This document is an Amendment (0007) to a federal solicitation for a construction project at Lakehurst Joint Base McGuire-Dix-Lakehurst (JBMDL), New Jersey. The amendment modifies the original solicitation for the Manufacturing Lab Addition between Buildings 331 and 332 and their renovations. Key changes include revisions to multiple drawings across three project phases, including reissued drawings for clarification in Phases 1, 2, and 3. Specification sections for flooring, window treatments, HVAC, and other systems have been revised or deleted.

The amendment also addresses contractor questions, providing clarifications on roller shade power supply (non-motorized), flooring system specifications (vinyl-chip system with 30mil thickness), and Option Line Item 0004's timeline. The government confirmed that phases are structured so only one phase can be worked on at a time, with a potential additional 270 calendar days available if Option 0004 is exercised between October 2025 and September 2026. The bid opening remains scheduled for 4 June 2025 at 2:00 P.M. EST, and bidders must acknowledge receipt of this amendment to remain compliant with the solicitation requirements.

View the file

Other files

File Type Posted
Bid Abstract.pdf PDF
Phase 1 - Spec - Amd 0007.pdf PDF
Phase 2 - Plans - Amd 0007.pdf PDF
Phase 3 - Plans - Amd 0007.pdf PDF
Phase 3 - Specs - Amd 0007.pdf PDF
Phase 1 - Plans - Amd 0007.pdf PDF
Phase 2 - Specs - Amd 0007.pdf PDF
Amendment W912DS25BA0040006.pdf PDF
Appendix H - Bldg 332 - Interior Photos.pdf PDF
Amendment W912DS25BA0040005.pdf PDF
Appendix G - Bldg 331 - Interior Photos.pdf PDF
Appendix J - AMRS Meter Specification 2021.pdf PDF
Appendix I - Transformer and Switchboard.pdf PDF
Amendment W912DS25BA0040004.pdf PDF
W912DS25BA0004 Amendment 03.pdf PDF
Amendment 2 - Plans.pdf PDF
Amendment W912DS25BA0040002.pdf PDF
Appendix F - Exterior Site Photos.pdf PDF
Amendment 1 - Spec 01 35 26.pdf PDF
Appendix D - B331-332 Hazmat Survey.pdf PDF
Appendix E - Site Visit Sign-in.pdf PDF
Amendment W912DS25BA0040001.pdf PDF
Phase 2 - Bldg 331 Renovation - Plans.pdf PDF
Phase 1 - Lab Addition - Specifications.pdf PDF
Phase 3 - Bldg 332 Renovation - Plans.pdf PDF
Solicitation - W912DS25BA004.pdf PDF
Phase 1 - Lab Addition - Plans.pdf PDF
Appendix C - Color and Finishes.pdf PDF
Appendix A - MONACO FA.pdf PDF
Phase 2 - Bldg 331 Renovation - SID.pdf PDF
Phase 3 - Bldg 332 Renovation - SID.pdf PDF
Phase 1 - Lab Addition - Exterior Finish.pdf PDF
Phase 3 - Bldg 332 Renovation - Specifications.pdf PDF
Phase 2 - Bldg 331 Renovation - Specifications.pdf PDF
Phase 1 - Lab Addition - SID.pdf PDF
Appendix B - HVAC.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.

If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

NOTE: Bidders must acknowledge receipt of this amendment by date specified in the bid (or as amended) by one of the following methods:

In the space provided on the SF 1442, by separate letter, or by signing block 15 below . FAILURE TO

ACKNOWLEDGE AMENDMENT BY DATE SPECIFIED MAY RESULT IN REJECTION OF

YOUR BID IN ACCORDANCE WITH THE LATE BID, LATE MODIFICATION OF BID, OR

LATE WITHDRAWAL OF BID (FAR 14.304)

SUMMARY OF CHANGES

Section 00 21 13 - Instructions to Bidders

Lakehurst JBMDL, NJ Additive Lab Add & B331/332 Reno

W912DS25BA004

Amendment 0007

AMENDMENT 0007 to DRAWINGS and SPECIFICATIONS for Additive Lab Add & B331/332 Renovation at Lakehurst JBMDL, NJ.

TO OFFERORS

The following changes shall be made to the drawings and specifications.

