This document is an amendment to a solicitation for repair and HEMP shielding upgrades at a power building at the Pituffik Space Base in Greenland. The amendment provides revisions to drawings and specifications, answers questions from potential offerors, and deletes clauses regarding Buy American requirements that do not apply. Relevant changes include replacing roof and wall panels, removing and replacing water, sanitary and electrical utility lines totaling over 200 meters, demolishing control room equipment after temporary power is established, installing HEMP doors, insulating and adding heaters to a water storage tank, and conducting power studies and protective device coordination. Offerors must submit proposals by January 2024 and the government will not guarantee an award or notice to proceed in time for the 2024 shipping season. The amendment also provides site weather data, storm condition protocols, and clarifies asbestos and hazardous waste disposal requirements.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912DS24R0004
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Please see the continuation page for the purpose of this amendment.
NOTE: Offerors must acknow ledge receipt of this amendment by the date specified in the proposal (or as amended) by one of the follow ing methods: in the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).
1. CONTRACT ID CODE PAGE OF PAGES
J 1 12
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Dec-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS24R0004
X 9B. DATED (SEE ITEM 11)
20-Oct-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Dec-2023
CODE
US ARMY CORPS OF ENGINEERS, NEW YORK
26 FEDERAL PLAZA, RM 16-300
NEW YORK NY 10278-0090
W912DS 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0003
Pituffik SB, Greenland Repair BMEWS Power, Bldg 4016
Amendment 0003
AMENDMENT 0003 to DRAWINGS and SPECIFICATIONS for Repair BMEWS Power, Bldg 4016, Pituffik SB, GL.
TO OFFERORS
The following changes shall be made to the drawings and specifications.
DRAWINGS
1. The following DRAWINGS have been REVISED but NOT REISSUED:
- None
2. The following DRAWINGS have been REVISED and REISSUED:
- Drawing C-102
- Drawing C-103
- Drawing C-105
- Drawing S-001
- Drawing S-101
- Drawing S-410
- Drawing S-420
- Drawing S-501
- Drawing M-301
- Drawing M-404
- Drawing M-406
- Drawing M-504
- Drawing M-601
- Drawing EP-105
- Drawing E-615
- Drawing ES-102 * only available to US Prime contractor with executed NDA
- Drawing X-151 * only available to US Prime contractor with executed NDA
3. The following DRAWINGS have been ADDED:
- None
4. The following DRAWINGS have been DELETED:
- None
SPECIFICATIONS
1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:
- Appendix R - Site Photos (J-Plant) – Addendum – additional site photos
2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:
- None
3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:
- Section 33 16 15 Water Storage Steel Tanks – is hereby replaced in its entirety (changes underlined)
4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:
- Section 01 00 00 – General Requirements – revise paragraph 22 in its entirety with the following: “Please refer to Specification Section 01 32 01.00 10 paragraph 3.8.5 (b)”
- Section 01 00 00 – General Requirements – revise paragraph 34 (b) (1) in its entirety as follows: “In view of the short construction season and the estimated date of arrival of the sealift at Pituffik on July 15, limited air shipment is available, but at the contractor’s expense. The cost for airfreight from McGuire to Pituffik can be obtained by contacting 821sptslgdistro@us.af.mil.“
- Section 01 00 00 – General Requirements – revise paragraph 34 (b) (6) in its entirety as follows: “Available cargo aircraft that support Pituffik SB include C-130, C-17. C-5 can be used however it requires additional coordination thru AMC. Cargo space availability is subject to mission requirements and aircraft limitations. Specific information about the cargo being shipped will be needed before a quote can be given. Please contact 821sptslgdistro@us.af.mil for more information.”
- Section 01 32 01.00 10 – Project Schedule – revise paragraph 3.8.5 (b) in its entirety as follows:
“1. This provision specifies the procedure for determination of time extension for usually severe weather in accordance with the contract clause entitled “Default: (Fixed Price Construction).” In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe, that is, Base Command declares storm conditions as “Charlie”, or “Delta” weather conditions.
b. The unusually severe weather must cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
2. ADVERSE WEATHER FOR WORK: The annual estimated number of calendar days lost due to “Charlie”, or “Delta” storm conditions at the 12 SWS J-Plant project site, is 40 calendar days.
This estimate does not include the period during Holiday, where construction operations normally shutdown from December 15 to January 15 of each year. This will constitute the base line for annual weather time evaluations. The Contractor’s progress schedule must reflect these anticipated adverse weather delays in any weather dependent activities. Adverse weather days are to be applied as follows: Apply approximately 20 percent onto weekends, 80 percent onto work weekdays including work weekday holidays and special event days. This is based on a 6-day work week.
3. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor must record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor’s scheduled workday. The number of actual adverse weather delay days must include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month and be recorded as full days. If the number of actual adverse weather delay days for a 12-month period not including the calendar days the construction operations are shut down for Holiday, exceeds the number of days anticipated in paragraph 2 above, the Contracting Officer will convert qualifying delays to calendar days, giving full consideration for equivalent fair-weather workdays, and issue a modification in accordance with the contract clause entitled “Default (Fixed Price Construction)”.
4. The Base Command declares storm conditions as they occur; either "Normal", "Alpha", "Bravo", Charlie, or a "Delta" condition is declared. For each of the latter four conditions the contractor and his personnel must adhere to precautions and restrictions prescribed in the following under "Storm Conditions". When called for all contractor personnel must check in and report their location to the "storm" coordinator (SOC). All Contractor personnel are considered to be engaged in non-essential work with regard to these storm conditions unless otherwise categorized by the Contracting officer.
WEATHER CONDITIONS
Weather conditions at Pituffik Main Base:
The following weather chart is furnished for convenience only:
TEMP
C (F)
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Absolute 5 6 2 6 10 17 17 14 9 6 4 4 max. (41) (43) (35) (43) (50) (63) (62) (57) (49) (43) (39) (39)
Mean daily -19 -21 -22 -22 -3 3 7 6 0 -8 -14 -19 max. (-3) (-5) (-7) (-7) (26) (38) (44) (43) (32) (18) (7) (-2)
Mean daily -27 -28 -29 -22 -9 -1 2 2 -5 -14 -22 -18 min. (-17) (-19) (-20) (-8) (15) (30) (36) (35) (23) (7) (-7) (-1)
Absolute -39 -44 -42 -38 -27 -10 -4 -5 -21 -31 -35 -39 min. (-39) (-47) (-44) (-36) (-17) (14) (24) (23) (-5) (-24) (-31) (-39)
Mean number of hours of
JAN FEB MAR APR MAY JUN JUL AUG SEP OC
T
NO
V
DE
C daylight per day
0 4 10 21 24 24 24 24 14 7 0 0
STORM CONDITIONS
Arctic winter storms are divided into these classifications: Normal, Alpha, Bravo, Charlie, and Delta. Delta represents the most serious threat to life and property. Two factors (visibility and temperature) are assessed to determine the applicable storm conditions. When any one of these two factors are present, the appropriate storm condition is declared.
A. Storm Condition Normal - Business as usual.
Storm Condition Alpha - Initial warning of a potential Arctic winter storm. No danger exists at this point; however, all personnel should prepare for Storm Conditions.
Storm Condition Bravo - All pedestrian traffic will use the buddy system (two or more people traveling together). All personnel must stay on approved roads. If you are traveling alone in a vehicle, it must have a comm radio or use the buddy system.
Storm Condition Charlie - All non-essential base facilities close. Return To Quarters. Pedestrian traffic is prohibited. Call the base taxi or use the base shuttle bus service if dedicated vehicles are not available.
Storm Condition Delta - All personnel are restricted to the buildings in which they are located at the time a Storm Delta is declared. Absolutely No Pedestrian or Vehicular Travel Is Permitted.
Only emergency vehicles will operate during this condition and only at the direction of the Base Commander.
All year long, Pituffik weather is like weather in many northern states, unpredictable. It can rain, sleet, snow, and be very sunny and warm all in one 24-hour period. Always be prepared and expect the unexpected.
For your protection, storm shelters (phase shacks) are located at short intervals along the roads leading to off-base worksite locations. Each shelter is heated and stocked with emergency food, water, bedding, and a telephone. They are for use by anyone caught in a sudden storm condition. Remember, these shelters are for emergency use only.
Storm Condition
Winds Visibility Location of Personnel
Allowed to Travel
ALPHA Hazardous Weather within
12 Hrs
> 1 Mile
No restrictions Yes
BRAVO >25 Knots < 3/4 Mile
No restrictions:
Must use buddy system and radios
Non-essential restricted to main base
CHARLIE >35 Knots < 1/2 Mile
Dorm/shelter Remain in shelter;
Movement must be approved by the SOC
DELTA >50 Knots 100 Yards
Dorm/shelter Rescue operations only;
Must be approved by the
SOC
- Section 26 11 14.00 10 – Medium Voltage Metal-Clad Switchgear – revise 1st subparagraph of
2.2.6 (c) as follows: “For redundancy, all master control automation functions shall be capable of being executed from either of hot-tie distributed processors. If the automation processor executing master control automation functions should fail, the next available automation processor shall automatically assume control of all master control automation functions. The redundant automation processors shall each consist of a fully redundant power supply and CPU.
