractSecurityRequirements.aspx

1.13.1 Employee Identification and Control Procedure

An employee identification and control procedure shall be submitted for approval for identification and control of employees entering or leaving the project site. It is expected that this will include a unique photo identification card for each contractor and subcontractor employees working at the Center Hill project site.

1.13.2 Pre-Screening Contractor's On-Site Employees

The Contractor must pre-screen on-site employees using the E-verify Program website (http://www.dhs.gov/E-Verify) to meet the established employment eligibility requirements. The Contractor must ensure that each on-site employee has two valid forms of Government issued identification prior to ensuring the correct information is entered into the E-verify system. An initial list of verified/eligible on-site employees must be provided to the COR no later than 3 business days after the initial contract award.

1.13.3 Non-Disclosure of Government Information

Neither the Contractor, nor Contractor personnel, shall divulge, or release data or information developed or obtained under performance of this work statement, except to authorized Government personnel or upon written approval of the Contracting Officer. The Contractor shall not use, disclose, or reproduce proprietary data which bears a restrictive legend, SECTION 01 00 00 Page 9 other than as specified in this work statement.

Neither the Contractor nor the Contractor's employees shall disclose or cause to be disseminated, any information concerning the operations of the activity which could result in, or increase the likelihood of, the possibility of a breach of the activities, security or interrupt the continuity of its operation.

All inquiries received by the Contractor for information concerning work performed under this contract shall be referred to the Government for evaluation under the Freedom of Information Act of 1975, Public Law 93-502, 5 U.S.C., Section 552. The determination of whether records will be released will remain with the government. The Contractor shall assist the COR in compiling information or records for submission upon request by the Government.

The Contractor shall not release any information (including photographs, files, public announcements, statements, denials, or confirmations) on any portion of the subject matter of this contract or any phase of any program hereunder without the prior written approval of the COR. All documentation showing individuals, names or other personal information will be controlled and protected. The provisions of the Privacy Act of 1974, Public Law 93-579, 5 U.S.C., Section 552a, shall apply.

1.13.4 Conduct of Contractor Employees

All contractor employees and subcontractors shall conduct themselves in a proper manner at all times. No alcoholic or intoxicating beverages or substances or illegal drugs or controlled substances not prescribed by a physician shall be possessed, consumed, or be under the influence of any such substance while on Government property.

The Contractor shall remove from the site any individual whose continued employment is deemed by the appointed receiving agent to be contrary to the public interest or inconsistent with the best interests of the U.S. Army Corps of Engineers.

The Contracting Officer or his appointed representative will require the Contractor to immediately remove from the work site anyone who is incompetent or who endangers persons or property or whose physical or mental condition is such that it would impair the employee's ability to satisfactorily perform the work. Notification to the Contractor will be made in writing if time and circumstances permit. Otherwise, notification will be verbal and will be confirmed in writing as soon as possible. No such removal, however, will reduce the Contractor's obligation to perform all work required under this contract and immediate replacement shall be made as required.

1.13.5 Government Furnished Materials and Equipment

The Contractor shall provide control to ensure Government furnished equipment, property, or items are utilized only for contract purposes. The Contractor will be provided keys to allow access to certain secure areas, and will be held responsible for losses due to his negligence and for the replacement of compromised locks (which can occur due to loss or duplication of keys). The Contractor is required to conduct semi-annual "show-me" inventories of all keys issued to the Contractor. These inventories will be conducted on a semi-annual schedule set by, and in the presence of, the COR or their authorized representative. Upon completion

SECTION 01 00 00 Page 10

(including any extensions of contract term) or termination of the contract for any reason, and except for fair wear and tear, the Contractor shall return all Government furnished equipment, keys and any unused material or supplies in the same condition as received. Any discrepancies (except for fair wear and tear), damages or deficiencies in the inventory shall be chargeable against the Contractor.

1.13.6 Damage or Loss of Contractor's Supplies and Property

The Contractor is responsible for taking the action necessary to protect Contractor supplies, materials and equipment, and the personal property of Contractor employees from loss, damage or theft. The Government assumes no responsibility for theft, damage, etc., of the above. All incidents of theft (or suspected theft) of Contractor materials, supplies, or equipment from project lands shall be reported through the COR and to the District Security Office.