DRAWINGS

1. The following DRAWINGS have been REVISED but NOT REISSUED:

- None

2. The following DRAWINGS have been REVISED and REISSUED:

Phase 1

- Drawing CD101A

- Drawing S101A

- Drawing AE120A

- Drawing AE503A

- Drawing AE505A

- Drawing MD101A (Reissued for clarification)

- Drawing M101A

- Drawing M301A

- Drawing M601A

- Drawing P101A

- Drawing P501A Phase 2

- Drawing M101B Phase 3

- Drawing AE601C (Reissued for clarification)

- Drawing MD101C (Reissued for clarification)

- Drawing M101C

3. The following DRAWINGS have been ADDED:

- None

4. The following DRAWINGS have been DELETED:

- None

SPECIFICATIONS

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

- None

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

- Section 21 13 13 – is hereby removed in its entirety from Phase 2 (B331) Specifications

- Section 21 13 13 – is hereby removed in its entirety from Phase 3 (B332) Specifications

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

- Section 09 67 13.05 – Phase 1 (Lab Addition)

- Section 09 67 23.13 – Phase 2 (B331)

- Section 09 67 23.13 – Phase 3 (B332)

- Section 12 24 13 – Phase 2 (B331)

- Section 12 24 13 – Phase 3 (B332)

- Section 23 30 00 – Phase 1 (Lab Addition)

- Section 23 30 00 – Phase 2 (B331)

- Section 23 30 00 – Phase 3 (B332)

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

- None

PROPOSER’S QUESTIONS AND GOVERNMENT REPLY

Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.

CLARIFICATION to RFI 59 as issued in amendment 0005:

59. E-501B Electrical Schedules: B331 & B332 include roller shades are specified as motor operated. We did not see them in the Electrical Schedules or noted on plans? Would you please advise of power supply? RESPONSE: The roller shades are not motorized, please refer to section 12 24 13 paragraph 2.1.2.

1. Please clarify if the government would like a trowel mortar system or a colored quartz aggregate or a vinyl-chip. All have varying degrees of overall finish and nominal thickness. All of which have been listed in the spec RESPONSE: Basis of design is vinyl-chip system (per finish schedule) Basis of design, nominal thickness is (+/-) 30mil, please refer to revised specifications, (quarts has been removed).

2. Would slurries and/or high build broadcast systems be considered by the government as a trowel mortar system RESPONSE: Please bid the project per specifications, any substitutions or deviations from the specification will be addressed during submittal preview process, after award.

3. Option Line Item 0004 on the Bid Proposal Form is still very confusing. Phase 1 and 2 have a total duration of 750 days. If Option 0004 is awarded at the same time along with the Lab Addition and BLdg 331, are we to complete all three buildings within the 750 days? Can we work on bldgs. 331 and 332 at the same time if they are awarded together.

RESPONSE: The Government is unsure where the confusion lies, please read the words of the CLIN and NOTES carefully, the window for exercising CLIN 0004 is 1 October 2025 thru 30 Sep 2026, if/when CLIN 0004 is exercised (within the window given) additional 270 Calendar days will be added to the POP. Per plans and specs the Phases are structured in such a way that only one phase can be worked on, at any given time.

4. According to Amendment 5 Bid proposal form, have you eliminated the possibility of awarding Option 0004 after September 30, 2026 and the additional 270 days?

RESPONSE: No, amendment 5 clarified CLIN 0004 ambiguity related to expected execution window and POP extension, if/when executed. If the funds for phase 3 are not available within the noted time window, the contract will only cover what was awarded.

Amendment 0005 - Add Lab B331&332.pdf
DRAWINGS
SPECIFICATIONS
PROPOSER’S QUESTIONS AND GOVERNMENT REPLY
IDCode: J
Page: 1
Pages: 2
AmendNo: 0007
EffDate: 27 MAY 2025
ReqNo:
ProjNo: PANN 004082
IssCode: W912DS
AdmCode:
IssuedBy: W2SD ENDIST NEW YORK

KO CONTRACTING DIVISION, 26 FEDERAL PLAZA ROOM 16 300

NEW YORK, NY 10278-0004

UNITED STATES

NICHOLAS EMANUEL, EMAIL: NICHOLAS.P.EMANUEL@USACE.ARMY.MIL TELEPHONE: 9177908069

AdminBy:

SCD: PAS:

ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: W912DS25BA004
SolDate: 22 APR 2025
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is to:

1. Answer questions to prospective bidders for informational purposes only

2. Revise and Reissue Specs and Drawings

3. Delete Specs

Bid Opening remains 4-June-2025 at 2:00 P.M. EST