W912P5-14-R-0003-0004.pdf

PDF 29 KB Posted

Attached to
Center Hill - Auxiliary Dam Reinforcing Berm and Left Rim Stabilization
Solicitation number
W912P5-14-R-0003
Issued by

About this file

Amendment 0004

View the file

Other files

File Type Posted
W912P5-14-R-0003-0008.pdf PDF
W912P514R0003PlansAm8.pdf PDF
W912P5-14-R-0003TspecsAm8Pgs.pdf PDF
W912P5-14-R-0003-0007.pdf PDF
W912P5-14-R-0003TspecsAm7Pgs.pdf PDF
W912P514R0003PlansAm6.pdf PDF
W912P5-14-R-0003TspecsAm6Pgs.pdf PDF
W912P5-14-R-0003-0006.pdf PDF
W912P5-14-R-0003TSpecsAm5Pgs.pdf PDF
As-BuiltDrawings-ForInfoOnly.pdf PDF
W912P5-14-R-0003-0005.pdf PDF
W912P514R0003PlansAm3.pdf PDF
W912P5-14-R-0003-0003.pdf PDF
W912P514R0003TSpecsAm3Pgs.pdf PDF
W912P514R0003PlansDGN08.zip ZIP file
W912P5-14-R-0003Plans.pdf PDF
W912P5-14-R-0003TSpecsAppB4of5.pdf PDF
W912P5-14-R-0003TSpecsAppB5of5.pdf PDF
W912P5-14-R-0003TSpecsAppB3of5.pdf PDF
W912P514R0003TspecsAm2Pgs.pdf PDF
W912P5-14-R-0003TSpecsAm1Pgs.pdf PDF
W912P5-14-R-0003TSpecsAppendixA.pdf PDF
W912P514R0003PlansDGN02.zip ZIP file
W912P514R0003PlansDGN04.zip ZIP file
W912P514R0003PlansDGN03.zip ZIP file
W912P514R0003PlansDGN05.zip ZIP file
W912P514R0003PlansDGN07.zip ZIP file
W912P514R0003PlansDGN10.zip ZIP file
W912P5-14-R-0003TSpecs.pdf PDF
Q4-RCC-G-08.1.pdf PDF
W912P5-14-R-0003TSpecsAppB2of5.pdf PDF
W912P5-14-R-0003-0002.pdf PDF
W912P5-14-R-0003.pdf PDF
W912P5-14-R-0003TSpecsAppB1of5.pdf PDF
W912P514R0003PlansDGN01.zip ZIP file
W912P514R0003PlansDGN09.zip ZIP file
W912P514R0003PlansDGN06.zip ZIP file
W912P5-14-R-0003-0001.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W38XDD33094432

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Center Hill - Auxiliary Reinforcing Berm and Left Rim Stabilization

The purpose of this amendment is to:

1. Change the estimated quantities for CLIN 0009, Overburden Excavation for the Reinforcing Berm, and CLIN 0011, Rock Excavation for Reinforcing Berm, on the Proposal Price Breakout Schedule.

2. Update clause 52.252-3 Alterations in Solicitation.

The due date for proposals remains 2 December 2015, at 2:00 PM Central Time.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 06-Nov-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P5-14-R-0003

X 9B. DATED (SEE ITEM 11)

30-Sep-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Nov-2015

CODE

US ARMY CORPS OF ENGINEERS-CELRN-RC-N

DIRECTORATE OF CONTRACTING

110 9TH AVENUE SOUTH, ROOM A680

NASHVILLE TN 37202-1070

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P5-14-R-0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The following have been modified:

PRICE BREAKOUT SCHEDULE

AUXILIARY DAM REINFORCING BERM AND LEFT RIM STABILIZATION

Center Hill Reservoir

DeKalb County, Tennessee

PROPOSAL PRICE BREAKOUT SCHEDULE

ITEM

NO.

DESCRIPTION 01 22 00

Para. No.

EST.

QTY.

UNIT UNIT

PRICE

ESTIMATED

AMOUNT

Mobilization/Demobilization 1.1.1 0001 Mobilization and Demobilization 1.1.1.1 1 JOB $ $

0002 Miscellaneous Site Work 1.1.1.2 1 JOB $ $

Left Rim Stabilization/Excavation 1.1.2 0003 Presplitting for the Main Dam's Left Rim 1.1.2.1 3,500 SY $ $ 0004 Excavation for the Main Dam's Left Rim 1.1.2.2 290,000 CY $ $ 0005 Shotcrete Placement for Main Dam's Left

Rim

1.1.2.3 400 SY $ $

0006 Reinforcement Bolts for Main Dam's Left Rim

1.1.2.4 1,800 LF $ $

Excavation - Reinforcing Berm 1.1.3 0007 NQ Core Drilling, Vertical Holes 1.1.3.1.1 1,100 LF $ $

0008 NQ Core Drilling, Angled Holes 1.1.3.1.2 200 LF $ $

0009 Overburden Excavation for the Reinforcing Berm

1.1.3.2 57,000 CY $ $

0010 Presplitting at Reinforcing Berm 1.1.3.3 4,000 SY $ $ 0011 Rock Excavation for Reinforcing Berm 1.1.3.4 103,000 CY $ $ 0012 Shotcrete Placement for Reinforcing Berm 1.1.3.5 1,200 SY $ $ 0013 Reinforcement Bolts for Reinforcing Berm 1.1.3.6 500 LF $ $

Foundation Preparation 1.1.4 0014 Hole Drilling in Concrete and Rock 1.1.4.1.1 19,000 LF $ $ 0015 Hole Re-Drilling 1.1.4.1.2 200 LF $ $