1.14 EVALUATION OF CONTRACTOR PERFORMANCE

The Contractor's performance will be evaluated in accordance with FAR Part

42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum. The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is included in Appendix A - FORMS AND

ATTACHMENTS.

The Contractor's review of the evaluation shall be completed electronically at the CPARS / CCASS website, http://www.cpars.gov. This website also includes guidance and the user's manual.

Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.

1.15 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS

222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

Federal Veteran employment information at:

http://www.fedshirevets.gov/index.aspx

Department of Labor Veterans Employment Assistance:

http://www.dol.gov/vets/

Department of Veterans Affairs-VOW to Hire Heroes Act:

http://benefits.va.gov/vow/

SECTION 01 00 00 Page 11

Army Wounded Warrior Program:

http://wtc.army.mil/modules/employers/index.html

U.S. Chamber of Commerce Foundation-Hiring Our Heroes http://www.hiringourheroes.org/

Guide to Hiring Veterans - Reference Material:

http://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_-_ guide_to_hiring_veterans_0.pdf

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 FIELD SURVEYS

3.1.1 Survey Requirements

Surveys shall be required for all baselines and top of drill hole locations and alignment. In addition, all haul roads and disposal areas shall be surveyed to aid construction for positioning major components of the work designated on the drawings and as specified within. All non-government surveys shall be performed and certified by a land surveyor registered by the State of Tennessee. They shall be conducted in the presence of the Contracting Officer or an authorized representative unless this requirement is waived by the Contracting Officer. The Contractor shall notify the Contracting Officer not less than five working days in advance of each survey. In the event of unavailability of the Contracting Officer or an authorized representative, the Contractor shall perform the survey and certify to the Contracting Officer that it complies with these specifications. Survey results certified by the registered surveyor shall be provided to the Contracting Officer in the form of raw data and also in legible scaled plots of the data three (3) days after completion. All provided survey results will be provided in NGVD 29 vertical datum and NAD 83 horizontal datum.

3.1.2 Disposal/Borrow Area Survey

After clearing and grubbing has been performed, a survey shall be made of the area designated to receive material for the disposal area(s), environmental dikes, ponds, etc. These cross-sections shall be used by the Contracting Officer to provide direction to the Contractor on fine-tuning the desired location for each area(s). No construction shall begin prior to approval of the location by the Contracting Officer. As-built cross-sections shall be produced at the end of the project.

3.1.3 As-Found Survey

The Contractor shall verify as-built information provided in the drawings to ensure information is adequate and correct for the work required in this contract.

3.1.4 Final Survey

A final survey shall be performed by the Contractor. The Government will not be responsible for any input into the process of developing final surveys. This survey shall be used to verify that the location and dimension of project features after all work is complete. The Contractor

SECTION 01 00 00 Page 12 shall conduct the final surveys for any period from which progress payments are requested. Final surveys shall be the basis from which any disputes over changes in conditions shall be made. Within fourteen (14) days after completing the survey, the Contractor shall furnish all originals of all field notes and all other records relating to the survey to the Contracting Officer. The Contractor shall retain copies of all such material furnished to the Contracting Officer. The Contractor shall furnish the following information to substantiate the quantities of work performed during each progress payment period: Field Notes, Weigh Tickets or Quantity Computations, and plotted cross sections of completed work. The Contracting Officer must agree to any template section deviations prior to payment. Progress payments on partially completed work shall not be made without the data required by this paragraph. Determination of such quantities will be made by the Contracting Officer. Specific details and provisions of the final surveys shall be in accordance with Section 01 78 00

CLOSEOUT SUBMITTALS.

3.2 AVAILABILITY AND USE OF UTILITY SERVICES

3.2.1 Contractor Responsibilities

a. The Contractor shall be responsible for the availability of utilities for use on the project. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to and paid for by the Contractor. The Contractor shall carefully conserve any utilities furnished without charge.

b. The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

3.2.2 Alterations to Utilities

a. Where changes and relocations of utility lines are noted to be performed by others, the Contractor shall give the Contracting Officer at least thirty (30) days written notice in advance of the time that the change or relocation is required. In the event that, after the expiration of thirty (30) days after the receipt of such notice by the Contracting Officer, such utility lines have not been changed or relocated and delay is occasioned to the completion of the work under contract, the Contractor will be entitled to a time extension equal to the period of time lost by the Contractor after the expiration of said thirty (30) day period. Any modification to existing or relocated lines required as a result of the Contractor's method of operation shall be made wholly at the Contractor's expense and no additional time will be allowed for delays incurred by such modifications.

b. Separate payment will not be made for alterations or relocations of utilities.