Transfer of master control functions to a redundant processor shall be bump less. The master control automation functions shall include:”
- Section 26 23 00.00 40 Switchboards and Switchgear – revise paragraph 2.2.1.1 as follows:
“Ensure that the switchboard, switchgear enclosure is NEMA ICS 6 Type 1 fabricated entirely of galvanized cold rolled steel with painted finish. Bolt the enclosure together with removable bolt-on side and hinged rear covers. Provide front and rear doors with stainless-steel padlockable vault handles with a three-point catch. Ensure that bases, frames and channels of enclosure are corrosion resistant and fabricated of ASTM A240/A240M type 304 or 304L stainless-steel. Base includes any part of enclosure that is within 75 mm of concrete pad. Paint the enclosure, including the bases, ASTM D1535 light gray No. 61 or No. 49. Ensure that the paint coating system complies with IEEE C57.12.28 for galvanized steel.”
- Section 26 28 01.00 10 Coordinated Power System Protection – replace 1st subparagraph of
1.2 as follows: “The short-circuit fault current analysis and protective device coordination study shall be submitted to the Government within 120 days of award of contract and prior to receiving final approval of the distribution equipment shop drawings.”
- Section 26 32 15.00 Engine-Generator Set Stationary 3300KW, with Auxiliaries – Revise part of paragraph 2.1.1 (Mechanical Characteristics table on page 15 - Identification – Intercooler Type) as follows: “Single circuit water cooled with an inlet temp of 50C”
- Section 26 32 15.00 Engine-Generator Set Stationary 3300KW, with Auxiliaries – Revise paragraph 2.8.2.1 (a) as follows: “Design Conditions: Each radiator unit must have ample capacity to remove not less than the total 2160 kW of heat rejected by its respective engine at 100 percent full-rated load to the jacket water, fuel oil, and lubricating oil system, and intercooler.
There must be a dual cooling circuit that is divided as per the P&IDs on sheet M-706; one will be for the engine jacket water cooling and the other for the lube oil/aftercooler circuit due to the different temperature requirements. Radiator capacity must be rated at optimum temperature of coolant leaving the engine and intercooler as recommended by the engine manufacturer with an ambient dry bulb air temperature outside of the building of 19.1 degrees C maximum, and minus
37.2 degrees C minus minimum at the site elevation specified in the paragraph SITE CONDITIONS, and with the coolant mixture specified in the paragraph ENGINE CAPACITY.
Pressure drop through the radiator must not exceed 35.8 kPa when circulating the maximum required coolant flow. Radiator air velocity must be a maximum of 7.6 meters per second.”
- Section 26 32 15.00 Engine-Generator Set Stationary 3300KW, with Auxiliaries – Revise the Minimum load step resolution in paragraph 2.22 from “500kW” to “0.5kW”
- Section 26 32 15.00 Engine-Generator Set Stationary 3300KW, with Auxiliaries – Revise the last sentence of paragraph 2.22.1 as follows: “The load bank must deliver full rated kW at rated voltage on 500kW steps.”
PROPOSER’S QUESTIONS AND GOVERNMENT REPLY
Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s). Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.
1. This RFP requires the US Prime Contractor to issue a Performance Bond for the work in the amount of 100% of the contract value. As with other RFP requirements, the 100% Performance Bond requirement will be flowed down to the Dansih/Greenlandic Subcontractor. For Danish and Greenlandic contractors a bond of 100% of the contract value is over and beyond national industry standards. In all other USACE RFP's at Pituffik Space Base there is a requirement for a Bank Letter of Guarantee for the performance of the work in the amount of 15% of the contract value. To enable Danish and Greenlandic contractors to participate as Subcontractors to the US Prime we request the requirement be revised to the standard
15% Bank Letter of Guarantee. RESPONSE: The P&P bonds are submitted by the Prime. The 100 percent bond covers all the work to include that of the subcontractor(s). There is no flow down and as a result, the subcontractor does not provide a Bank Letter of Guarantee.