0016 Placing Grout 1.1.4.1.3 76,000 GAL $ $ 0017 Government Directed Stand-by Time for

Grouting

1.1.4.1.4 12 HR $ $

0018 Automated Grouting Monitoring and Data Collection System

1.1.4.1.5 1 JOB $ $

0019 Cement in Grout 1.1.4.1.6 5,000 CF $ $ 0020 Sand in Grout 1.1.4.1.7 87,000 LB $ $ 0021 Bentonite in Grout 1.1.4.1.8 37,000 LB $ $ 0022 Preliminary Cleanup 1.1.4.2.1 31,000 SY $ $ 0023 Foundation Preparation 1.1.4.2.2 16,000 SY $ $ 0024 Dental Excavation 1.1.4.2.3 500 CY $ $ 0025 Dental Concrete 1.1.4.2.4 500 CY $ $ 0026 Protective Concrete (Mud Slab on Monolith

Foundations)

1.1.4.2.5 7,000 CY $ $

Concrete Materials (Conventional and RCC) 1.1.5 0027 Cement 1.1.5.1 18,000 TON $ $

0028 Pozzolan 1.1.5.2 17,000 TON $ $ 0029 Water-Reducing and Retarding Admixture 1.1.5.3 20,000 GAL $ $

0030 Air Entraining Admixture 1.1.5.4 50 GAL $ $

0031 Fine Aggregate 1.1.5.5 59,000 TON $ $ 0032 Coarse Aggregate 1.1.5.6 125,000 TON $ $ 0033 DBase Aggregate 1.1.5.7 135,000 TON $ $ 0034 Reinforcing Steel 1.1.5.8 1 JOB $ $ 0035 Water Supply System 1.1.5.9 1 JOB $ $

RCC Test Section 1.1.6 0036 Test Section Roller Compacted Concrete 1.1.6.1 1 JOB $ $

Reinforcing Berm and Apron 1.1.7 0037 Roller Compacted Concrete 1.1.7.1 1 JOB $ $

0038 Additional RCC Outside Neat Line Quantity 1.1.7.2 1,000 CY $ $

0039 Reinforced Concrete 1.1.7.3 1 JOB $ $ 0040 Internal Waterstop System 1.1.7.4 4,100 LF $ $

0041 Foundation Drainage Gallery 1.1.7.5 1 JOB $ $

0042 Miscellaneous Metals 1.1.7.6 1 JOB $ $

Placement of Excavated Material 1.1.8 0043 Engineered Rock Fill - Placement 1.1.8.1 160,000 CY $ $

Gallery - Electrical/Mechanical Items 1.1.9 0044 Interior Plumbing 1.1.9.1 1 JOB $ $

0045 HVAC System 1.1.9.2 1 JOB $ $ 0046 Interior Electrical System 1.1.9.3 1 JOB $ $

0047 Exterior Electrical System 1.1.9.4 1 JOB $ $ 0048 Exterior Lighting 1.1.9.5 1 JOB $ $ 0049 Interior Lighting 1.1.9.6 1 JOB $ $

0050 Uninterruptible Power Supply (UPS) Systems

1.1.9.7 1 JOB $ $

0051 Intrusion Detection System 1.1.9.8 1 JOB $ $ 0052 Closed Circuit Television System 1.1.9.9 1 JOB $ $ 0053 Communications Cabling Systems 1.1.9.10 1 JOB $ $

Instrumentation 1.1.10 0054 Thermal Data Loggers 1.1.10.2 225 EA $ $

Grading/Earthwork 1.1.11 0055 Permanent Seeding with Tree Planting 1.1.11.1 33 ACR $ $

0056 Permanent Seeding without Tree Planting 1.1.11.2 3 ACR $ $

Bonds 0057 Performance & Payment Bonds 1.1.12 1 JOB $ $

TOTAL ESTIMATED AMOUNT $

SECTION 00600 - REPRESENTATIONS & CERTIFICATIONS

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001: The purpose of this amendment is to:

1. Add an additional organized site visit and opportunity to view geologic cores.

2. Extend the due date for questions to 2 November 2015 at 9:00 AM Central Time.

3. Revise the Specifications.

4. Add the CAD drawings.

5. Update clause 52.236-27 Alt I Site Visit (Construction)

6. Update clause 52.252-3 Alterations in Solicitation

7. Update clause 252.236-7001 Contract Drawings and Specifications

Amendment 0002: The purpose of this amendment is to:

1. Post first round of Questions and Answers. The due date for questions has been changed to 6 November 2015 at

9:00 AM CT.

2. Revise the Specifications and add Appendix B to the Technical Specifications.

3. Replace one exiting drawing, Q4-RCC-G-08.1.

4. Post Site Visit Comments and Attendees.

5. Update clause 52.252-3 Alterations in Solicitation.

6. Update clause 252.236-7001 Contract Drawings and Specifications.

Amendment 0003: The purpose of this amendment is to:

1. Revise the Plans and Specifications.

2. Post the second site visit attendees.

3. Post second round of Questions and Answers. The due date for questions remains 6 November 2015 at 9:00 AM

CT.

4. Revise the Proposal Price Breakout Schedule

5. Update clause 52.252-3 Alterations in Solicitation.

6. Update clause 252.236-7001 Contract Drawings and Specifications.

Amendment 0004: The purpose of this amendment is to:

1. Change the estimated quantities for CLIN 0009, Overburden Excavation for the Reinforcing Berm, and CLIN 0011, Rock Excavation for Reinforcing Berm, on the Proposal Price Breakout Schedule.

2. Update clause 52.252-3 Alterations in Solicitation.

(End of Summary of Changes)