3.2.3 Interruptions of Utilities

a. No utility services shall be interrupted by the Contractor to make connections, to relocate, or for any purpose without approval of the Contracting Officer.

SECTION 01 00 00 Page 13

b. Request for Permission to shut down services shall be submitted in writing to the Contracting Officer not less than seventeen (17) days prior to date of proposed interruption. The request shall give the following information:

(1) Nature of Utility (Gas, L.P. or H.P., Water, etc.)

(2) Size of line and location of shutoff.

(3) Buildings and services affected.

(4) Hours and date of shutoff.

(5) Estimated length of time services will be interrupted.

c. Services shall not be shutoff until receipt of approval of the proposed hours and date from the Contracting Officer.

d. Shutoffs which will cause interruption of Government work operations as determined by the Contracting Officer shall be accomplished during regular non-work hours or on non-work days of the Using Agency.

e. Operation of valves on water mains will be by Government personnel.

Where shutoff of water lines interrupts service to fire hydrants or fire sprinkler systems, the Contractor shall arrange his operations and have sufficient material and personnel available to complete the work without undue delay or to restore service without delay in event of emergency.

-- End of Section --

SECTION 01 00 00 Page 14

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 PAYMENT ITEMS

1.1.1 Mobilization/Demobilization

1.1.1.1 Mobilization and Demobilization

1.1.1.1.1 Payment

1.1.1.1.2 Measurement

1.1.1.1.3 Unit of Measure

1.1.1.2 Miscellaneous Site Work

1.1.1.2.1 Payment

1.1.1.2.2 Measurement

1.1.1.2.3 Unit of Measure

1.1.2 Left Rim Stabilization/Excavation

1.1.2.1 Presplitting for the Main Dam's Left Rim

1.1.2.1.1 Payment

1.1.2.1.2 Measurement

1.1.2.1.3 Unit of Measure

1.1.2.2 Excavation for the Main Dam's Left Rim

1.1.2.2.1 Payment

1.1.2.2.2 Measurement

1.1.2.2.3 Unit of Measure

1.1.2.3 Shotcrete Placement for Main Dam's Left Rim

1.1.2.3.1 Payment

1.1.2.3.2 Measurement

1.1.2.3.3 Unit of Measure

1.1.2.4 Reinforcement Bolts for Main Dam's Left Rim

1.1.2.4.1 Payment

1.1.2.4.2 Measurement

1.1.2.4.3 Unit of Measure

1.1.3 Excavation - Reinforcing Berm

1.1.3.1 Subsurface Drilling, Sampling, and Testing

1.1.3.1.1 NQ Core Drilling, Vertical Holes

1.1.3.1.1.1 Payment

1.1.3.1.1.2 Measurement

1.1.3.1.1.3 Unit of Measure

1.1.3.1.2 NQ Core Drilling, Angled Holes

1.1.3.1.2.1 Payment

1.1.3.1.2.2 Measurement

1.1.3.1.2.3 Unit of Measure

1.1.3.2 Overburden Excavation for the Reinforcing Berm

1.1.3.2.1 Payment

1.1.3.2.2 Measurement

1.1.3.2.3 Unit of Measure

1.1.3.3 Presplitting at Reinforcing Berm

1.1.3.3.1 Payment

1.1.3.3.2 Measurement

SECTION 01 22 00 Page 1

1.1.3.3.3 Unit of Measure

1.1.3.4 Rock Excavation for Reinforcing Berm

1.1.3.4.1 Payment

1.1.3.4.2 Measurement

1.1.3.4.3 Unit of Measure

1.1.3.5 Shotcrete Placement for Reinforcing Berm

1.1.3.5.1 Payment

1.1.3.5.2 Measurement

1.1.3.5.3 Unit of Measure

1.1.3.6 Reinforcement Bolts for Reinforcing Berm

1.1.3.6.1 Payment

1.1.3.6.2 Measurement

1.1.3.6.3 Unit of Measure

1.1.4 Foundation Preparation

1.1.4.1 Drilling and Grouting

1.1.4.1.1 Hole Drilling in Concrete and Rock

1.1.4.1.1.1 Payment