2. 01 00 00, 4. Insurance - Please confirm that Insurance requirements will be aligned with Danish Law for Danish and Greenlandic contractors. RESPONSE: US Prime contractor will adhere to US law for insurance regarding their portion of the project work (HEMP) and the Danish/Greenlandic firms will adhere to Danish law for their construction requirements.
3. The solicitation mentions C-141s which are no longer in use. The solicitation also states the maximum limit in lbs. for the C-5 is 50,000 lbs. The specification sheet for the C-5 states the maximum cargo weight limit is 281,000 lbs. The specification sheet for the C-17 states the maximum cargo weight limit is 170,900 lbs. Please confirm the types of aircraft that fly to Pituffik and the cargo weight limits for these aircraft.
RESPONSE: The primary aircraft servicing Pituffik are: C17, C130, and the 757 Combi are primary methods of receiving cargo. Pricing and capacity for the airlift vary depending on space availability, size, weight, and origin of the cargo. One option would be to buy out an entire aircraft.
Approximate costs can range from $330K to $450K depending on the load and aircraft type. POC 1st Lt Glenn Peters (glenn.peters.2@spaceforce.mil)
4. Will the Government please provide bidders with a copy of the Final Governing Standards applicable to the Thule Defense Area, which respect Greenland Home Rule environmental standards? (Per FedCenter.gov, "Final Governing Standards are developed in accordance with DOD Instruction 4715.5, Management of Environmental Compliance at Overseas Installations, dated 1 May 2007, to address the protection of human health and the environment in each foreign country where DOD maintains substantial installations," but these documents are only available on FedCenter.gov to U.S. military personnel with a membership account. RESPONSE: Environmental Final Governing Standards for Greenland can be found in Package 4, Appendix L as well as other governing updated Appendices issued under previous amendment.
5. Amendment 2 RFI 58 - The solicitation schedule is predicated upon making the 2024 PACER GOOSE for bulk material delivery and work start. A June 30, 2024 NTP precludes meeting the 2024 PACER GOOSE mission. Will the Government ensure the contract award date will be made in sufficient time to meet the 2024 PACER GOOSE timelines? RESPONSE: At this time the Government cannot guarantee the Award or NTP in time for 2024 shipping season. Note, there is a submittal review/approval process required before ANY material should be purchased and shipped.
6. FAR Clauses 52.225-10, 52.225-11 and 52.225-12 relating to the “Buy American Act” are all included in the solicitation. Please confirm BAA does not apply to this solicitation as the prescription is limited to CONUS sites. RESPONSE: The BAA does not apply to this solicitation therefore, FAR Clauses 52.225-10, 52.225-11, and 52.225-12 will be removed from the solicitation in this amendment.
7. Would the Government provide a conformed copy of the solicitation to ensure compliant and responsive proposals are submitted allowing for a straightforward and easy evaluation? RESPONSE: The Government will not provide a conformed copy. It is the responsibility of the Offeror to check all amendments to ensure compliant and responsive proposals are submitted.
8. With reference to Amendment no.2: Offer to be submitted latest 9. January 2024. Deadline for forwarding inquiries seems unchanged. Please confirm that deadline for inquiries remain 27th November 2023.
RESPONSE: Inquiries can be submitted till December 14th.
9. With reference to Amendment no.2 (Q/A: 1): “Applicable Pituffik regulation to follow”. Answer seems not responding our requirement for clarification: Is it correct understood, that all companies (US firms and Danish firms) under this contract must follow Inatsisartutlov nr. 11 of 1 December 2021 under Greenlandic law. Requiring that companies entering agreements with foreign defense authorities (with U.S Government) on Pituffik Space Base, must be registered – after award of the contract/works - as a limited company or private limited company domiciled in Greenland, and its management must have its seat in Greenland, allowing for Greenlandic taxation of the works under this contract? RESPONSE: (a) NO, The Inatsisartutlov nr. 11 of 1 Dec 2021 DOES NOT APPLY to US Prime Contractor/this solicitation.
10. With reference to document: Package 4 – Appendices. Appendices incl. “Asbestos Survey Report dated 2006”. Can we conclude that the quantities defined within this report, is the asbestos containing types/quantities to be removed/handled/disposed – if not please, specify types/quantities? RESPONSE:
Correct, quantities and locations as outlined in the report are what is expected to be found/removed. Should additional location be discovered, notify the COR immediately.
