W912DS21R0003 Amendment 00002.pdf

PDF 553 KB Posted

Attached to
Cullum Hall Repair Building 605
Solicitation number
W912DS21R0003
Issued by

About this file

This amendment modifies a solicitation for repair work at Building 605 Cullum Hall at West Point, New York. The Army Corps of Engineers seeks to repair Building 605 located at 605 Cullum Road in West Point. The amendment includes an additional site visit scheduled for April 20, 2021 and May 4, 2021 at 10:00 AM EST each day. All attendees must follow current COVID protocols, require visitor passes, and limit attendance as needed. Offerors must acknowledge receipt of this amendment by the revised deadline.

View the file

Other files

File Type Posted
W912DS21R0003 Amendment 00009.pdf PDF
W912DS21R0003 Amendment 00008.pdf PDF
W912DS21R0003 Amendment 00007.pdf PDF
CULLUM_Amendment 7_Drawings Combined.pdf PDF
CULLUM_Amendment 7_Specifications Combined.pdf PDF
CULLUM_Amendment 6_Specs Combined.pdf PDF
CULLUM_Amendment 6_Drawings Combined.pdf PDF
W912DS21R0003 Amendment 00006.pdf PDF
W912DS21R0003 Amendment 00005.pdf PDF
Cullum Hall Site Visit Sign In Roster 20APR2021.pdf PDF
Cullum Site Visit Sign In Roster 4 May 2021.pdf PDF
W912DS21R0003 Amendment 00004.pdf PDF
Amendment 3_Cullum_C-502.pdf PDF
Amendment 3 Demolition Sheets.pdf PDF
Amendment 3 _ Cullum H-1B2_HAZMAT_PLAN_BASEMENT_LEVEL_2.pdf PDF
W912DS21R0003 Amendment 00003.pdf PDF
CULLUM_Amendment 3_Specifications Combined.pdf PDF
CULLUM_Amendment 3_Drawings Combined.pdf PDF
CULLUM_Amendment 1_Drawings Combined.pdf PDF
W912DS21R0003 Amendment 00001.pdf PDF
CULLUM_Amendment 1_Specifications Combined.pdf PDF
CULLUM RTA SPECS - VOLUME 1.pdf PDF
CULLUM RTA DRAWINGS - VOLUME 1.pdf PDF
CULLUM RTA DRAWINGS - VOLUME 3.pdf PDF
CULLUM RTA DRAWINGS - VOLUME 2.pdf PDF
CULLUM RTA SPECS - VOLUME 2.pdf PDF
JA -Milford Granite.pdf PDF
JA -E Shark 200 Meters.pdf PDF
JA-Distributed Antenna System C Squared systems.pdf PDF
JA- Hirsch Card Access system.pdf PDF
W912DS21R0003.pdf PDF
JA -Monaco Cullum.pdf PDF
JA -Best Hardware Lock Cylinders and Cores.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to:

1. include an additional site visit.

NOTE: Off eror must acknow ledge receipt of this amendment by the date specif ied in the proposal (or as amended) by one of the follow ing methods: In the space provided on SF1442, by separate letter, or by signing block 15 below . FAILURE TO ACKNOWLEDGE AMENDMENTS BY THE DATE AND TIME SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER IN ACCORDANCE WITH THE SUBMISSION, MODIFICATION, REVISION, AND WITHDRAWAL OF PROPOSALS (FAR 15.208).

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Apr-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DS21R0003

X 9B. DATED (SEE ITEM 11)

13-Apr-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Apr-2021

CODE

US ARMY CORPS OF ENGINEERS, NEW YORK

26 FEDERAL PLAZA, RM 16-300

NEW YORK NY 10278-0090

W912DS 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912DS21R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

The following have been modified:

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- 20 April 2021 at 10:00AM EST. and 04 May 2021 at 10:00AM EST.

(c) Participants will meet in front of -- 605 Cullum Road West Point, NY 10996

All attendees will need to follow current COVID protocols.

Contractors will need to process through the visitor’s center.

All attendees will be required to wear masks.

Contractor’s should also limit the number of attendees to the extent possible.

NOTE: Please arrive early enough and proceed to the Visitor Center to receive background check and be issued a temporary one day visitor pass.

(End of provision)

(End of Summary of Changes)