This document is a Structural Interior Design (SID) Package for the renovation of Building 331 at Joint Base McGuire-Dix-Lakehurst in Lakehurst, New Jersey. The project involves a single-story renovation of an existing facility, with the primary goal of creating a safe, productive, and comfortable environment for manufacturing personnel and administrative staff. The interior design focuses on a warm, analogous color palette with complementary accents to achieve visual continuity and durability.
The renovation includes specific design details for three main areas: the Machine Shop, Compressor Room, and Restroom. For each space, the design specifies epoxy flooring, painted walls (either CMU or gypsum wallboard), and exposed ceilings painted white. The Machine Shop will have painted CMU walls with stainless steel wall base and corner guards, while the Compressor Room and Restroom will have similar finishes with slight variations. The exterior finishes have been selected to be compatible with surrounding facilities, including Hangar 1, which is part of the Lighter Than Air Historic Preservation District. The project is part of a larger expansion of Buildings 331 and 332, with this document specifically addressing the renovation of Building 331.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
601 NE 63rd Street
Oklahoma City, OK 73105
229 Peachtree Street NE
International Tower, Suite 600
Atlanta, GA 30303
Structural Interior Design Package
Final Submittal
January 2025
Building 331/332 Lab Expansion
MSBL 12-4029
Joint Base McGuire/Dix/Lakehurst
Lakehurst, NJ
B331 Renovation
This page intentionally left blank.
Joint Base McGuire-Dix-Lakehurst, Lakehurst, NJ
Structural Interior Design
TABLE OF CONTENTS TAB
SID NARRATIVE 1
INTERIOR FINISH SAMPLES 2
FINISH MATERIALS LIST 3
FLOOR PATTERN PLANS 4
ROOM FINISH SCHEDULE 5
INTERIOR ELEVATIONS 6
MILLWORK SECTIONS 7
SIGNAGE 8
SID Narrative
Section 1
Joint Base McGuire/Dix/Lakehurst, Lakehurst, NJ
1. Design References:
a UFC 3-120-10, Interior Design
2. General Description:
The B331/332 Lab Expansion at Joint Base McGuire/Dix/Lakehurst (JBMDL) will consist of a single-story addition and the renovation of two existing facilities and will be separated into three projects. This document discusses the Structural Interior Design (SID) for the second project, the renovation of B-331.
The addition was constructed in the first project and B-332 will be renovated in the third. The intent of the interior design is to create a safe, productive, and comfortable environment for all manufacturing personnel and administrative staff of the facility.
Exterior finishes have been selected to be compatible with surrounding facilities, including Hangar 1, that are part of the Lighter Than Air Historic Preservation District.
3. SID Narrative:
The Interior color scheme will include a warm, analogous color palette for the background and complementary accents. The goal is to achieve visual continuity and overall cohesiveness with durability, longevity, and flexibility in mind throughout the facility.
a. Machine Shop: Flooring will be epoxy. The walls will be painted CMU and gypsum wall board with a level 4 finish, eggshell paint, and stainless-steel wall base. The ceiling will be exposed to the structure and painted white. Doors and frames will be painted. All exposed gypsum wallboard corners will receive stainless steel corner guards.
b. Compressor: Flooring will be epoxy. The walls will be gypsum wall board with a level 4 finish, eggshell paint, and stainless-steel wall base. The ceiling will be exposed to the structure and painted white.
Doors and frames will be painted
c. Restroom: Flooring will be epoxy. The walls will receive stainless steel wall base only in this project.
All other finishes have been provided in the first project, the construction of the addition. Doors and frames will be painted
| TOC |
| Section 1 - SID Narrative |
| Section 2 - Interior Finish Samples |
| Section 3 - Drawings |
| AF001B - Finish Materials List |
| AF101B - Floor Pattern Plan |
| AF601B - Room Finish Schedule |
| AI201B - Interior Elevations |
| IG101B - Signage Floor Plan |
| IG501B - Sign Types |
| IG601B - Signage Schedule |
File details come from the government source that posted it. Updated .