11. With reference to document: Drawing C102, C103 and C105. Scale 1:400. Drawings indicate scale 1:400 however exclude any “rulers” or information about original size of drawings – meaning it is not possible to measure works. Please provide scale information allowing offeror to measure the works to be priced. RESPONSE: Please refer to updated drawings with scale. 1 cm:400mm
12. With reference to document: Water utility lines Specification Sections 33 11 00 & Drawings C-103, C-504.
There are no scaled drawings showing the new water utility lines. Please provide quantities of piping and fittings used for water utility lines. On drawing C-504 detail 1 is shown a detail cutting in a new line on an existing line. We can’t find that on the plan drawings. Please confirm where that shall be executed.
RESPONSE: Please refer to C drawings for pipe routing and needed fittings, Detail 1 on C-504 is a generic detail to use when teeing off a water line.
13. On drawing C-504 detail 3 is shown a detail of culvert below grade. According to specifications there shall be a drain point at all low point. That means inside the culvert. Is that correct understood? RESPONSE:
Correct, the drain valve should be located in low spot so that it can be visible and accessed in case of an emergency.
14. With reference to document: Drawing C103. New 150mm sanitary. Pipe also to be installed downhill as we understand the topographic. Therefor length cannot be measured on the drawing. Which total length of “Existing sanitary to be replaced (150mm)” shall be considered within the pricing? Please clarify quantities for fittings etc. to be included, since not possible to extract this from the drawing. RESPONSE:
Please refer to updated drawings with scale. The terrain gradually slopes to the south (away from bldg 4016)
15. With reference to document: Drawing C102. Removal utility lines. For following utility lines additional is required to price the demolition works: (a) “Remove abandoned Utility as needed” (works cannot be defined by this drawing); (b) “Existing sanitary to be replaced” (works cannot be defined by this drawing and utility probably running downhill); (c) “Existing water line to be removed” (works cannot be defined by this drawing and utility probably running downhill). For a), b) & c): Please provide some information as type of pipes, diameter etc. + length + if any concrete pads/foundations incl. numbers to be removed/demolished – allowing us to price these works. RESPONSE: (a) the abandoned utility refers to abandoned cable lines, with the provided scale work can be estimated. (b) the length of the sanitary line can be determined from C103, the site has a gradual slope away from B4016. (c) refer to updated drawings, as well as Appendix R addendum, yes there is a slope to the site, about 20m of waterline is contributed to steeper slope. The utilities are on wooden sleepers or wooden supports on grade.
16. With reference to document: Drawing C-102 Hazardous Waste Hazardous waste from demolition works.
Tender package seems only include a survey report for asbestos. Drawing C-102 Demolition Note 5 states a list of possible hazardous materials as PCB, oil, mercury, lead. To price the correct removal/handling/disposal of such hazardous waste – location/type/product/quantities is needed. Pleas provide a survey report/environmental mapping of all hazardous waste materials to be considered within this project incl. the mentioned data/information. RESPONSE: PCB, mercury, and lead contaminated material are not quantified, any suspect materials must be carefully handled and is to be disposed of at the approved landfill with other construction debris or containerized as hazardous waste then stored in the HWSA (building 935 & 604), oil will also be determined to be deemed for recycling or hazardous waste then stored in building 580 or the HWSA respectively. Hazardous waste is not to be disposed of in the landfills at Pituffik, and will require sampling to determine disposal methods.
17. With reference to document: W912DS24R0004 “Solicitation, offer and Award” – Section 01 00 00 Special Requirements – Clause 22 – Time extension for unusually weather. Time extension after 10 days lost work each year. Our experience is, that this is a very low number of days. Only valid for working on main base, not J-Site, were returning to main base is required much earlier. Please consider increasing number of days allowing this to be included in the P6 schedule from the beginning/contract. Is it correct understood, that only time extension will be granted, if more time lost then contractual stated days, meaning Contractor have the risk and bear all standstill cost for all stop of work due weather, even for additional days accepted for time extension? RESPONSE: Please refer to section 01 32 01.00 10 paragraph 3.8.5 for revisions. It is correct that only time extensions are granted due to adverse weather.