1.1.4.1.1.2 Measurement

1.1.4.1.1.3 Unit of Measure

1.1.4.1.2 Hole Re-Drilling

1.1.4.1.2.1 Payment

1.1.4.1.2.2 Measurement

1.1.4.1.2.3 Unit of Measure

1.1.4.1.3 Placing Grout

1.1.4.1.3.1 Payment

1.1.4.1.3.2 Measurement

1.1.4.1.3.3 Unit of Measure

1.1.4.1.4 Government Directed Stand-by Time for Grouting

1.1.4.1.4.1 Payment

1.1.4.1.4.2 Measurement

1.1.4.1.4.3 Unit of Measure

1.1.4.1.5 Automated Grouting Monitoring and Data Collection System

1.1.4.1.5.1 Payment

1.1.4.1.5.2 Measurement

1.1.4.1.5.3 Unit of Measure

1.1.4.1.6 Portland Cement in Grout

1.1.4.1.6.1 Payment

1.1.4.1.6.2 Measurement

1.1.4.1.6.3 Unit of Measure

1.1.4.1.7 Sand in Grout

1.1.4.1.7.1 Payment

1.1.4.1.7.2 Measurement

1.1.4.1.7.3 Unit of Measure

1.1.4.1.8 Bentonite in Grout

1.1.4.1.8.1 Payment

1.1.4.1.8.2 Measurement

1.1.4.1.8.3 Unit of Measure

1.1.4.2 Foundation Preparation

1.1.4.2.1 Preliminary Cleanup

1.1.4.2.1.1 Payment

1.1.4.2.1.2 Measurement

1.1.4.2.1.3 Unit of Measure

1.1.4.2.2 Foundation Preparation

1.1.4.2.2.1 Payment

1.1.4.2.2.2 Measurement

1.1.4.2.2.3 Unit of Measure

1.1.4.2.3 Dental Excavation

1.1.4.2.3.1 Payment

1.1.4.2.3.2 Measurement

SECTION 01 22 00 Page 2

1.1.4.2.3.3 Unit of Measure

1.1.4.2.4 Dental Concrete

1.1.4.2.4.1 Payment

1.1.4.2.4.2 Measurement

1.1.4.2.4.3 Unit of Measure

1.1.4.2.5 Protective Concrete (Mud Slab on Monolith Foundations)

1.1.4.2.5.1 Payment

1.1.4.2.5.2 Measurement

1.1.4.2.5.3 Unit of Measure

1.1.5 Concrete Materials (Conventional and RCC)

1.1.5.1 Portland Cement

1.1.5.1.1 Payment

1.1.5.1.2 Measurement

1.1.5.1.3 Unit of Measure

1.1.5.2 Pozzolan

1.1.5.2.1 Payment

1.1.5.2.2 Measurement

1.1.5.2.3 Unit of Measure

1.1.5.3 Water-Reducing and Retarding Admixture

1.1.5.3.1 Payment

1.1.5.3.2 Measurement

1.1.5.3.3 Unit of Measure

1.1.5.4 Air Entraining Admixture

1.1.5.4.1 Payment

1.1.5.4.2 Measurement

1.1.5.4.3 Unit of Measure

1.1.5.5 Fine Aggregate

1.1.5.5.1 Payment

1.1.5.5.2 Measurement

1.1.5.5.3 Unit of Measure

1.1.5.6 Coarse Aggregate

1.1.5.6.1 Payment

1.1.5.6.2 Measurement

1.1.5.6.3 Unit of Measure

1.1.5.7 DBase Aggregate

1.1.5.7.1 Payment

1.1.5.7.2 Measurement

1.1.5.7.3 Unit of Measure

1.1.5.8 Reinforcing Steel

1.1.5.8.1 Payment

1.1.5.8.2 Measurement

1.1.5.8.3 Unit of Measure

1.1.5.9 Water Supply System

1.1.5.9.1 Payment

1.1.5.9.2 Measurement

1.1.5.9.3 Unit of Measure

1.1.6 RCC Test Section

1.1.6.1 Test Section Roller Compacted Concrete

1.1.6.1.1 Payment

1.1.6.1.2 Measurement

1.1.6.1.3 Unit of Measure

1.1.7 Reinforcing Berm and Apron

1.1.7.1 Roller-Compacted Concrete

1.1.7.1.1 Payment

1.1.7.1.2 Measurement

1.1.7.1.3 Unit of Measure

1.1.7.2 Additional RCC outside Neat Line Quantity

1.1.7.2.1 Payment

1.1.7.2.2 Measurement

SECTION 01 22 00 Page 3

1.1.7.2.3 Unit of Measure

1.1.7.3 Reinforced Concrete

1.1.7.3.1 Payment

1.1.7.3.2 Measurement

1.1.7.3.3 Unit of Measure

1.1.7.4 Internal Waterstop System

1.1.7.4.1 Payment

1.1.7.4.2 Measurement

1.1.7.4.3 Unit of Measure

1.1.7.5 Foundation Drainage Gallery

1.1.7.5.1 Payment

1.1.7.5.2 Measurement

1.1.7.5.3 Unit of Measure

1.1.7.6 Miscellaneous Metals

1.1.7.6.1 Payment

1.1.7.6.2 Measurement

1.1.7.6.3 Unit of Measure

1.1.8 Placement of Excavated Material

1.1.8.1 Engineered Rock Fill

1.1.8.1.1 Measurement

1.1.8.1.2 Payment