18. With reference to document: Package 2 - Specification Section 01 50 00 Temporary Construction Facilities. Facilities and site area at J-Plant/J-Site. (a) Will there be any restrictions - winter or summer/winter - to establish contractor’s facilities as cabins for offices, sanitary and storage at J-Plant/J- Site? (b) Will there be any restrictions - winter or summer/winter - to outside storage areas for materials as new roof/wall panels etc. at J-Plant/J-Site? (c) Will there be any restrictions - winter or summer/winter
- to outside handling/temporary storage of demolished and sorted materials at J-Plant/J-Site, which following need to be transported to dedicated dump or similar location? RESPONSE: (a) Weather conditions, wind and snow drift will be the major restrictions for operations. The contractor will be able to setup their offices and facilities at the project site, coordination with COR and BCE will be needed, contractor must consider the environment and properly secure the structures. (b) Storage of materials will be allowed near the project site, laydown plan and coordination with COR and BCE will be needed. Contractor must consider the environment (wind and snow drift) before storing any material at project site, contractor will be responsible for properly securing and protecting the materials. (c) Snow drift and win will be an issue at the site. Only limited amount of demolished material may be stored at the site. Consideration must be given to the type of material stored and weather conditions, material that can be blown away should be secured and removed from site at end of the day and disposed of at appropriate dump site. Any material that is blown off site will be contractors responsibility to cleanup.
19. With reference to document: Contract documents – Demolition works. Disposal of demolished materials and waste. Please clarify if it is correctly understood – that all demolished / removed materials and waste (incl. all types of hazardous waste) can be disposed at Pituffik Space Base at designated areas/dumps, and without any fees to be paid by the Contractor? RESPONSE: Incorrect, no hazardous waste can be disposed of at Pituffik. Only asbestos and C&D materials can be disposed of in the asbestos landfill. All hazardous waste is required to be shipped off island and turned into DLA. Base Maintenance Contractor may be utilized to assist in disposal procedures, all hazardous material disposal must follow the requirements as outlined in IHMP, OHWMP, etc. as provided in appendices.
20. With reference to document: Water Tank insulation, Specification Sections 33 16 15 & Drawings C-503.
There are no specifications of insulation and cladding of the water tank. Is it correct that it is not needed to insulate the water storage tank? There is no insulation in the water tank pad. Is that correct?
RESPONSE: The water storage tank will require insulation with cladding, and tank heater. Refer to updated specification 33 16 15 for requirements and updated electrical drawing for power disconnect update. The water tank pad will not require insulation.
21. With reference to Package 1: Drawing M-706 Generator and Radiator Circuit P&ID: Generator and Radiator Circuit P&ID In this case with 50°C demand for intercooler, Contractor advice to specify Single Circuit (Combined) System with one low temperature radiator cooler as indicated in Mechanical Schedules Sheet ID M-601 and Section 26 32 15.00 Page 15 - Paragraph 2.1.1 Engine-Generator Parameter Schedule and Page 28 Paragraph 2.8 Cooling system. RESPONSE: The Radiators must be equipped with two circuits with one for aftercooler and the other with Jacket water as noted on drawing M-706. The temperature requirements are different for each. Please use a Radiator with two circuits with temperature control to conform to the manufacturer’s recommended inlet water temperatures as noted in the plans and specifications (revised)
22. 13 27 54 Section 2.12.2 refers to SELDS details in the drawing package. For example, “See the SHIELDED FLOOR SELDS TESTING detail on the HEMP Standard Details drawings.” We cannot find the concrete embedded SELDS system details in the drawing package that are refereed to in the specification. Would the Government please identify the applicable drawing number and detail designation? RESPONSE: HEMP shield floor details on S-501 have been updated to show general placement of SELDS testing PVC conduits. Shop drawings showing the HEMP shield floor plate joints and location of the PVC conduits must be submitted for approval. As such, HEMP shield floor notes have been updated on S-101, S-410, S-420 to include this requirement. Also, refer to drawing X-151 for Shielded Floor SELDS Testing Detail.
23. With reference to Package 2: Section 26 32 15.00 2.10.1 Flexible Sections and Expansion Joints:
"Provide a flexible section at each engine and a expansion joint at each muffler" Generator and Supporting equipment Typical Building Section Sheet M-301 does not indicate any exhaust gas silencer.
We have not found any information for noise abatement requirements in the Tender material. Please clarify noise limits - if any, for the J - Plant, new permanent plant as well as temporary. RESPONSE:
Contractor to install silencer and expansion joints and associated structural support in accordance with revised drawings S-001, M-301 and M-406. Please follow manufacturer’s instructions and conform to the performance criteria as directed by the generator manufacturer for back pressure limitations.
24. With reference to Package 2: Section 26 11 14.00 10 2.2.6 SPS Features: "c. for redundancy, all mater control automation functions shall be capable of being executed from any of multiple distributed processor’s…" We assume “mater” to be replaced with master? Will it be accepted if the offered solution will be with redundant controllers for each engine, but another redundant controller cannot take over execution of another engine? RESPONSE: Dwg E-607 SWITCHGEAR NETWORK DIA. SHOWS ONLY TWO hot TIE MASTER PLC’S, the reference in the specification to multiple is incorrect.
Refer to revised spec 26 11 14.00 par 2.2.6 (c).
25. With reference to document: Drawings AD100+EP104+EP105. Removal & demolition works bldg. 4012.
In addition to the removal of 5kV feeders (as ED601 note 3), we have only identified other removal / demolition works to be done in Bldg. 4012 specified on drawing AD100 (detail D8), EP104 (keynote2) + EP105 (keynote2). Sequence of construction works (note 1C dwg. E-003) specify a survey to be done during execution, however, works need to be priced now. Please clarify that above listed removal/demolition work at bldg. 4012, is limited to the scope to be priced within the offer. If not, please define further works to be included. RESPONSE: Refer to revised Dwg EP105, Key Note 2 calls for removal of out of service wiring and equipment, E-504 Detail E2 and Dwg EP104 Key Note 4.
Sufficient information is provided to determine extent of work.
26. With reference to document: Drawings EP105, Keynote 2. Keynote referring to “Detail? DWG E-504”.
We have only found the single line diagram on drawing E-504 – please clarify if this reference is an error or specify which detail shall be considered. RESPONSE: Please refer to revised drawing EP-105 as issued in this amendment. Note should refer to detail E2.
27. With reference to document: Outline drawing FX100. Is there documentation of signal and supply cables from the surrounding buildings, e.g., 4090, 4091, 4020, etc. Which can ensure safety when dismantling cables and Cable routes in building 4016, so that there are no cables running through building 4016, which will be removed during a total dismantling of this building? RESPONSE: FX100 is a site plan showing the water tank supply, fire hydrants, and fire water line serving B4016 and B4013. The sheet is not supposed to show any electrical or fire alarm information. We address fire alarm cabling in the RFI-28 response. Telecom cables that were going through or serving B4016 are being pulled back and rerouted prior to demolition. This is indicated on the Demolition Topology diagram T-601.
28. With reference to document: Electrical demolition ED101. Point 5 - To ensure the necessary operation of vital equipment is maintained with Power and signal, it is a necessity to have drawings/documentation of these equipment. Point 6 - Must the existing fire alarm system be kept intact throughout the construction period and must the fire detectors be installed on temporary structures during the rebuild until a new fire alarm system is established, tested, and approved. RESPONSE: The plant dates from the 1950’s and existing documents are lacking; Contractor is responsible to work with site operators to ensure any systems to be maintained are to continue in operation. Refer to contract drawing FD102 Notes #1-4 and FA101 Note #9, regarding direction on Point 6
29. With reference to document: ELECTRICAL ABBREVIATIONS AND GENERAL NOTES at Drawing E-002.
Can the entire control room be dismantled without following up and recording cables and their connections? How do we get an overview of equipment that needs to be supplied temporarily, since there is no equipment/cable list of these components? Should this drawing be labeled ED-002 instead of E- 002? RESPONSE: Demo of the existing generator system will not begin until the Temporary Power system is operational, ALL existing J Plant generator interconnecting control cables, wiring and equipment is to be removed. The cut over of the 5 KV cables area are well documented.
Refer to Dwgs E-601, E-611, E-612 & E-613. Dwg E-002 is correctly labeled.
30. With reference to document: Drawing EP-107, E611 etc.: Design criteria for temporary power system Please clarify whether it will be accepted if the Contractor provide more than 4 generating units for the temporary power system, provided that the capacity of min. 8.25 MVA and N+1 is met? RESPONSE:
Concur, The Contractor may choose any selection as longs as the total 8.25 MVA capacity with N+1 is met.
31. With reference to document: section 26 23 00.00 40 page 6, note 2.2.1.1. Enclosure, we need to “Ensure that the switchboard, switchgear enclosure is NEMA ICS 6 Type 1 fabricated entirely of 12-gauge ASTM A240/A240M type 04 or 304L stainless-steel. Is stainless steel necessary? Does that also apply for the MV switchgear, the panelboards, the splice boxes etc.? RESPONSE: Specifications have been corrected to cold rolled sheet steel. Refer to revised spec 26 23 00.00 40.
32. With reference to document: Drawing E-603. Placement of existing splice-boxes in passageway B4000.
Exactly where are they placed? That passageway is about 1000m long! RESPONSE: As the note states it is “Existing”. It is shown on Dwg EP-105 right of col 11-B in the passageway. See also
ES102.