1.1.8.1.3 Unit of Measure

1.1.9 Gallery - Electrical/Mechanical Items

1.1.9.1 Interior Plumbing

1.1.9.2 HVAC System

1.1.9.3 Interior Electrical System

1.1.9.4 Exterior Electrical System

1.1.9.5 Exterior Lighting

1.1.9.6 Interior Lighting

1.1.9.7 Uninterruptible Power Supply (UPS) Systems

1.1.9.8 Intrusion Detection System

1.1.9.9 Closed Circuit Television System

1.1.9.10 Communications Cabling Systems

1.1.10 Instrumentation

1.1.10.1 Survey Markers/Benchmarks

1.1.10.2 Thermal Data Loggers

1.1.10.2.1 Measurement

1.1.10.2.2 Payment

1.1.10.2.3 Unit of Measure

1.1.11 Grading/Earthwork - RCC Reinforcing Berm

1.1.11.1 Permanent Seeding with Tree Planting

1.1.11.1.1 Payment

1.1.11.1.2 Measurement

1.1.11.1.3 Unit of Measurement

1.1.11.2 Permanent Seeding without Tree Planting

1.1.11.2.1 Payment

1.1.11.2.2 Measurement

1.1.11.2.3 Unit of Measurement

1.1.12 Performance & Payment Bonds

1.1.12.1 Payment

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 22 00 Page 4

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 PAYMENT ITEMS

Payment items for the work under this contract are listed in the PROPOSAL PRICE BREAKOUT SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular payment item, shall be included in the listed item most closely associated with the work involved. Payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, tools, supplies, equipment, and incidentals necessary to accomplish the required work, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, cleanup of the area, disposal of any waste, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Mobilization/Demobilization

1.1.1.1 Mobilization and Demobilization

The Contractor shall provide supporting documentation for payment of each item and shall not receive payment until the Contracting Officer has receipts to prove that payment for all items claimed have been validated.

1.1.1.1.1 Payment

Payment for mobilization and demobilization shall be done in accordance with Contract Clause 252.236-7004, PAYMENT FOR MOBILIZATION AND DEMOBILIZATION. The total amount paid will not exceed the contract amount for this payment item.

1.1.1.1.2 Measurement

The Mobilization and Demobilization shall be paid for at the contract price per Job for "Mobilization and Demobilization".

1.1.1.1.3 Unit of Measure

Unit of measure: Job (JOB).

1.1.1.2 Miscellaneous Site Work

1.1.1.2.1 Payment

Payment will be made at the contract price per Job for costs associated with "Miscellaneous Site Work" which includes: surveying, temporary seeding, maintenance and control of traffic, environmental protection, cleaning of Highway 96, earth work, concrete for minor structures, maintenance of disposal area, maintenance of staging areas, disposal area reclamation and closure, demolition of temporary haul and access roads, construction of permanent access roads, implementation of survey markers, SECTION 01 22 00 Page 5 tree clearing, stone protection for excavated slopes, geotextiles, apron cover, barrier swing gates, RCC US and DS Access Roads, security fences and other site restoration. All costs associated with earthwork or fill material classified as other than Engineered Rock Fill, as specified in Section 31 00 00 EARTHWORK, or Stone Protection shall be incidental to Miscellaneous Site Work.