33. With reference to document: Drawing E-702 electrical feeder schedule. It appears that most feeders are wires in steel pipes, also the MV feeders. (a) Are detailed drawings available for above? (b) Like sections and similar and maybe as well in a 3D model? (c) Will it be accepted to use armored cables instead of wires in steel pipes, inside the HEMP shield? (d) Will it be accepted to use armored and shielded cables instead of wires in steel pipes, outside HEMP shield? (e) If above listed cables are NOT accepted, please provide detailed specifications for anticipated cables/wires and conduits as specified in E-702.
RESPONSE: (a) The documents are diagrammatic and actual routing is responsibility of Contractor. (b) CADD files will be available upon construction contract award. (c) All cables are specified in Division 26 sections. E-702 5 KV MV Feeder Schedule, identifies which feeders are to be HEMP conduits. (d) Type MC cable would be accepted in noncritical support areas provided installed in accordance with the specifications, (e) please refer to division 26 of specifications for cable/wire specifications.
34. With reference to document: Quality for drinking water, Drawings P-501. Information required. Is it correct understood that there is no treatment of portable water even that it is coming from a storage tank even that is used for drinking water? RESPONSE: Storage tank is a potable water source and does not require any additional treatment prior to be used as drinking water.
35. With reference to document: Electrical trap primer, Drawings P-502. 15 mm trap primer lines are not shown on the plan drawings. Please indicate how many meters of pipe are used for that purpose? It seems that the trap primer is in mech room 110 on first floor. But there is a floor drain at second floor and trap primers shall normally be installed 12” above level of device it serves. Can you please provide us with a product that can be installed below the floor? RESPONSE: Per drawings, there are three TP-1 electronic trap primers (installation height should be around 1meter above the floor) on the 1st floor (one in Mech/Plumb 119, two in Open Area 104), these serve the floor drains in Mech/Plumb 119, Fire Pump 102, Bathrooms 127 & 129, and in Open Area 104. The floor drain in Unisex Toilet 203 is served by TP-2, a pressure drop activated trap primer on the supply to break sink SK-2 (installed at least 0.3m or 12” above the floor). Approximate total length of 15mm trap primer piping is 125m. All floor drains within the HEMP enclosure will utilize ASSE 1072 trap guards for trap protection.
36. With reference to document: Flue stack for hot water boilers, Drawings M-502. We can’t find any details showing how to support the hot water flue stack to the building. Please provide information about how to connect to building structures. RESPONSE: Contract drawings do not show pipe or flue supports and it is up to the contractor’s engineer to propose how the supports are managed through shop drawing submittals for approval. The contractor is responsible for supporting the boiler flue stack and bracing for any seismic loads.
37. With reference to document: Hot water system diagram, Drawings M-701, M-805. On control drawing M- 805 is shown a flow meter on the hot water system. But on flow diagram M-701 it is not shown. Please clarify which drawing is correct? On control drawing M-805 is shown a differential pressure drop sensor on the hot water system, but on flow diagram M-701 it is not shown. Please clarify which drawing is correct. RESPONSE: For the controls associated with the heating hot water system, all control and field devices including flow meter and differential pressure sensor shown on M-805 must be provided.
38. 26 28 01.00 10, par 1.2 Considering the required contract/subcontracting actions to begin the power study, review of the existing Government provided Easy Power Software files, the LOA and travel arrangements (typically 14 to 30 days), the data collection, and the report generation, 60 days appears to be insufficient time to perform this task. Would the Government consider revising the report due date to within 120 days of award of contract? RESPONSE: Additional time is given, please refer to revised spec section paragraph.
39. 08 34 49.00 20, Would the Government consider brass knife edge HEMP doors to allow for increased supplier options, competition, and cost savings? RESPONSE: Yes, knife-edge HEMP doors that meet the shielding requirements and other non-shielding requirements would be acceptable.
SECTION 00 45 00 - REPRESENTATIONS AND CERTIFICATIONS
The following have been deleted:
52.225-11 Buy American--Construction Materials Under Trade
Agreements
DEC 2022
52.225-12 Notice of Buy American Requirement - Construction Materials Under Trade Agreements
MAY 2014
SECTION 00 72 00 - GENERAL CONDITIONS
The following have been deleted:
52.225-10 Notice of Buy American Requirement--Construction
Materials
MAY 2014
(End of Summary of Changes)