1.1.1.2.2 Measurement

The Miscellaneous Site Work shall be paid for at the contract price per Job for "Miscellaneous Site Work".

1.1.1.2.3 Unit of Measure

Unit of measure: Job (JOB).

1.1.2 Left Rim Stabilization/Excavation

1.1.2.1 Presplitting for the Main Dam's Left Rim

1.1.2.1.1 Payment

Payment will be made for presplitting work satisfactorily completed as specified in Section 31 23 06 BLASTING. Payment shall be full compensation for furnishing all plant, equipment, labor, materials and supplies for drilling, blasting, and for performing all other necessary incidentals.

1.1.2.1.2 Measurement

Measurement for presplitting will be made by the square yard of vertical and sloped rock surfaces actually developed as the final face using the presplit method.

1.1.2.1.3 Unit of Measure

Unit of measure: Square Yard (SY).

1.1.2.2 Excavation for the Main Dam's Left Rim

Payment will be made for excavation for the Main Dam's Left Rim as specified in Section 31 23 05 EXCAVATION.

1.1.2.2.1 Payment

Payment for excavation will be made only for the volume of materials actually removed by the Contractor, and only for the material excavated within the excavation limits shown on the drawings or established in the field by the Contracting Officer's Representative. Payment for any given volume of excavation will not be made under more than one classification of excavation. Payment for excavation shall be at the contract prices for " Excavation for the Main Dam's Left Rim." Over-excavation and subsequent backfilling of excavations necessary through the fault or negligence of the Contractor shall be at no additional cost to the Government. No separate payment shall be made for dewatering, surveying, hoe-ramming, mucking, rock surface cleanups, stockpiling, sandbagging, total of 10-days of geologic mapping, and surveying for determination of excavation quantities. No separate payment will be made for the excavation of materials used as temporary fill for the convenience of the Contractor during the course of construction. No separate payment will be made for removing and disposing

SECTION 01 22 00 Page 6 of soil nails, rock anchors, wire mesh drapery, shotcrete, and rock fall fencing installed by a previous contractor. No separate payment will be made for sheeting and shoring necessary to produce a safe work environment. These are all considered incidental to Excavation for the Main Dam's Left Rim.

1.1.2.2.2 Measurement

At a minimum, pre and post construction surveys of cut areas shall be made under this contract. All measurements for payment will be based on the initial survey and additional surveys as specified in Section 31 23 05 EXCAVATION without regard to any changes that may occur during the execution of the work. All quantity computations for payment will be made using the average end area method from cross-sections taken at intervals not to exceed 50 feet. Final quantities will be measured by comparing the pre and post construction surveys. The Contracting Officer's Representative will make all decisions concerning classification of the excavated materials. Quantities will be measured to the nearest cubic yard.

1.1.2.2.3 Unit of Measure

Unit of measure: Cubic Yard (CY).

1.1.2.3 Shotcrete Placement for Main Dam's Left Rim

The contract price shall constitute full compensation for furnishing all plant, labor, equipment, materials, and supplies, except as otherwise specified, and for performing all operations required for the completion of all work included as specified in Section 03 37 13 SHOTCRETE, shown on Drawing Q4-RCC-B-13, or directed by the Contracting Officer's Representative. All measurements for payment shall be made by or in the presence of the Contracting Officer's Representative.

1.1.2.3.1 Payment

Payment will be made for costs associated with shotcrete placement. All costs associated with satisfactory placement and curing of shotcrete shall be included and shall not be paid as separate items. Areas to be treated with shotcrete will be determined or approved by the Contracting Officer's Representative. Shotcrete placement for test panels is included in the paragraph 3.7.1 Strength Testing of Section 03 37 13 SHOTCRETE, and is considered incidental to "Shotcrete Placement for Main Dam's Left Rim".

Costs associated with laboratory strength testing of cores and sawed beams of shotcrete test panels shall be included in this payment and shall not be paid as separate items. Costs associated with materials and placement of drains shall be included in this payment and shall not be paid as separate items. Payment will be made under Line Item "Shotcrete Placement for Main Dam's Left Rim".

1.1.2.3.2 Measurement

Shotcrete placed will be measured for payment on the basis of shotcrete material sprayed through the nozzle onto the rock surface designated for treatment by the Contracting Officer's Representative.

This is the start of the file's text. The full file is on GovTribe.